SUPERSEDED Decision Notice - 010.2006.00000159.001 [As Published] · 142006.159

of 10

Text shows just the words. Original shows the document exactly as it was published.

NOOSA COUNCIL IDAS Development Application Decision Notice                                                  4 of 10


             0619-08                 dated 23 January 2007      by Callaghan & Toth

             0411-DD01C              dated August 2005          by Middap & Ditchfield

             M1757-03C               dated 9 November 2006      by Jones Flint & Pike

             25908-C1C               dated 16 March 2006        by Riemac

             25908-C12B              dated 16 March 2006        by Riemac

             1451-0-1A               dated 27 April 2006        by Construction Hydraulics

             1451-0-2A               dated 27 April 2006        by Construction Hydraulics

             or as modified herein

14.   Roof and surface runoff connection to Council’s drainage system shall be as shown on drawing No. 1451-
      0-2A dated 27 April 2006 By Construction Hydraulics.

15.   A footpath 2.0 metres wide shall be constructed across the full Gympie Terrace frontage of the
      development and footpath 1.5 metres wide shall be constructed across the Mill Street frontage of the
      development. The footpaths shall have a slip resistant surface. The alignment, of which, shall be
      determined on site with Council’s Construction Technical Officer. The expansion joints in any
      bikeway/footpath shall be “sawcut” not trowel jointed.

16.   The total required pavement thickness shall be based on the Department of Transport’s Pavement Design
      Manual using soaked CBR tests of the subgrade.

      The design pavement thickness, together with CBR test results shall be submitted to Council’s Manager -
      Land Development for approval prior to placement of pavement material.

17.   Suitable sediment control devices ("in pit” pollution control devices) shall be temporarily installed into the
      first existing external downstream stormwater structure.
      These devices are to be checked and cleaned on a regular basis and specifically after each rain event.
      These devices are to remain in place during the civil works and construction phases of the development.
      The location and type of device to be installed shall be established at the “pre start” meeting with
      Council’s Construction Technical Officer and shall be installed prior to the commencement of any works.
18.   Council’s Construction Technical Officer, Tony Doughty (ph 0410 512 505), shall be given seven (7) days’
      notice of intention to commence works to arrange a “pre start” meeting regarding the civil works.

19.   The principal contractor must have all the appropriate insurance and public liability documentation to carry
      out the works. The principal contractor is also responsible to ensure that any sub contractors also have
      the appropriate insurance and public liability documentation.

20.   Prior to the “pre start” meeting, the principal contractor must be provided with a copy of Council’s signed
      approved drawings and conditions by the applicant.

21.   The Consulting Engineers for the project shall be currently Registered Professional Engineers of
      Queensland (RPEQ). The consulting engineers are responsible for arranging all inspections, with
      Council’s Construction Technical Officer or nominated staff. Council’s Construction Technical Officer shall
      provide an inspection form for signing off by the Engineer at appropriate stages of construction, during on-
      site meetings. Construction Technical Officer will also sign the form at each stage when conditions
      required have been satisfied. The works will be accepted “On Maintenance” after this form, signed by the
      inspector for each stage is complete, together with a letter from the Engineer requesting that the works go
      “On Maintenance”.

22.   Prior to works commencing, Council is to be advised of the Engineer (RPEQ) supervising the project.
      (This person will be the contact for the project).

23.   Council standards shall apply to these works unless otherwise modified herein.




AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@ac07b383\@[email protected]

Used in these records

About this file

File size
43 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

SUPERSEDED Decision Notice - 010.2006.00000159.001 [As Published].pdf · 43 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.