               78.    Reticulated electricity and telecommunication services must be provided to each lot in
                      accordance with the approval for Operational Works and the standards and requirements of
                      the relevant service provider.
               79.    Unless otherwise stipulated by telecommunications legislation at the time of construction, the
                      development must be provided with all necessary conduits, pits and pipes to accommodate
                      the future connection of optic fibre technology telecommunications.
               80.    Certification must be submitted to Council from all relevant service providers (Energex, NBN
                      and Unitywater which certifies that the development has met the requirements of this
                      Decision Notice and all applicable legislation at the time of construction.
               81.    Certification must be submitted to Council from a qualified person* which certifies that the
                      development has been constructed in accordance with the landscape conditions of this
                      Decision Notice.
                      *(Refer to Advisory Note)
               5.     REFERENCE DOCUMENTS

                Plan No.                Rev.   Plan/Document Name                                  Date

                22393-001               Rev0 Geotechnical Investigation and Slope Stability 26/10/2022
                                             Assessment, prepared by Tectonic Geotechnical &
                                             Environmental Engineers

               6.     REFERRAL AGENCIES

               The referral agencies applicable to this application are:

                Referral Status        Referral Agency and Referral Trigger                Response
                                       Address
                Concurrence            SARA at DILGP SARA        Schedule 10, Part 4,      The agency provided its
                                       at DILGP Via MyDAS2       Division 3, Table 1       response on 10
                                       at https://prod2.dev-     (Planning Regulation      January 2023
                                       assess.qld.gov.au/suite   2017): Premises           (Reference No. 2212-
                                       / (for assistance,        contaminated because of   32310 SRA). A copy of
                                       contact DILGP at 5352     unexploded ordnance.      the response is
                                       9701 or                                             attached.
                                       email:[email protected]

               7.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
                      Infrastructure Charges
               1.     All developments and/or changes to existing developments may require payment of
                      “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
                      made pursuant to the planning legislation and regulations current at the time of issue. For
                      further       information,     please        refer to https://www.noosa.qld.gov.au/planning-
                      development/development-tools-guidelines/infrastructure-charges




                                                                                                     Page 22 of 25

Document Set ID: 22435587
Version: 8, Version Date: 15/06/2023

Used in these records

About this file

File size
3.6 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Delegated Report - Code - Planning MCU22 0197 [As Published].pdf · 3.6 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.