09 Aug 2012 Level 9, 269 Wickham St
Ref. no. 2012.164.600 PO Box 612 Fortitude Valley
QLD 4006, Australia
T +61 7 3251 8555
Fulton Trotter F +61 7 3251 8599
18 Portman Lane [email protected]
PO Box 353 www.blightanner.com.au
SPRING HILL QLD 4004 ABN 32 061 537 666
Attention: Mark Kalinowski / Belinda Gleeson
Dear Mark & Belinda,
PROJECT: Noosa Flexi Learning Centre
RE: Infrastructure Servicing Comments
This letter briefly outlines the civil engineering aspects of the proposed development of Lot
RP887636 at 2 Girraween Crt, Sunshine Beach, Qld. This letter has been prepared to
accompany a Development Application to Sunshine Coast regional Council for a Material
Change of Use for the proposed development. The site will be developed to create a Flexi
Learning Centre for about 80 students and 10 staff.
The proposed land use is consistent with the town plan (Community Use, Education (Type 2
School)), and so it is assumed there is sufficient capacity in trunk infrastructure to meet the
needs of the site.
Site Overview:
The 0.56 ha site has a slight grade (1.6%) towards the southern frontage on Girraween Crt.
It is on sandy soils and currently vegetated with a mix of native vegetation. It is currently
undeveloped. It is directly opposite Sunshine Beach High School, and at the end of the Crt is
the Noosa Aquatic Centre. Eenie Creek Rd lies to the rear of the lot.
Water Supply
Unitywater has an existing water supply connection in front of Lot 2. This connects to a water
supply main which runs along the opposite side of Girraween Crt (Lot 2 has recently been
subdivided along a north/South axis into two lots, and the proposed development is on the
western subdivided Lot. This connection point appears to be in front of the eastern lot). The
capacity of this water supply main has not been verified, however from a water supply
perspective there appears to be no constraints to developing the site.
There is a fire hydrant on Girraween Crt directly opposite the site.
Wastewater
Unitywater has an existing sewer manhole in the south-western corner of the lot. This
manhole is the upper end of a sewer main which drains to a pump station at the western end
of Girraween Crt. The capacity of this sewer has not been verified, however from a
wastewater perspective there appears to be no constraints to developing the site.
DIRECTORS | ROD BLIGH | CHRIS TANNER | PAUL CALLUM | DAVID HAMLYN-HARRIS | PAUL EASINGWOOD
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Appendix D - Infrastructure Services Assessment.pdfRelated documentApplication case desk ↗
About this file
- File size
- 2.3 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.