Council archive · source document
Bulk_20160905165259 · MCU13/0215
Attached to the e-mail Operational Works Application – OPW16/0253.
Noosa Council documents
OPW16/0097
5. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not
form part of the assessment manager conditions:
General Advisory Notes
1. It must be noted that a Preliminary Approval for Operational Works does NOT
permit commencement of any works. Further representation to change the
Preliminary Approval to a Development Permit may be made within the appeal
period (normally 20 business days unless the appeal period is suspended). After
the appeal period expires, the Preliminary Approval cannot be changed to a
Development Permit, and a fresh development application for Operational Works
will be required to be made, addressing the requirements of the Preliminary
Approval.
2. A Development Permit for Operational Works has not been issued because
payment of the Performance Bond as described in Condition 5 of the higher order
Development Permit for Material Change of Use, Council Reference
MCU13/0215.03 dated 21 July 2016, has not been made. Council may favourably
consider changing the Preliminary Approval to a Development Permit via the
Negotiated Decision process, if the applicant has made payment of the
Performance Bond.
6. PROPERTY NOTES
Not Applicable
7. PRELIMINARY APPROVAL OVERRIDING PLANNING SCHEME
Not Applicable
8. FURTHER DEVELOPMENT PERMITS REQUIRED
Development Permit for Operational Work Engineering Works - Road Works,
Stormwater, Landscaping, Erosion & Sediment Control
9. SELF ASSESSABLE CODES
Not Applicable
10. SUBMISSIONS
Not Applicable
11. REASONS/GROUNDS FOR APPROVAL
Not Applicable
12. RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions
from the Sustainable Planning Act 2009 is attached.
During the appeal period, you as the applicant may suspend your appeal period and
make written representations to Council about the conditions contained within the
development approval. If Council agrees or agrees in part with the representations, a
“negotiated decision notice” will be issued. Only one “negotiated decision notice” may be
given. Taking this step will defer your appeal period, which will commence again from
the start the day after you receive a “negotiated decision notice”. (Refer to Part 8
Page 2 of 5
Document Set ID: 20155575
Version: 1, Version Date: 05/09/2016 Print Date: 5 September 2016, 4:52 PM
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Bulk_20160905165259.pdfRelated documentApplication case desk ↗
Bulk_20160905165259.pdfRelated documentApplication case desk ↗
Bulk_20160905165259.pdfRelated documentApplication case desk ↗
About this file
- File size
- 183 KB (small file)
- File type
No other editions are linked here.