GE11-N Planning Act 2016 - Appeal provisions · MCU19/0001.01
Attached to the e-mail Change to SARA response & approval - MCU19/0001 & MCU19/0001.01.
Attached to the e-mail SARA Response - 152006.1999.4.
Attached to the e-mail SARA Decision notice - 6 - 10 Diamond St, Cooroy - MCU19/0001.
Attached to the e-mail 132008.176.06 - SARA Response - Decision for change application.
3. Extension applications
For an extension application other than an extension application called in by the Minister, an appeal may be made against—
(a) The assessment manager’s decision on the extension application; or
(b) A deemed refusal of the extension application.
Column 1 Column 2 Column 3 Column 4 Co-respondent
Appellant Respondent Co-respondent by election (if
(if any) any)
1. The applicant The assessment manager If a concurrence agency starts If a chosen assessment
the appeal—the applicant manager
2. For a matter is the respondent—the
other than a deemed prescribed assessment
refusal of an extension manager
application—a
concurrence agency, other
than the chief executive,
for the application
4. Infrastructure charges notices
An appeal may be made against an infrastructure charges notice on 1 or more of the following grounds—
(a) the notice involved an error relating to—
(i) the application of the relevant adopted charge; or
Examples of errors in applying an adopted charge:
▪ the incorrect application of gross floor area for a non-residential development
▪ applying an incorrect ‘use category’, under a regulation, to the development
(ii) the working out of extra demand, for section 120; or
(iii) an offset or refund; or
(b) there was no decision about an offset or refund; or
(c) if the infrastructure charges notice states a refund will be given—the timing for giving the refund; or
(d) the amount of the charge is so unreasonable that no reasonable relevant local government could have imposed the amount.
Column 1 Column 2 Column 3 Column 4 Co-respondent
Appellant Respondent Co-respondent by election (if
(if any) any)
The person given the The local government that gave — —
infrastructure charges notice the infrastructure charges notice
5. Conversion applications
An appeal may be made against—
(a) the refusal of a conversion application; or
(b) a deemed refusal of a conversion application.
Column 1 Column 2 Column 3 Column 4 Co-respondent
Appellant Respondent Co-respondent by election (if
(if any) any)
The applicant The local government to which — —
the conversion application was
made
6. Enforcement notices
An appeal may be made against the decision to give an enforcement notice.
Page 6 of 10 GE11-N
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
GE11-N Planning Act 2016 - Appeal provisions.pdfRelated documentApplication case desk ↗
GE11-N Planning Act 2016 - Appeal provisions.pdfRelated documentApplication case desk ↗
GE11-N Planning Act 2016 - Appeal provisions.pdfRelated documentApplication case desk ↗
GE11-N Planning Act 2016 - Appeal provisions.pdfRelated documentApplication case desk ↗
GE11-N Planning Act 2016 - Appeal provisions.pdfRelated documentApplication case desk ↗
GE11-N Planning Act 2016 - Appeal provisions.pdfRelated documentApplication case desk ↗
About this file
- File size
- 288 KB (small file)
- File type
No other editions are linked here.