07/0387 - Information Request - Op Works 26 Orealla Crescent [As Published] · 142007.387
Colleen Keegan, 07 5449 5183
Email: [email protected]
Application Ref: 2007/387
30 March 2007
Ausmar Homes
PO Box 418
COOROY QLD 4563
Dear Sir/Madam,
Re: Application for a Development Permit for Operational Works - Landscaping,
Carparking & Access, Frontage Works, Stormwater & Drainage and Fill
situated at 26 Orealla Crescent Sunrise Beach described as Lot 161 on
RP220508
I refer to the above application 07/0387 for a Operational Works - Landscaping,
Carparking & Access, Frontage Works, Stormwater & Drainage and Fill and wish to
advise that following preliminary examination of the plans, the following information is
required to be submitted:-
Land Use
1. An amended Landscaping Layout Plan in accordance with Condition 3 of
(04/5045) Material Change of Use – Duplex Dwelling and detailing the following:-
1.1. Compliance with Council’s Policy on Landscaping Guidelines; and
1.2. A landscape plan with a plant schedule that clearly indicates the location
and size of each species to be planted on the site. It is noted that the
current plan does not clearly identify the location and size of the species of
plants on site.
1.3. Compliance with Condition 4 of the corresponding Material Change of Use
04/5045 illustrating the location and species of the 2 X 100L native canopy
trees within the front setback; and
1.4. Compliance with Condition 6 of the corresponding Material Change of Use
illustrating the location of fencing on the site and the landscaping to be
provided on the area of land between the fence and the front property
boundary; and
1.5. Compliance with Condition 7 illustrating the densely vegetated buffer to be
provided along the rear property boundary; and
1.6. Compliance with Condition 8 by clearly illustrating the height and location of
the required fencing on the site; and
Award Winner - Australian Clean Beach
Challenge 2004 Litter Prevention
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 3 pages
Page 2
1.7. Details of any existing trees on the site to be retained or removed and
within road reserve that are to be retained in accordance with Condition 9
of the corresponding Material Change of Use.
2. Amended plans that demonstrate:-
2.1. Compliance with Land Use Condition 5 with regard to further articulation to
be provided along the northern, southern, and eastern elevations of the
duplex; and
2.2. Compliance with Condition 10 by clearly illustrating the proposed colour
scheme and materials and finishes for the development.
2.3. Reduction in the size of the decks in accordance with Condition 11 to
ensure that a 0.5 metre landscaped area is provided to the adjoining
properties.
Land Development
Stormwater
3. Please revise the design plan Drawing No. 16115-OW-1A prepare by SCG
Consulting Engineers:
3.1. Each lot (Lots 1 & 2 on SP189331) are to be separate systems,
3.2. The revised design is to include that each system is to connected within the
site and have a single outlet point in the kerb and channel,
3.3. Indicate on the plans the levels of the proposed drainage system and the
finished levels of the floors and landscaping.
3.4. Indicate on the design plans the calculated pre-development and post-
development stormwater runoff amounts for the site and the proposed
outlet flow rate at the kerb and channel in accordance with Condition 37 of
the Decision Notice File No. 2004/5103 dated 1 August 2005, and
3.5. Please provide additional detail on the proposed drainage system for the
driveway and carparking area in accordance with Condition 39, 40, 41 and
42 of the Decision Notice File No. 2004/5045 dated 1 August 2005.
Access/Carparking
4. Please provide a revised design plan for the access driveway that is in
accordance with Conditions 23 and 24 of the Decision Notice File No. 2004/5045
dated 1 August 2005 and the Noosa Plan’s Driveways and Carparking Code.
5. Please provide a Longitudinal Section of the access driveway. The longitudinal
section shall extend from the centreline of the existing formation to the carparking
area and shall include a section of for the pedestrian footpath 1.5m wide with a
maximum crossfall of 2.5% and be in accordance with and the Noosa Plan’s
Driveways and Carparking Code..
6. Please ensure that all relevant plans, landscaping, drainage etc, is in accordance
with the access driveway design plans.
Award Winner - Australian Clean Beach
Challenge 2004 Litter Prevention
Page 3
7. Indicate on the plans the available headroom at the entrance to the carparking
area and at the garage doors.
8. Indicate on the plans the location and type of the required signposting in
accordance with Condition 29 of the Decision Notice File No. 2004/5045 dated 1
August 2005.
Frontage Works
9. Please provide additional detail, width, materials, levels etc of the required
footpath across the frontage of the site.
Site Works
10. It is noted that the submitted plan, drawing No. 16115-OW-1A prepare by SCG
Consulting Engineers, indicates that sheet piling and other works are to take
place on the adjoining properties. Please revise the drawing to indicate that all
works are to be wholly contained within the subject site. Should any temporary
structures be placed on and/or works need to be undertaken on the adjoining
properties a letter of approval signed by the adjoining property owners shall be
submitted to Council with the revised plans.
11. Please provide comment from a suitably qualified engineer regarding the impacts
of the proposed site works and the construction of the proposed pools will have
on the Council sewer main located on the adjoining properties at the rear of the
site. Should this comment indicate that the proposed works would have an
adverse affect on the sewer main the proposed works shall be modified to ensure
that no adverse affects will occur to the sewer main.
Please provide four (4) copies of all information that you are providing. In addition, it
would assist Council if you could also provide an electronic copy of your response.
Pursuant to the conditions of the Development Permit for a Material Change of Use
please note that all bonds and contributions are required to be paid prior to the issue of
the Operational Works approval.
Please be aware that under Section 3.2.12 of the Integrated Planning Act, the applicant
is to respond to any information request within 12 months of the request or otherwise,
the application lapses.
Under the provisions of the Integrated Planning Act 1997, you as the applicant, have
three options available in response to this Information Request. You may give the
assessment manager (in this instance Council) and each referral agency (if any):-
1. all of the information requested; or
2. part of the information requested together with a letter asking the assessment
manager and each referral agency to proceed with the assessment of the
application; or
3. a letter:-
3.1. stating that you do not intend to supply any of the information requested;
and
3.2. asking the assessment manager and each referral agency to proceed with
the assessment of the application.
Award Winner - Australian Clean Beach
Challenge 2004 Litter Prevention
Page 4
The above information is required to be submitted, prior to assessment of the
application. If any further matters arise as part of assessment of this application, you
will be advised accordingly.
Should you have any further queries in relation to the above, please do not hesitate to
contact a on the above number.
Yours faithfully,
Colleen Keegan
PLANNING OFFICER
Award Winner - Australian Clean Beach
Challenge 2004 Litter Prevention
Used in these records
07/0387 - Information Request - Op Works 26 Orealla Crescent [As Published]Related documentApplication case desk ↗
About this file
- File size
- 13 KB (small file)
- File type
No other editions are linked here.