SUPERSEDED Change to an Existing Approval - 010.2001.00210331.005 [As Published] · 132001.210331.5

of 11

Text shows just the words. Original shows the document exactly as it was published.

                                               Officer:          Tracy Jones
                                               Direct Telephone: (07) 5449 5228
                                               Response Address: Locked Bag 72
                                                                 Sunshine Coast Mail Centre QLD 4560
                                               Email:            [email protected]
                                               Our Reference:    22441 DA (2001/210331)
                                               Your Reference:
20 October 2009

Peninsular Aviation Pty Ltd
CARE Martoo Consulting Pty Ltd
PO Box 1684
NOOSA HEADS QLD 4567



Dear Sir

                          Change to an Existing Approval
                                    Integrated Planning Act 1997

I refer to your request to make a change to an existing approval. On 15 October 2009 Council
decided your requested changes.
Details of the decision are as follows:

1        APPLICATION DETAILS

    Application No:                22441 DA
    Street address:                10 Park Road, Noosa Heads
    Real property description:     Lot 55 RP 52918
    Planning Scheme:               The Noosa Plan

2        DECISION DETAILS
Council on 12 June 2003 decided to issue the following type of approval: -
     Development Permit for Material Change of Use - Dwelling
In relation to the request to make a change to the existing approval, Council on 13 December 2007
decided to:
A.      Approve the change with amendment to Conditions 1, 10 and 21

B.      Include the following additional Conditions: -

         1. The driveway and garage are not approved in their current location and shall be sited in
            accordance with the Footing Plan prepared for The Robertson Residence

         2. A qualified arborist shall be present on site to supervise works around the root zones of all
            trees required to be retained. Prior to commencing any works safety fences shall be
            installed around the trunks and as much of the root zone as possible to minimise the risk
            of compaction and damage.



                                                                                          Page 1 of 11
Full text of the other 10 pages

Page 2

                                                                            22441 DA (2001/210331)




C.    Refuse to change Condition 36.4 as the use of vibratory equipment is likely to adversely
      impact on the slope and surrounding properties and the geotechnical report has not
      satisfactorily addressed this matter
D.    Issued a Compiled Decision Notice
In relation to the request to make a change to conditions of the Development Approval, Council on
18 April 2008 decided to:
A.    Approve a change to Condition 10
B.    Issue a Decision Notice – Change to an Existing Approval
In relation to the request to make a change to the existing approval and extension to currency period,
Council on 31 March 2009 decided to:
A.    Approve a change to Conditions 1, 6, 10, 16, 26, 27, 35 and 36
B.    Include two additional conditions 3 & 4
C.    Delete Additional Condition 1
D.    Issue a Change to an Existing Approval
In relation to the request to make a change to the existing approval, Council on 15 October 2009
decided to:
A.    Approve a change to Condition 1
B.    Include two additional Conditions 5 & 6
C.    Issue a Change to an Existing Approval
3     RELEVANT PERIOD OF APPROVAL

The relevant period for this Development Approval is identified in the Assessment Manager
conditions.

4     ASSESSMENT MANAGER CONDITIONS
Land Use
1.    Development undertaken in accordance with this approval must generally comply with the
      approved plans of development. The approved plans are titled and numbered: -
       Plan /             Rev.    Plan / Document Name                       Date
       Document No.
       SK-A-02.01         P9      Site Plan – Cecilia Brown Design           3 December 2008
       SK-A-03.01         P10     Garage Plan – Cecilia Brown Design         3 December 2008
       SK-A-03.02         P10     Maid Room Plan – Cecilia Brown             3 December 2008
                                  Design
       WD-A-03.03         P18     Cabana Plan – Cecilia Brown Design         8 May 2008
       SK-A-03.04         P9      Master Bed Plan – Cecilia Brown            3 December 2008
                                  Design
       SK-A-03.05         P9      Roof Plan – Cecilia Brown Design           3 December 2008
       SK-A-04.01         P4      West Elevation – Cecilia Brown Design      3 December 2008
       SK-A-04.02         P4      South Elevation – Cecilia Brown Design     3 December 2008
       SK-A-04.03         P4      North Elevation – Cecilia Brown Design     3 December 2008

                                                                                    Page 2 of 11

Page 3

                                                                           22441 DA (2001/210331)




     SK-A-04.04          P4      East Elevation Master Bed & East           3 December 2008
                                 Elevation Cabana & Maid – Cecilia
                                 Brown Design
     SK-A-05.01          P1      Section A – Cecilia Brown Design           4 December 2008
     SK-A-05.02          P1      Section B – Cecilia Brown Design           4 December 2008

     and as may be amended by these conditions.
2.   The use and all activity on the site, including construction and excavation, is to be carefully
     controlled and interference with vegetation kept to an absolute minimum to ensure that the
     proposed use does not undermine or compromise the Noosa Hill Development Control Plan
     and the Strategic Plan objective of preserving the natural character and appearance of Noosa
     Hill. The approval is to be implemented with this objective as the overriding factor.
3.   All roofing of the structures on site are to be of a non-reflective nature and coloured with
     muted earth tones. All structures are to use colours that integrate with the natural
     environment and be of muted earth tones of browns, greens, ochres, greys etc. A colour
     scheme showing compliance with the above is to be submitted for approval prior to release of
     the development permit for operational works.
4.   The glass provided along the western elevation of the dwelling house is to be angled
     downwards towards the slope of the site so as not to be reflective. Non reflective glass shall
     also be utilised for the development.
5.   The development must be undertaken and operated in a manner that causes no detrimental
     effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
     lighting nuisance or other emissions.
6.   The open space and setback areas are to be landscaped in accordance with Council’s Policy
     on Landscaping Guidelines and a properly prepared landscape plan is to be prepared and
     submitted for approval. The landscaping is to be completed prior to the premises being
     occupied and maintained at all times thereafter. The landscape plan is to clearly indicate:-
     6.1. the retention of vegetation and reinforcement planting of endemic species on the site;
          and
     6.2. the provision of shallow rooted vegetation above the underground garage with species
          provided that are endemic to the Noosa Heads area; and
     6.3. the proposed means of protecting trees to be retained, particularly during the
          construction process.
     Additionally, the applicant is to submit a survey plan of existing vegetation on the site, where
     this plan is to denote vegetation proposed to be removed and that proposed to be retained.
     To this end, as indicated on plan 000705/B dated 16/07/02 and prepared by Ken Hicks &
     Associates, only one substantial tree is to be removed. All trees identified on the plan for
     retention are to be marked and numbered for retention prior to construction on site. The plans
     shall be amended to provide a minimum setback of 300mm from the building for trees 49, 56,
     54 and 53, with no excavations taken in proximity to these trees.
7.   No fencing is permitted to be erected across the Park Road frontage of the site.
8.   Security in the form of a cash bond or trading bank guarantee to the sum of $100000 must be
     submitted, to secure performance of all conditions of this approval, prior to the issue of a
     Development Permit for operational works. The cash bond or trading bank guarantee will be
     returned on performance of the conditions of approval less any costs incurred by Council in
     respect of enforcing performance of this permit.



                                                                                   Page 3 of 11

Page 4

                                                                                   22441 DA (2001/210331)




9.    The requirements of this development approval are to be satisfied, prior to the commencement
      of the use of the premises. Council reserves the right to call upon the bond or guaranteed sum
      referred to in this approval to effect compliance with conditions.
10.   The Development Permit for a material change of use of premises lapses if the use has not
      happened by 13 June 2010, unless an application to extend the currency is approved by
      Council.
11.   The developer must obtain all of the other Development Permits referred to in the Decision
      Notice, prior to obtaining a Development Permit for building works.
Land Development

      Vehicle Access
12.   A vehicular access driveway to serve the site shall be constructed from the Park Road
      frontage of the site with a maximum width of 3.0 metres.
      The driveway shall be designed and constructed to Council’s design standards and to grades
      that prevent vehicles from scraping and/or bottoming. Should any driveways be constructed to
      grades that do not comply with AS2890.1-1993 and AS2890.2-1989, Council will require that
      the driveway be removed and reconstructed to levels that do comply.
13.   All vehicles shall enter and leave the site in a forward direction.
14.   All vehicles shall enter the site via a right turn and exit the site via a left turn.
15.   Council Officers must approve vegetation trimming within the road reserve required to improve
      the sight distance in conjunction with the Development Permit for Operational Works (access).
      However, no trees are to be removed from the road reserve.
      Carparking
16.   Carparking and Turn Table shall be provided within the site as shown on drawing number SK-
      A-03.01 dated 08 May 2008 revision P10 submitted by Cecilia Brown Design and Associate,
      except as modified herein.
17.   A minimum of 2 covered carpark spaces shall be provided on site.
18.   The carparking area shall be designed to comply with the provisions of AS 2890.1-1993 for
      user class 1 except the minimum head clearance (headroom) at any point shall be 2.3m.
      Stormwater Drainage
19.   All stormwater drainage shall be collected on site and discharged to Council’s existing
      drainage structures on the eastern side of Park Road. The design shall incorporate some
      means of reducing the head of the discharge prior to entry to Council’s system. In this regard,
      plans shall be prepared by a Registered Professional Civil Engineer and submitted to Council
      prior to obtaining a Development Permit for Operational Works.
20.   The stormwater drainage system shall be designed in accordance with plan titled, ‘Stormwater
      & Sewerage Details, Robertson Residence’ by whaleycg consulting group.
21.   The site shall be connected to Council’s existing sewerage reticulation systems in Park Road
      and be constructed in accordance with Council’s standards and requirements at no cost to
      Council.
      To ensure Council’s sewer main is accessible for maintenance purposes and is protected from
      risk of damage, no structures requiring a building permit (eg. buildings, retaining walls
      exceeding 1m in height, raised terraces, etc) shall be constructed within the ‘zone of influence’
      or within 1.5m of the centreline of the sewer main, whichever is the greater. As such the
      applicant shall indicate the location of the sewer main and setback distance on the Building
      plans to ensure compliance.

                                                                                              Page 4 of 11

Page 5

                                                                              22441 DA (2001/210331)




      Sewer Mains
22.   The site shall be connected to Council’s existing sewerage reticulation systems in Park Road
      and be constructed in accordance with Council’s standards and requirements at no cost to
      Council.
23.   The sewerage system shall be designed in accordance with plan titled, Stormwater &
      Sewerage Details, Robertson Residence’ by Whaleycg Consulting Group.
      Town Water Supply
24.   The site shall be connected to Council’s existing town water supply in Park Road and be
      constructed in accordance with Council’s standards and requirements at no cost to Council.
25.   Each water connection to the water reticulation system shall extend to the property boundary
      and be metered.
      Geotechnical Issues/Construction
26.   The disposal of sand, soil or any materials created by the construction of the dwellings shall
      be removed in accordance with the Construction Management Plan with trucks greater than 6
      metres in length not permitted. Details of the method of this disposal of materials are to be
      submitted to Council at the Building Application stage. Not more than one vehicle at a
      particular time will be parked in Park Road for the removal of, or the delivery of, materials
      associated with the site and no such vehicle shall remain overnight. No materials are
      permitted to be stored within the road reserve.
27.   A program of works is to be submitted with any application for any Development Permit for
      Operational Works detailing the construction schedule and proposed environmental protection
      measures, including a vegetation management plan, which addresses stabilisation of
      disturbed areas. All plans submitted for any Development Permit for Operational Works shall
      show the existing public services with and adjacent to the site including the existing sewer
      main and its levels and zone of influence.
      Prior to commencement of works, a suitably qualified Registered Professional Engineer
      Queensland (RPEQ) shall certify the plans for operational works and the program of works.
      Where the program of works is changed for any reason whatsoever, a copy of the revised
      program shall be submitted to Council’s Works Inspector within seven (7) days.
28.   A Traffic Management Plan for the Construction of the Dwelling addressing the access to the
      site, the locating of equipment and any potential conflicts with local traffic shall be submitted
      and approved by Council prior to Development Permit for Operational Works. It should be
      noted that workers vehicles are to park in Allambi Rise, with no vehicles associated with the
      construction of the dwelling permitted in Park Road.
29.   Prior to the issue of a Development Permit for building works the builder shall submit written
      acknowledgment that building works shall proceed in accordance with the 9 tonne load limit
      applicable to Park Road, unless varied by Council.
30.   At the completion of construction the consulting geotechnical engineer will certify that all works
      were carried out in accordance with their recommendations and that the structures and the
      site are stable.
      Erosion and Sediment Control
31.   Any person acting on this permit shall prevent erosion and sediment export from leaving the
      site. Site control measures such as silt fencing, controlled gravel access to the site and
      controlled disposal of waste, will be necessary.
      In this regard plans detailing the methods of controlling erosion and sediment are required to
      be submitted to the Council for approval prior to obtaining a Development Permit for
      Operational Works.

                                                                                      Page 5 of 11

Page 6

                                                                            22441 DA (2001/210331)




      General
32.   Any damage caused to any public utility during the course of construction shall be repaired to
      Council’s standards and at no cost to Council.
33.   Any alteration of any public utility or other facilities necessitated by the development of the
      land or associated construction works external to the site shall be at no cost to Council.
34.   The transportation of all materials to and from the site shall be undertaken in a manner such
      that no particle matter escapes onto a public road. All vehicles carrying materials either to or
      from the site shall be covered to prevent materials including dust being windblown from the
      vehicle.
35.   Where the existing retaining wall along the Park Road frontage of the site is removed to create
      the driveway crossover the retaining wall shall be remediated immediately following the
      completion of the earthworks for the driveway. The height of any retaining wall constructed
      within the zone of influence of the existing sewer main shall not exceed one (1) metre unless a
      written approval is obtained from Council’s Infrastructures Delivery Unit. A Development
      Permit for Operational Works shall be obtained for these frontage works.
Building
36.   The Geotechnical report submitted as part of your application has been appraised and
      approved subject to the following conditions:-
      36.1. There is to be no uncontrolled discharge of water onto the slope;
      36.2. Stripping of vegetation for construction purposes should be minimised. If vegetation is
            destroyed it should be reinstated immediately after that stage of construction is
            completed;
      36.3. Additional load due to fill, construction equipment or stockpiled materials should not be
            located on the dune slope;
      36.4. The use of vibratory equipment of any kind is not permitted to be used, including
            vibrating rollers, the use of vibrating installation techniques for sheet piling and other
            construction vibrations caused by excavating, earthmoving or demolition machinery or
            other similar construction techniques;
      36.5. All construction works on site shall accord with the Building Construction Report
            prepared by Whaleycg Consulting Group dated December 2002 and the Morrisson
            Geotechnic reports dated 1/9/00, 25/5/01.
      36.6. A condition survey is to be carried out of adjoining buildings, structures and services
            prior to any demolition works or construction works taking place on site. If distress
            already exists, a photographic survey shall be undertaken, the distress measured and a
            plan to monitor changes to distress shall be implemented. A copy of this report is to be
            submitted to Council within 5 business days of survey and prior to construction work
            proceeding;
      36.7. Copies of all inspection reports by engineers are to be submitted to Council within 5
            business days of the inspection taking place;
      36.8. A RPEQ is to be engaged by the client to oversee the piling works and copies of all
            inspection reports are to be submitted to Council within 5 business days of the
            inspection taking place;




                                                                                    Page 6 of 11

Page 7

                                                                              22441 DA (2001/210331)




       36.9. The applicant’s Geotechnical engineer will be required to be on site for the whole of the
             time during any excavation. The construction of the whole of the foundations is to be
             supervised and directed on site by a consulting Geotechnical engineer. No work of any
             such kind relating to the foundations shall be carried out if he is not on the site and
             supervising and directing this work. Such works shall only be carried out during dry
             weather conditions and if there is a risk of sand movement occurring, all work shall be
             suspended until such steps, approved by the applicant’s Geotechnical engineer and the
             Council’s Building Surveyor, have been taken to ensure that no further slippage will
             result.
       36.10.The builder, landscaper and all workers associated with construction of the works shall
             at all times comply with the directions of the consulting geotechnical engineer.
       36.11.The applicant shall take all necessary measures to ensure that the construction works
             on the site will not have any adverse impact on the short-term and the long-term stability
             of the sand dune formation or the stability of any adjoining property including buildings
             and underground services. The applicant shall be responsible for any remedial works if
             required on other properties as a consequence of the development works on the site.
       36.12.Where the development works on the site requires the use (above ground or
             underground) of other private properties, it is the applicant’s responsibility to negotiate
             and arrange for any Permit to Enter these properties and any other related legal
             requirements if needed prior to obtaining a Development Permit for Operational Works.
37.    A verification survey of the building is to be carried out by a Licensed Surveyor and a
       certificate lodged with Council at completion of the work confirming compliance with the
       minimum required floor level and the maximum building height above natural surface, required
       by the provisions of the Planning Scheme.
Additional Conditions
1.     Deleted.

2.     A qualified arborist shall be present on site to supervise works around the root zones of all
       trees required to be retained. Prior to commencing any works safety fences shall be installed
       around the trunks and as much of the root zone as possible to minimise the risk of compaction
       and damage.
3.     The rock wall adjacent to the decking of the swimming pool shall not exceed a maximum
       height of 1.8 metres above the level of the decking.
4.     Tree no. 47 shall be replaced with a suitable native species and located generally in the same
       vicinity.
5.     The proposed deck extension and all associated structures shall be setback a minimum of 2
       metres from the northeastern side boundary. The setback shall be densely landscaped with
       such landscaping to be in accordance with a revised landscaping plan which is required to be
       submitted to Council for approval prior to the use commencing.
6.     The undercroft areas of the swimming pool and deck shall be screened with landscaping with
       such landscaping to be in accordance with an revised landscaping plan which is required to be
       submitted to Council for approval prior to the use commencing.

5      REFERRAL AGENCY CONDITIONS

The referral agencies applicable to this application are:

 Referral Trigger            Referral Status     Referral Agency         Referral Address

 Nil




                                                                                      Page 7 of 11

Page 8

                                                                               22441 DA (2001/210331)




6     APPROVED PLANS/DOCUMENTS
The approved plans and / or documents for this development approval are listed in the following
table:
 Plan / Document No.       Rev.    Plan / Document Name                        Date
 SK-A-02.01                P9      Site Plan – Cecilia Brown Design            3 December 2008
 SK-A-03.01                P10     Garage Plan – Cecilia Brown Design          3 December 2008
 SK-A-03.02                P10     Maid Room Plan – Cecilia Brown              3 December 2008
                                   Design
 WD-A-03.03                P18     Cabana Plan – Cecilia Brown Design          8 May 2008
 SK-A-03.04                P9      Master Bed Plan – Cecilia Brown             3 December 2008
                                   Design
 SK-A-03.05                P9      Roof Plan – Cecilia Brown Design            3 December 2008
 SK-A-04.01                P4      West Elevation – Cecilia Brown Design       3 December 2008
 SK-A-04.02                P4      South Elevation – Cecilia Brown Design      3 December 2008
 SK-A-04.03                P4      North Elevation – Cecilia Brown Design      3 December 2008
 SK-A-04.04                P4      East Elevation Master Bed & East            3 December 2008
                                   Elevation Cabana & Maid – Cecilia
                                   Brown Design
 SK-A-05.01                P1      Section A – Cecilia Brown Design            4 December 2008
 SK-A-05.02                P1      Section B – Cecilia Brown Design            4 December 2008

7     ADVISORY NOTES

The following Advisory Notes are for information purposes only and do not form conditions of
approval:
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries
out an activity must take all reasonable and practicable measures to ensure the activity does not
harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial
monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions
may also be issued by the Land and Resources Tribunal, and the Minister administering the ACH Act
can also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural
heritage or the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Co-ordination Unit on 07 3238 3838 to discuss any
obligations under the ACH Act.

8     PROPERTY NOTES

Not applicable

9     PRELIMINARY APPROVAL OVERRIDING SCHEME
Not applicable


                                                                                       Page 8 of 11

Page 9

                                                                          22441 DA (2001/210331)




10     FURTHER DEVELOPMENT PERMITS REQUIRED

 Type of Development Permit required        Subject of the required Development Permit
 Development Permit for Building Works      All Building Works

 Development Permit for Operational         Landscaping, Carparking, Access, Frontage Works,
 Works                                      Stormwater Drainage, Site Civil Works, Sewer
                                            Reticulation & Water Reticulation

11     SELF ASSESSABLE CODES

Not applicable
12     SUBMISSIONS

There were three (3) properly made submissions about the application.

13     REASONS / GROUNDS FOR APPROVAL DESPITE CONFLICT WITH SCHEME
Not applicable

14     RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Integrated Planning Act 1997 is attached.

15     OTHER DETAILS

Should you wish to obtain more information about Council’s decision electronic copies are available
on line at www.sunshinecoast.qld.gov.au, or at Council Offices.


Decision Notice History
12 June 2003          Original Decision Notice

13 December 2007      Compiled Decision Notice with amendment to Conditions
                      1, 10 and 21, additional Conditions 1 & 2 and refuse to
                      change Condition 36.4

18 April 2008         Change to an Existing Approval with amendment to
                      Condition 10

31 March 2009         Change to an Existing Approval with amendment to
                      Conditions 1, 6, 10, 16, 26, 27, 35 & 36, inclusion of two
                      additional conditions 3 & 4 and deletion of Additional
                      Condition 1
15 October 2009       Change to an Existing Approval with amendment to
                      Condition 1 and inclusion of two additional Conditions 5 &
                      6
Yours faithfully,



Kerri Coyle
COORDINATOR PLANNING APPLICATIONS (NORTH)
                                                                                   Page 9 of 11

Page 10

                                                                                      22441 DA (2001/210331)




                                                  Appeal Rights
                                                  INTEGRATED PLANNING ACT 1997 & 1998 REGULATION




The following is an extract from the Integrated              development that would have required public
Planning Act (Chapter 4).                                    notification under the repealed Act.
Division 8 - Appeals to court relating to                         (6) If an application involves assessment
development applications
                                                             against a concurrence agency code, appeal rights
Appeals by applicants                                        for submitters for the application are not available
4.1.27.(1) An applicant for a development                    against the part of the approval that represents the
application may appeal to the court against any of           concurrence agency’s response for the code.
the following-                                               Appeals by advice agency submitters
(a) the refusal, or the refusal in part, of a                4.1.29.(1) An advice agency may, within the limits
    development application;                                 of its jurisdiction, appeal to the court about the
(b) a matter stated in a development approval,               giving of a development approval for a
    including any condition applying to the                  development application if-
    development, and the identification of a code            (a) the development application involves impact
                          1
    under section 3.1.6;                                          assessment; and
(c) the decision to give a preliminary approval              (b) the advice agency told the applicant and the
    when a development permit was applied for;                    assessment manager to treat its response to
(d) the length of a currency period;                              the application as a submission for an appeal.
(e) a deemed refusal.                                             (2) The appeal must be started within 20
    (2) An appeal under subsection (1)(a) to (d)             business days after the day the decision notice or
                                                             negotiated decision notice is given to the advice
must be started within 20 business days (the
“applicant’s appeal period”) after the day the               agency as a submitter.
decision notice or negotiated decision notice is             Appeals for matters arising after approval given
given to the applicant.                                      (co-respondents)
    (3) An appeal under subsection (1)(e) may be             4.1.30.(1) For a development approval given for a
started at any time after the last day a decision on         development application, a person to whom any of
the matter should have been made.                            the following notices have been given may appeal
Appeals by submitters                                        to the court against the decision in the notice-
4.1.28.(1) A submitter for a development                     (a) a notice giving a decision on a request for
                                                                  extension of the currency period for an
application may appeal to the court about-
                                                                  approval;
(a) the giving of a development approval, including
    any conditions (or lack of conditions) or other          (b) a notice giving a decision on a request to make
                                                                  a minor change to an approval.
    provisions of the approval; or
                                                                  (2) The appeal must be started within 20
(b) the length of a currency period for the approval.
                                                                      business days after the day the notice of the
    (2) The appeal must be started within 20                          decision is given to the person.
business days (the “submitters appeal period”)
                                                                  (3) Subsection (1)(a) does not apply if the
after the day the decision notice or negotiated
                                                                      approval resulted from a development
decision notice is given to the submitter.
                                                                      application (superseded planning scheme)
    (3) If a person withdraws a submission before                     that was assessed as if it were an
the application is decided, the person may not                        application under a superseded planning
appeal the decision.                                                  scheme.
    (4) If an application involves both impact                    (4) Also, a person who has made a request
assessment and code assessment, appeal rights                         mentioned in subsection (1) may appeal to
for submitters are available only for the part of the                 the court against a deemed refusal of the
application involving impact assessment.                              request.
    (5) If an application is processed under section              (5) An appeal under subsection (4) may be
6.1.28(2), appeal rights for submitters for the                       started at any time after the last day the
application are available only for the aspects of the                 decision on the matter should have been
                                                                      made.
1
     Section 3.1.6 (Preliminary approval may override
    local planning instrument)
                                                                                             Page 10 of 11

Page 11

                                                                                  22441 DA (2001/210331)




Division 9 - Appeals to court about other               Division 3 – Appeals to tribunals relating to
matters                                                 development applications
Appeals for matters arising after approval given        Appeals by applicants
(no co-respondents)
4.1.31.(1) A person to whom any of the following
notices have been given may appeal to the court         4.2.9(1) An applicant for a development application
against the decision in the notice-                     may appeal to the Building and Development
(a) a notice giving a decision on a request to          Tribunal against any of the following-
    change or cancel a condition of a development       (a) the refusal, or the refusal in part, of a
    approval.                                               development application;
                                   2
(b) a notice under section 6.1.44 giving a decision     (b) a matter stated in a development approval,
    to change or cancel a condition of a                    including any condition applying to the
    development approval.                                   development, and the identification of a code
                                                                                  3
    (2) The appeal must be started within 20                under section 3.1.6;
        business days after the day the notice of the   (c) the decision to give a preliminary approval when a
        decision is given to the person.                      development permit was applied for;
    (3) Also, a person who has made a request           (d) the length of a period mentioned in section 3.5.21
        mentioned in subsection (1)(a) may appeal             currency period;
        to the court against a deemed refusal of the    (e) a deemed refusal.
        request.                                            (2) An appeal under subsection (1)(a) to (d) must
    (4) An appeal under subsection (3) may be           be started within 20 business days (the “applicant’s
        started at any time after the last day the      appeal period”) after the day the decision notice or
        decision on the matter should have been         negotiated decision notice is given to the applicant.
        made.                                               (3) An appeal under subsection (1)(e) may be
Appeals against decisions to change approval            started at any time after the last day a decision on the
conditions under the repealed Act                       matter should have been made.
4.1.33A.(1) A person who is dissatisfied with a         The Registrar for the Building and Development
                                                        Tribunal may be contacted at the website
decision made on an application to change the
                                                        http://www.localgovernment.qld.gov.au/
conditions attached to an approval given under
section 2.19(3)or section 4.4 of the repealed Act
may appeal to the court against-
(a) the decision; or
(b) a deemed refusal of the application.
    (2) An appeal under subsection (1)(a) must be
started within 20 business days after the day notice
of the decision is to be given to the person.
    (3) An appeal under subsection (1)(b) may be
started at any time after the last day a decision on
the matter should have been made.
Appeals against local laws
4.1.33B.(1) An applicant who is dissatisfied with a
decision of a local government or the conditions
applied under a local law about the use of premises
or the erection of a building or other structure
permitted by the planning scheme may appeal to
the court against the decision or the conditions
applied.
    (2) The appeal must be started within 20
business days after the day notice of the decision
is given to the applicant.
For Building Works Only
Rights of appeal conferred by Section 4.2.9 of the
Integrated Planning Act 1997 as follows:


2
     Section 6.1.44 (Conditions may be changed or
                                                        3
    cancelled by assessment manager or concurrence           Section 3.1.6 (Preliminary approval may override
    agency in certain circumstances)                        local planning instrument)
                                                                                          Page 11 of 11

Used in these records

About this file

File size
69 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

SUPERSEDED Change to an Existing Approval - 010.2001.00210331.005 [As Published].pdf · 69 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.