Decision Letter - Change to an Existing Approval - 010.2007.00001173.03 [As Published] · 142007.1173.03
2007/1173
7 ADVISORY NOTES
The following Advisory Notes are for information purposes only and do not form conditions of
approval:
1. The applicant is advised that development contributions and infrastructure charges applicable to
this development approval have been based on the following Uses Class/ Uses and applicable
quantities:-
Existing Development Approved Development
Existing Use Class / Approved Use Class
Existing Quantity Approved Quantity
Use / Use
Commercial
Commercial Business
Business Type 1 - 41m² Use Area 55m² Use Area
Type 1 - Office
Office
2. The applicant is informed that approval of this development application will trigger an
Infrastructure Charge in accordance with the Coastal Major Road Network Infrastructure
Charges Plan for the estimated amount of $2,025 and is subject to variations in the Consumer
Price Index, All Groups Brisbane from September 2008 until the date of payment. An
Infrastructure Charge Notice will be issued in accordance with Chapter 5 of the Integrated
Planning Act 1997.
3. The applicant is informed that payment via credit card transaction will not be an acceptable
method of payment for development contributions conditioned in this permit or for infrastructure
charge notices issued separately.
4. Should any changes or modifications to the approved plans be required as a result of
construction constraints, a Change to an Existing Approval Application under the Integrated
Planning Act must be made. Amended plans clearly indicating the changes must be lodged with
this application along with the appropriate fees.
5. The requirements of the Environmental Protection Amendment Regulation (No. 2) 1999 and
Local Law No. 12, prevents a builder or building contractor carrying out building work on a
building site in a way that makes or causes audible noise to be made from the building work:-
5.1. On a Sunday or public holiday, at any time; or
5.2. On a Saturday or a business day, before 7.00am or after 6.30pm.
A maximum penalty of $1,500 applies to an offence under this legislation.
6. Pursuant to the Building and Construction Industry (Portable Long Service Leave) 1991 Act if the
cost of operational works exceeds $80,000, then a portable long service leave levy is required to
be paid. In accordance with Section 77.(1) of the Act, Council is required to sight the approved
form issued by the Building and Construction Industry (Portable Long Service Leave) Authority
that confirms that the requirements of the Act have been satisfied. A statutory declaration
outlining the cost of the operational works must be submitted to Council prior to commencement
of work.
Additional advice conditions
1. The jetty must be licensed with the Council upon completion of the structural work and be
licensed annually thereafter.
2. Wastewater and sullage from vessels must only be disposed of at approved pumpout facilities.
Page 5 of 21
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Letter - Change to an Existing Approval - 010.2007.00001173.03 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 837 KB (small file)
- File type
No other editions are linked here.