Council archive · source document
Decision Notice MCU22 0199 · MCU22/0199
Environment
9. Sediment or any other material including building materials or waste products must not be
deposited or released into the road reserve, stormwater drain or adjacent properties.
Water Supply
10. The approved dwelling must be serviced with a rainwater tank having a minimum storage
capacity of no less than 60,000 litres.
Waste Water Treatment and Disposal
11. The dwelling must be provided with an on-site waste water treatment and effluent disposal
system having a capacity sufficient for the use*.
*(Refer to Advisory Note)
Bushfire Management
12. An accessible dam, swimming pool or water tank (in addition to day to day water supply) with
an onsite water volume of not less than 5,000 litres must be available for firefighting
purposes, located within reasonable proximity to building.
13. A water supply outlet pipe 50 millimetres in diameter and fitted with a standard fire brigade
fitting must be connected to the water supply (other than where the water supply is in a
swimming pool or dam).
ENGINEERING
Site Access and Driveways
14. A sealed access driveway must be provided from Cooroy Belli Creek Road to all parking and
manoeuvring areas of the development. The access driveway must be located and
constructed to not adversely affect the existing conditions of the local road network. The
works must be undertaken in accordance with an Operational Works approval, be generally
in accordance with SCG Consulting’s Driveway Re-Aligning Plan (33002-DR1.1) dated April
2023 and be constructed using compacted gravel and seal as described on RS-056.
Stormwater Drainage
15. Stormwater runoff from the development must be disposed of on-site without causing scour
or damage to the subject site or any adjoining property.
Easements
16. Unless otherwise agreed in writing by the relevant service provider, any public or third party
infrastructure located on the subject site must be placed within an easement registered
against the title of the property.
17. All easements must be designed in accordance with the planning scheme and granted at no
cost to the Grantee. Where the Grantee is Council or a service authority, the easement
documentation must be in accordance with the Grantee’s standard easement terms. Draft
easement documentation must be submitted to Council for endorsement.
18. All works must be kept clear of any existing or proposed easements on the subject land,
unless agreed otherwise in writing by the Grantee.
Geotechnical Stability
19. All works must be carried out in accordance with the recommendations contained in section
7 of Core Consultants’ Geotechnical Investigation & Stability Assessment (J001783-001-R-
Rev1).
Earthworks and Retaining Walls
20. All earthworks and associated batters for the new dwelling must be undertaken generally in
accordance with SCG Consulting Engineers Plan No 33002-C2.1 dated February 2022 and
the recommendations contained in the Geotechnical Investigation & Stability Assessment –
Report No J001783-001-R-Rev 1 prepared by Core Consultants.
Page 3 of 6
Document Set ID: 22432751
Version: 2, Version Date: 19/05/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice MCU22 0199.pdfRelated documentApplication case desk ↗
2024072 - NSC MCU Decision Notice with Conditions (Dated 19-05-2023) (1).pdfRelated documentApplication case desk ↗
001 ECM_22432751_v2_Decision Notice MCU22 0199.pdfRelated documentApplication case desk ↗
About this file
- File size
- 171 KB (small file)
- File type
No other editions are linked here.