Original source · versioned page text
Stormwater management plan 20220156 9 Kauri St SWMP
Plans and drawings: the text below has words only, no drawings.
Original PDF page 23, section 1. The text section number identifies this passage in the reader.
EARTHWORKS NOTES
EW LEGEND
Lower_value Upper_value Colour 1. FOR GENERAL NOTES REFER DWG C01, WHICH IS TO BE REQUESTED AND VIEWED PRIOR TO COMMENCEMENT OF
CONSTRUCTION IF NOT SUPPLIED.
-3.0 to -2.9 m
2. IT IS RECOMMENDED THAT THE GEOTECHNICAL CONSULTANT BE CONTACTED TO CONFIRM THE SOIL CONDITIONS PRIOR TO
EARTHWORKS COMMENCING.
-2.9 to -2.8 m
3. GRASS AND TOPSOIL SHALL BE STRIPPED TO A MINIMUM DEPTH OF 100MM OVER THE EXTENT OF THE WORKS UNLESS
DIRECTED OTHERWISE AND STOCKPILED WHERE REQUIRED FOR FILL OF LANDSCAPING AREAS. TOPSOIL MATERIALS MUST NOT
-2.8 to -2.7 m
BE USED IN STRUCTURAL FILL.
4. UNSUITABLE NATURAL MATERIALS SUCH AS SATURATED, LOOSE OR SOFT MATERIALS ENCOUNTERED SHOULD BE REMOVED
-2.7 to -2.6 m DURING SUBGRADE PREPARATION FOR BULK EARTHWORKS. ALL UNSUITABLE MATERIAL TO BE REMOVED FROM SITE AT
CONTRACTORS EXPENSE.
-2.6 to -2.5 m
5. COMPACTION OF THE EXPOSED SAND SUBGRADE REQUIRES SUBSTANTIAL VOLUMES OF WATER COMBINED WITH VIBRATORY
-2.5 to -2.4 m COMPACTION EQUIPMENT(E.G VIBRATING PLATE OR MINIMUM 4 TONNE VIBRATING SMOOTH DRUM ROLLER). CARE MUST BE
TAKEN TO ENSURE THERE ARE NO IMPACTS ON SURROUNDING STRUCTURES. MATERIAL TO BE COMPACTED IN ACCORDANCE
-2.4 to -2.3 m WITH GEOTECHNICAL REPORT AND AS1289.
6. TEMPORARY SWALE DRAINS TO BE PROVIDED ALONG CREST AND TOE OF ANY CUTS AND ABOVE FILL BATTERS GRADING
-2.3 to -2.2 m DISCHARGE TO A CONTROL POINT FOR DISCHARGE TO EXISTING STORMWATER INFRASTRUCTURE IN ROAD RESERVE.
7. A MINIMUM 150MM THICK GRANULAR WORKING PLATFORM MAY BE REQUIRED ON SOIL SUBGRADES ALONG HAUL ROADS AND
-2.2 to -2.1 m LAYDOWN AREAS TO IMPROVE TRAFFICABILITY. SPECIFIC PLATFORM DESIGN WOULD BE REQUIRED PRIOR TO MOBILISATION
AND TRAFFICKING OF ANY HEAVY MOBILE PLANT ON THE SITE.
-2.1 to -2.0 m 8. IMPORTED GENERAL FILL MATERIAL SHALL BE SUPPLIED AND COMPACTED WHERE UNSUITABLE NATURAL MATERIALS ARE
LOCATED AND AS OTHERWISE NECESSARY TO OBTAIN SUBGRADE/PLATFORM LEVEL. IMPORTED GENERAL FILL MATERIAL
-2.0 to -1.9 m SHALL BE CLEAN GRADED MATERIAL FREE OF ORGANIC MATTER AND STONES, WITH MAXIMUM PARTICLE SIZE OF 100mm AND
CAPABLE OF BEING COMPACTED INTO COHERENT FILLING TO THE SPECIFIED STANDARD. THE MATERIAL SHALL HAVE A
-1.9 to -1.8 m MAXIMUM PLASTICITY INDEX OF 15%, A SHRINK-SWELL INDEX OF LESS THAN OR EQUAL TO 1% AND A MINIMUM C.B.R. OF 10%.
9. ALL EARTHWORKS TO BE CARRIED OUT AT +/- 2% OPTIMUM MOISTURE CONTENT FOR STANDARD COMPACTION.
28.00
-1.8 to -1.7 m
10. ANY PROPOSED RETAINING WALL WORKS MUST BE WHOLLY WITHIN THE PROPERTY BOUNDARY OF THE SUBJECT SITE,
m
-1.7 to -1.6 m
INCLUDING REAR OF RETAINING WALL DRAINAGE INFRASTRUCTURE FOR RETAINING WALLS IN CUT. RETAINING WALLS ARE TO
BE PREPARED IN ACCORDANCE WITH STRUCTURAL ENGINEERS SPECIFICATIONS, AND IN CONFORMANCE WITH CONSTRUCTION
-1.6 to -1.5 m
REQUIREMENTS OF GEOTECHNICAL REPORT.
11. REFER ARCHITECT/LANDSCAPE ARCHITECT DRAWINGS FOR CONFIRMATION OF RETAINING WALL COLOUR AND FINISH.
27.99
-1.5 to -1.4 m 12. ALL EARTHWORKS OPERATIONS SHALL BE CARRIED OUT WITH 'LEVEL 1' SOIL ENGINEERING SUPERVISION IN ACCORDANCE
WITH APPENDIX B OF AS 3798. THE NOMINATED GEOTECHNICAL TESTING AUTHORITY SHALL PROVIDE CERTIFICATION THAT ALL
-1.4 to -1.3 m
m GENERAL EARTHWORKS OPERATIONS HAVE BEEN CARRIED OUT IN ACCORDANCE WITH THE DRAWINGS AND SPECIFICATIONS
AND THE CONTROLLED FILL IS SUITABLE FOR PURPOSE TO THE REQUIRED BEARING CAPACITY UNDER THE
-1.3 to -1.2 m PLATFORM/STRUCTURES AS SPECIFIED BY THE GEOTECHNICAL REPORT.
13. ALL EARTHWORKS FILL AND EXCAVATED AREAS SHALL BE COMPACTED TO 98% STANDARD MAXIMUM DRY DENSITY OR A DRY
0
27.99 DENSITY INDEX OF AT LEAST 75% IN ACCORDANCE WITH THE GEOTECHNICAL REPORT IN LAYERS OF 250MM LOOSE THICKNESS
-1.2 to -1.1 m
.
m
0
(PRIOR TO COMPACTION).
-1.1 to -1.0 m
0
14. COMPACTION TESTING TO BE CARRIED OUT AT A MINIMUM OF TWO TESTS PER VERTICAL LIFT WHERE STRUCTURAL FILL
HEIGHTS EXCEED 300MM IN ACCORDANCE WITH AS3798. CONTRACTOR TO UNDERTAKE ALL EARTHWORKS TESTING IN
m
-1.0 to -0.9 m ACCORDANCE WITH GEOTECHNICAL ENGINEER AND LOCAL AUTHORITY REQUIREMENTS.
15. FINISHED SURFACES TO ALL DISTURBED AREAS ARE TO BE TREATED IN ACCORDANCE WITH LANDSCAPE DRAWINGS.
-0.9 to -0.8 m
16. ALL NEW WORKS TO MATCH NEATLY INTO EXISTING LEVELS.
-0.8 to -0.7 m 17. ALL WORKS TO BE CONSTRUCTED IN ACCORDANCE WITH APPROVED MANAGEMENT PLANS.
18. CONTRACTOR TO ENSURE SUITABLE EROSION CONTROL MEASURES ARE INSTALLED INCLUDING BUT NOT LIMITED TO SHAKE
-0.7 to -0.6 m DOWNS, SILT FENCE ETC IN ACCORDANCE WITH EROSION AND SEDIMENT CONTROL PLAN.
19. ADEQUATE SAFETY FENCING/BARRIERS TO BE APPLIED TO ALL BATTERS OR RETAINING WALLS (TEMPORARY OR PERMANENT)
-0.6 to -0.5 m AS PER RELEVANT AUSTRALIAN STANDARDS AND LEGISLATION.
20. DUST CONTROL MEASURES ARE TO INCLUDE SPRAYING WATER ON UNPAVED ROADS, ACCESS TRACKS AND STOCKPILES AT A
-0.5 to -0.4 m SUFFICIENT LEVEL TO SUPPRESS DUST GENERATION. ADDITIONALLY CONTRACTORS ARE TO COVER OR ENCLOSE STOCKPILES
WHERE REASONABLY PRACTICAL TO RESTRICT DUST MOVEMENT.
-0.4 to -0.3 m
0.00m 21. PRIOR TO THE CONTRACTOR COMMENCING ANY WORKS DETAILED ON THIS DRAWING, THE CONTRACTOR IS TO NOTIFY RECOR
76
AND RECEIVE WRITTEN CONFIRMATION THAT WORKS CAN COMMENCE.
-0.3 to -0.2 m
22. ALL EXCAVATIONS ARE TO BE CONDUCTED IN ACCORDANCE WITH THE REQUIREMENTS OF THE GEOTECHNICAL ENGINEER.
.
TEMPORARY UNSURCHARGED CUTS IN LOOSE TO VERY LOOSE SAND TO BE FORMED AT 1V:2H, AND IN MEDIUM DENSE SAND AT
3
-0.2 to -0.1 m
1V:1H FOR BATTERS UP TO 3M IN HEIGHT. DEEPER CUTS ARE TO BE ASSESSED BY THE GEOTECHNICAL ENGINEER. PERMANENT
4
-0.1 to 0.0 m
0.00m CUT AND FILL BATTERS TO BE A MAXIMUM 1V:2.5H.
m
23. EARTHWORKS FILL BATTERS TO BE MAXIMUM OF 1M IN HEIGHT, OR OTHERWISE RETAINED.
0.0 to 0.1 m 24. WHERE THE ABOVE TEMPORARY BATTER SLOPES CAN NOT BE ACHIEVED, TEMPORARY SHORING WILL BE REQUIRED UNDER
THE ADVICE OF A SPECIALIST SHORING CONTRACTOR.
0.1 to 0.2 m 25. EXCAVATIONS IN PROXIMITY TO EXISTING STRUCTURES WILL REQUIRE SPECIFIC DESIGN TO PREVENT UNDERMINING WHICH
0.00m
SHOULD BE CARRIED OUT BY A SUITABLY QUALIFIED AND EXPERIENCED RPEQ STRUCTURAL ENGINEER.
0.2 to 0.3 m
26. CONTRACTOR'S RPEQ GEOTECHNICAL ENGINEER IS TO CONFIRM THAT ANY CONSTRUCTED CUT/FILL BATTERS AND RETAINING
STRUCTURES ON THE SITE HAVE ACHIEVED ADEQUATE STABILITY WITH A LONG-TERM FACTOR OF SAFETY AGAINST
0.3 to 0.4 m
GEOTECHNICAL FAILURES TO THEIR SATISFACTION.
27. EARTHWORKS LEVELS SHOWN ARE NOMINALLY 200MM BELOW FINISHED SURFACE LEVELS INCLUSIVE OF TOPSOIL LAYER.
0.4 to 0.5 m
CONTRACTOR TO CONFIRM FINISHED SURFACE LEVLS BASED ON STRUCTURAL ENGINEERING DRAWINGS FOR BUILDING SLAB
THICKNESSES AND HYDRAULIC DRAWINGS FOR SUB-FLOOR DRAINAGE TO CONFIRM EARTHWORKS SURFACE LEVEL.
0.5 to 0.6 m
28. ANY PRELOADING REQUIRED IS TO OCCUR IN ACCORDANCE WITH THE GEOTECHNICAL ENGINEERS REQUIREMENTS.
0.6 to 0.7 m CONTRACTOR TO ALLOW FOR THE IMPORT AND REMOVAL OF ALL NECESSARY MATERIAL TO UNDERTAKE THE PRELOADING
OPERATIONS.
0.7 to 0.8 m 29. REFER ARCHITECTURAL DRAWINGS FOR BUILDING SETOUT.
0.8 to 0.9 m
0.9 to 1.0 m
1.0 to 1.1 m
1.1 to 1.2 m
1.2 to 1.3 m
Total cut -1250.209
1.3 to 1.4 m Total fill 275.75
Total balance -974.46
1.4 to 1.5 m ie excess of cut over fill 974.46
CLIENT DETAILS: PROJECT ADDRESS: APPROVED BY: PROJECT NAME:
PROPOSED RESIDENTIAL DEVELOPMENT
SUNSHINE GROVE PTY LTD TITLE: STATUS:
9 KAURI STREET BULK EARTHWORKS MATERIAL CHANGE OF USE
© ABN 89 647 469 707
COOROY, QLD, 4563 JARO BAULEKA LAYOUT PLAN AND
RPEQ: 20693
37 MARY ST
NOOSAVILLE, QLD 4566
A 10/08/22 COMBINED MCU AND OP WORKS ISSUE JAC BRP JB SCALE:
CPEng
OPERATIONAL WORKS
+61 7 5211 1003 REV DATE DESCRIPTION DWN CHK APP
AS INDICATED DATE: 10/08/22
DRAWING NUMBER: PROJECT NUMBER: SHEET REV:
SIZE:
RECORCONSULTING.COM REVISIONS
DO NOT SCALE, IF IN DOUBT ASK
C30 20220156 A1 A
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.