Installation steps
PRS-Neoloy® Tough Cells
Installation for Pavements
PRS Engineering – Ver. 2021.1
PRS Proprietary Information
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Installation steps.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.
Full text of the other 15 pages
Page 2
Installation – Steps
EQUIPMENT SITE CROSS LAYOUT
PREPARATION SECTION NEOLOY
FASTENING EXPANDING FILLING LEVELING AND
SECTION COMPACTION
PRS Proprietary Information Slide 2
Page 3
EQUIPMENT
Granular materials Pneumatic gun with
40cm long rebars
Neoloy sections Compressor (According to design staples
(10mm d)
specifications)
Other geosynthetics Compactor
Front-end Loader Road Grader Water Truck
(if required by design)
Page 4
Site Preparation Subgrade Geosynthetics (If defined on design) • Remove roots and vegetated surface • Install geosynthetics according to manufacturer • Execute excavation (if specify in design) instructions • Level and compact (recommended >95%) • Ensure overlap • Mark route
Page 5
Cross Section
Layers configuration
1) 200mm Neoloy-330-120-C filled with local
sand (120mm fill + 50mm overfill = 170mm)
2) Woven geotextile
3) Subgrade, compacted sand
PRS Proprietary Information 5
Page 6
Layout Neoloy
Anchoring
• Anchor at fixed intervals along route
1. Mark with string to align straight
2. Place anchors in both sides of the
road
3. For Neoloy-330, place stake anchor
every 49cm (2 cells)
4. Leave top exposed for easy removal
(recommended 10cm above Neoloy)
Insert Video of Anchoring
PRS Proprietary Information
Page 7
Layout Neoloy Layout Direction Opening • Disperse closed sections parallel to road • Calculate section size and road dimensions • Open sections perpendicular to road (8m width) • Cut as necessary • The 2.5m long needs to be expanded in the road direction
Page 8
Layout Neoloy Cutting Sections (If needed) September 15, 2022 PRS Proprietary Information Slide 8
Page 9
6. Fasten SectionsPneumatic Stapler &
Compressor
PNEUMATIC STAPLER with Generator
& COMPRESSOR WITH GENERATOR
Page 10
6. Fasten Sections
WITH PNEUMATIC STAPLER
• End to End
– Align and interleaf ends of 2 sections
– Fasten seams of each strip
– Do not skip strips!
• Face to Face
– Align 2 sections (lengthwise)
– Fasten each end (seam)
– Continue fastening the seam of each
cell
– Do not skip cells!
Page 11
6. Fasten Sections
STAPLE PROPERLY
• Staple on seams – not holes
• Do not skip cells or strips
• Must use correct no. of staples per height
• < PRS 075 mm – 3 staples (minimum)
• < PRS 100 mm – 4 staples
• < PRS 120 mm – 4 staples
• < PRS 150 mm – 5 staples
• < PRS 200 mm – 6 staples
NOTES:
* Must fasten at top and bottom of cell
* Staples must penetrate all strips and/or seams
Page 12
7. Expand (Open) Sections
Insert video
Expand Verify
• Place on anchors on one side • Cells are opened to correct dimensions
• Stretch and place over anchors on opposite side • Cut out extra cells
• Stakes are removed after infill
Page 13
Reminder – Do NOT step/drive on empty cells
Do Not Step on Empty Cells Do Not Drive on Empty Cells
Use Boards to Walk on Cells Drive on Cells Only after Infilled
PRS Proprietary Information 13
Page 14
8. Placing Infill
• Operating Vehicles
• Ensure 7 cm minimum infill before
driving on cells
• Minimize speed, braking, turning
• Placing Infill
• Overfill cells >7 cm above cells
• Limit drop height to 1m
• Compact infill with blade (shovel)
• Remove large debris
• No cells exposed
Insert video
Page 15
• Level, water & compact to required elevations and grades
• Remove anchors and large debris
9. Compaction • If total infill >20 cm, compact in separate layers
• >3 cm above cells AFTER full compaction
Page 16
Thank You Questions? [email protected] Geo-Technologies