SUPERSEDED - Minor Change Existing Approval 51983 3225 15 [As Published]
Officer: Lisa Pienaar
Direct Telephone: 07 53296514
Our Reference: 51983.3225.15
Your Reference: 02596
3 August 2022
RT Wadland TTE
C/- Martoo Consulting Pty Ltd
PO Box 1684
NOOSA HEADS QLD 4567
[email protected]
Dear Sir/Madam,
Decision Notice – Minor Change
Planning Act 2016
I refer to your application received on 22 April 2022, requesting a minor change to an existing
development approval. Council decided your requested changes.
Details of the decision are as follows:
1. APPLICATION DETAILS
Application No: 51983.3225.15
Street address: The Hastings 17/30 Hastings St Noosa Heads Qld 4567
Real property description: Lot 17 GTP 1154
Planning Scheme: Noosa Plan 2020 (25 September 2020)
2. DECISION DETAILS
The following type of approval was issued on October 1983
Town Planning Consent Permit for Multiple Dwelling 25 Units, 8 Shops
In relation to the request to make a minor change to the existing approval, Council on 1 August
2022, decided to approve the requested changes. The changes are detailed below.
A. Approve the change
B. Amend condition 1
3. CURRENCY PERIOD OF APPROVAL
The currency period for this development approval is stated in the conditions below.
PO Box 141 P. (07) 5329 6500 [email protected]
TEWANTIN QLD 4565 F. (07) 5329 6501 www.noosa.qld.gov.au
Page 1 of 14
Document Set ID: 22058500
Version: 4, Version Date: 04/08/2022
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.
Full text of the other 13 pages
Page 2
4. ASSESSMENT MANAGER CONDITIONS
PLANNING
When Conditions must be Complied With
1. Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to
the use commencing, and then compliance maintained at all times while the use continues.
Plan No. Rev. Plan, prepared by Date
No.1 Perspectives & Notes, prepared by Accolade 22/07/2014
Building Designs
No.3 Ground Floor & 1st Level, prepared by 22/07/2014
Accolade Building Designs
No.4 Elevations, prepared by Accolade Building 22/07/2014
Designs
Approved Plans - October 2015
DA 3001 A Site Plan, prepared by Peter Hull Architect Sept 15
DA 3002 B Floor Plans, prepared by Peter Hull Architect Sept 15
DA 3004 A Ground Floor and Carport Plan, prepared by Sept 15
Peter Hull Architect
DA 4001 B Sections, prepared by Peter Hull Architect Sept 15
DA 5001 B Elevations, prepared by Peter Hull Architect Sept 15
Approved Plans – March 2016
GRND FLR – Proposed (Unit 14), prepared by 14/10/2015
LPID
Elevation (Unit 14) – East Facing (Street 14/10/2015
Frontage), prepared by LPID
Elevation – North Facing (Unit 14), prepared 14/10/2015
by LPID
Elevation – South Facing (Unit 14), prepared 14/10/2015
by LPID
Elevation – West Facing (Unit 14), prepared 14/10/2015
by LPID
3D Views – Exterior (Unit 14), prepared by 14/10/2015
LPID
GRND FLR – Proposed (Unit 25), prepared by 14/10/2015
LPID
Elevation (Unit 25) – South View, prepared by 14/10/2015
LPID
Page 2 of 14
Document Set ID: 22058500
Version: 4, Version Date: 04/08/2022
Page 3
Elevation – East (Unit 25), prepared by LPID 14/10/2015
Elevation – West (Unit 25), prepared by LPID 14/10/2015
Elevation – North (Unit 25), prepared by LPID 14/10/2015
3D Views – Exterior (Unit 25), prepared by 14/10/2015
LPID
Approved plans – May 2016
Plan No. Rev. Plan, prepared by Date
DA.01 B Location Plan prepared by Bark Design Architects 26/02/201
6
DA.02 C Site Plan prepared by Bark Design Architects 23/02/201
6
DA.04 C Ground Floor Plan prepared by Bark Design 23/02/201
Architects 6
DA.05 C First Floor Plan prepared by Bark Design Architects 23/02/201
6
DA.06 C Second Floor Plan prepared by Bark Design 23/02/201
Architects 6
DA.07 C Roof Terrace Plan prepared by Bark Design 23/02/201
Architects 6
DA.11 B South Elevation prepared by Bark Design 26/02/201
Architects 6
DA.12 B East Elevation prepared by Bark Design Architects 26/02/201
6
DA.13 B North Elevation prepared by Bark Design Architects 26/02/201
6
DA.14 B West Elevation prepared by Bark Design Architects 26/02/201
6
Approved plans – March 2017 Unit 20
Plan No. Plan, prepared by Date
1016HMK 3D rendering, prepared by Accolade Building 23 March 2017
Sheet 1 Designs
1016HMK Floor Plans, prepared by Accolade Building 23 March 2017
Sheet 2 Designs
1016HMK Ground Floor plan, prepared by Accolade 23 March 2017
Sheet 3 Building Designs
Page 3 of 14
Document Set ID: 22058500
Version: 4, Version Date: 04/08/2022
Page 4
1016HMK Elevations, prepared by Accolade Building 23 March 2017
Sheet 4 Designs
Approved plans – April 2017 Unit 13
Plan, prepared by Date
Site plan, prepared by Mandy’s Design and Drafting March 2017
Proposed floor plan, prepared by Mandy’s Design and March 2017
Drafting
Elevations, prepared by Mandy’s Design and Drafting March 2017
Approved plans – August 2017 Unit 20
Plan No. Plan, prepared by Date
1016HMK 3D rendering, prepared by Accolade Building 23 March 2017
Sheet 1 Designs
1016HMK Floor Plans, prepared by Accolade Building 23 March 2017
Sheet 2 Designs
1016HMK Ground Floor plan, prepared by Accolade 23 March 2017
Sheet 3 Building Designs
1016HMK Elevations, prepared by Accolade Building 23 March 2017
Sheet 4 Designs
Approved plans – August 2017 Unit 5
Sheet 1 of Site Plan, prepared by Mandy’s Design and July 2017
4 Issue A Drafting
Sheet 2 of Existing Floor Plans, prepared by Mandy’s July 2017
4 Issue A Design and Drafting
Sheet 3 of Proposed floor plan, prepared by Mandy’s July 2017
4 Issue A Design and Drafting
Sheet 4 of Elevations, prepared by Mandy’s Design and July 2017
4 Issue A Drafting
Approved Plans – April 2018 Unit 21
Sheet 1 of Proposed Partial Enclosure of Ground Level 26/04/2018
6 Under Existing Unit, prepared by Accolade
Building Designs
Sheet 2 of Proposed Partial Enclosure of Ground Level 26/04/2018
6 Under Existing Unit, prepared by Accolade
Building Designs
Page 4 of 14
Document Set ID: 22058500
Version: 4, Version Date: 04/08/2022
Page 5
Sheet 3 of Proposed Partial Enclosure of Ground Level 26/04/2018
6 Under Existing Unit (floor plans), prepared by
Accolade Building Designs
Sheet 4 of Proposed Partial Enclosure of Ground Level 26/04/2018
6 Under Existing Unit (elevations), prepared by
Accolade Building Designs
Approved Plans – 1 August 2022 Unit 17
Sheet 01, Site Location, Site Plan & Floor Plans, June 2022
Issue H prepared by Innovate Architects
Sheet 02, Elevations, Section & External Finishes June 2022
Issue H Schedule, prepared by Innovate Architects
Sheet 07 Perspectives, prepared by Innovate Architects June 2022
Issue H
Approved Plans – March 2020 Unit 19
A01 Site Location, Site Plan & Calculations, 22 January 2021
prepared by Lisa Page
A02 Ground Floor Plan – with proposed alterations, 22 January 2021
prepared by Lisa Page
A03 Level 1 Floor Plan, prepared by Lisa Page 22 January 2021
A04 Level 2 Floor Plan, prepared by Lisa Page 22 January 2021
A05 Level 3 Terrace, prepared by Lisa Page 22 January 2021
A06 Elevations Views: North & South facing, 22 January 2021
prepared by Lisa Page (as annotated by
Council)
A07 Elevations Views: East & West facing, 22 January 2021
prepared by Lisa Page (as annotated by
Council)
A08 Perspective view, Terrace level, prepared by 22 January 2021
Lisa Page
A09 Perspective views: south, west, north facing, 22 January 2021
prepared by Lisa Page
A10 Perspective views: south/east/north views, 22 January 2021
prepared by Lisa Page
A11 Section view-east facing, prepared by Lisa 22 January 2021
Page
A12 External Material Finishes Palette 22 January 2021
by Lisa Page
Page 5 of 14
Document Set ID: 22058500
Version: 4, Version Date: 04/08/2022
Page 6
- Landscape Concept Design document -
including site plan and perspective, cross
sections, look and feel and design, prepared
by Louise Custance
Approved Plans – 21 October 2021 Units 9-10 (Lot 30 SP307674)
Plan No. Plan, prepared by Date
SD.102 Proposed Holyman Unit 3D perspectives, N/D
prepared by Gerard Smith Design
Iss P2
SD.104 Site / Roof Plan, prepared by Gerard Smith Aug 2018
Iss P10 Design
SD.201 Floor Plans, prepared by Gerard Smith Design Aug 2018
Iss P9
SD.501 Elevations proposed, prepared by Gerard Aug 2018
Iss P9 Smith Design
SD.601 Cross Sections – Sheet 2, prepared by Gerard Aug 2018
Iss P2 Smith Design
SD.951 Overviewing Diagrams – Level 1, prepared by Aug 2018
Iss P9 Gerard Smith Design
SD.952 Overviewing Diagrams – Level 2, prepared by Aug 2018
Iss P9 Gerard Smith Design
3 Development authorised by this approval must be undertaken generally in accordance with
the Approved Plans listed within this Decision Notice.
Construction Management Plan & Pre-Start Meeting
4 A Construction Management Plan must be submitted to and approved by Council prior to
obtaining a building approval and must specifically address the following:
a. Traffic Management during all aspects of the construct phase including.
i. Traffic Management Control Plan in accordance with Manual of Uniform Traffic
Control Devices (MUTCD) detailing all temporary signage and traffic control
measures prior to construction.
ii. Maintenance of safe and unobstructed access across the frontage of the site for
pedestrians and vehicles both during daily construction and after daily
construction has ceased.
iii. Parking arrangements, number, and locations for vehicles associated with the
proposed construction works that need to be onsite or in proximity to the site at
any time during the phases of the construction works. Where relevant, time slots
and off-peak hours should be indicated. All efforts must be made to prevent or
minimise adverse impact on public parking availability in the local area.
b. Works programme identifying key components of the works and their respective
durations.
c. Written confirmation from the Body Cooperate accepting the use of the common
property for activities associated with the construction works as identified in the final
Construction Management Plan and the Traffic Management Plan.
Page 6 of 14
Document Set ID: 22058500
Version: 4, Version Date: 04/08/2022
Page 7
d. Proposed fencing to the site during the construction phase of the development.
e. Protection fencing for existing landscaping and trees in proximity to the work activities.
f. Maintenance and protection of water quality and existing drainage lines through the
construction site through the implementation of appropriate erosion and sediment
control measures to prevent silt and contaminants from entering existing stormwater
system.
g. Establishment of a communication protocol with the general public, adjoining owners,
emergency services and local businesses to advise of agreed construction times,
impacts on traffic and services and other relevant issues.
h. identification of complaint management procedures including:
i. Contact details for the on-site manager.
ii. Dispute resolution procedures.
5 Council must be contacted at least 5 working days prior to any works commencing to
organise a pre-start meeting. The contact number to arrange a pre-start meeting is Diogo
Carrico on ph.53296465. The pre-start meeting must include:
a. The relevant parties for any Civil Engineering and Building works.
b. A representative of the Body Corporate.
The applicant must provide copies of the approved construction and traffic
management plans for the attendees at the prestart meeting.
Frontage Condition Report
6 A condition report including photographs of the frontage of the site must be completed and
submitted to council at the prestart meeting and prior to any works commencing.
General Requirements
7 Any conflict between the development and an existing or proposed service must be referred
to the relevant service authority for determination prior to commencement of works.
8 The developer must meet any costs to repair damage to any Council asset during
construction where damage is a result of the development works. Damage to assets must
be repaired immediately where it creates a hazard to the community. In circumstances where
the damage does not create a hazard to the community, it must be repaired immediately on
completion of the works associated with the development.
Performance Bond
9 Deleted.
Performance Bond
10 Security in the form of a cash bond or trading bank guarantee to the sum of $4000 must be
submitted to Council, to secure performance of all conditions of this approval, prior to the
issue of a Development Permit for Building Works. The cash bond or trading bank guarantee
will be returned on performance of the conditions of approval less any costs incurred by
Council in respect of enforcing performance of this permit. Council reserves the right to call
upon the bond or guaranteed sum to effect compliance with conditions.
Building Appearance
11 All air conditioning units or other mechanical equipment must be fully enclosed or screened
such that they are not visible externally from adjoining land uses.
Privacy – Unit 17
12 To ensure privacy is protected between adjoining units, the kitchen window located on Level
1 must either:
a. have a minimum window sill height or 1.7 metres above floor level; or
Page 7 of 14
Document Set ID: 22058500
Version: 4, Version Date: 04/08/2022
Page 8
b. be fitted with opaque glazing.
13 The balcony located on Level 1 and the roof top terrace must include either balustrading or
fixed external screens, positioned in such a way to obscure direct views into the habitable
room windows or private open space areas of the adjoining units.
Noise
14 Written certification is required from a suitably qualified person confirming that sound
pressure levels from all mechanical plant and equipment comply with the following:
a. Air-conditioning
7am to 10pm: Maximum level allowable = background + 5dB(A)
10pm to 7am: Maximum level allowable = background + 3dB(A)
b. Pumps/spa equipment
7am to 7pm: Maximum level allowable = background + 5dB(A)
7pm to 10pm: Maximum level allowable = background + 3dB(A)
10pm to 7am: No audible noise.
15 The certification must be submitted to Council at the completion of the building works, which
certifies that operational noise from any fixed plant and equipment complies with the
requirements of this Decision Notice.
Landscaping Works
16 The Cocos palm on Lot 17 must be removed prior to construction works commencing on site.
17 The Hills Fig tree on Lot 17 may be removed as part of preparing the site for construction.
18. The development site must be landscaped generally in accordance with Planning Scheme
Policy PSP03 – Landscaping Plants and guidelines and the following requirements:
a. Lot 17 - 2 x 45L Small Leaf Lilly Pilly’s (Syzygium luehmannii) planted in the general
location of the vegetation approved for removal.
b. Lot 17-3 x 45L trees listed in the PSP03 suitable for the Noosa Heads locality must be
planted between the building and the northern boundary and north western corner of
Lot 17 that grow to a maximum height of 7 metres.
c. Lot 19 - the works as generally shown on the approved Landscape concept plan as
prepared by Louise Custance except for the usage of exotic species and include 2
advanced local native tree species in a pot size of no less than 45L that grow to a
maximum height of 7 metres.
d. Lot 19 – Landscaping must be provided between the building and western boundary
that grow (on average) to a maximum height of 5 metres in order to soften the built
form where viewed from the west.
19. All landscape works must be established and maintained in accordance with the approved
design for the life of the development, and in a manner that ensures healthy, sustained and
vigorous plant growth. All plant material must be allowed to grow to full form and be
refurbished when its life expectancy is reached.
20. Landscape works must be completed prior to the commencement of the approval use.
21. Vegetation to be retained must be protected from clearing or construction activities by:
a. clearly marking vegetation to be retained with flagging tape
b. installing protective fencing around the drip line of the vegetation
c. restricting stockpiling, storage and vehicle parking to those areas which are
already cleared
d. using low impact construction techniques around vegetation.
Page 8 of 14
Document Set ID: 22058500
Version: 4, Version Date: 04/08/2022
Page 9
Damage to Services and Assets
22. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
Flood
23. In response to the potential flood risks, material and surface treatments below the defined
flood event must be resilient to water damage and do not include wall cavities that are
susceptible to the intrusion of water.
24. No habitable rooms are to be located on the ground floor.
Demolition
25. Security to the value of $5,000 must be provided to Council’s Building and Plumbing Services
prior to the issue of the Development Approval for Building Works – demolition of Unit 17 &
19. The security must be in the form of a cash bond or bank guarantee, for security against
satisfactory completion of works.
26. Any damage to footpaths, street plantings, natural vegetation/trees kerb and channel,
bridges or roadways at the removal site, the new site or between the sites must be repaired
or reinstated to at least pre-existing conditions.
27. All waste materials are removed from site.
28. Litter, erosion and sediment control measures are to be installed and/or maintained until soils
are stabilised by vegetation or sealed. NB: it is an offence under the Environmental Protection
Act 1994 to deposit or potentially allow litter, waste, soil, or other contaminants to enter a
waterway or storm water drainage system (e.g. roadside gutter).
29. Removal of building materials containing asbestos must be undertaken by a licensed
asbestos removalist.
30. Asbestos removal work (Section 466) of the Work Health and Safety Regulation
2011 requires a licensed asbestos removalist to give notice to Workplace Health and Safety
Queensland (WHSQ) of licensed asbestos removal work at least five days before the work
commences. Notification must be made using Form 65: Notification of licensed asbestos
removal work, demolition work or emergency demolition.
31. All building materials containing asbestos products are wrapped and disposed of in
accordance with the Public Health Regulation 2006 and the Environmental Protection
Regulation 2008. NB: Asbestos is a Regulated Waste. The Department of Environment &
Science licenses businesses that transport asbestos waste, and landfills that accept this
waste.
32. All building materials containing asbestos, including asbestos cement sheeting or roofing and
lagging are removed from the building prior to demolition/relocation.
33. It is a requirement of the ‘Plumbing and Drainage Regulation 2019’ that at demolition of a
building classed 1-10, the existing sanitary drain upstream from the connection point for a
service provider’s sewerage system must be sealed water tight. This work is deemed as
Notifiable Work and must be carried out by a suitably licenced plumber who shall submit an
As Constructed plan and Form 4 (Notifiable Works Form) to the QBCC (Queensland Building
Construction Commission) within 10 days of completing the work.
Page 9 of 14
Document Set ID: 22058500
Version: 4, Version Date: 04/08/2022
Page 10
Special conditions relating to the redevelopment of Unit 19 only – 4 March 2021
34. The Level 1 balcony is to be setback 0.5 metres from the western boundary and 3.5 metres
from the northern boundary.
35. All parts of the building must be wholly contained within Lot 19 with the exception of
structures in the exclusive use area as stipulated by the Community Management Statement
for the site.
36. The storage room on the ground level is not to be used as a bedroom or as any other
habitable room.
Additional Conditions specific for Lot 30 (and the use of Lots 7 & 11 for construction
and access) – 21 October 2021
Performance Bond - Planning
37. Security in the form of a cash bond or trading bank guarantee to the sum of $10,000 must
be submitted to Council, to secure performance of all conditions of this approval, specifically
for Lot 30, prior to the issue of a Development Permit for Building Works. The cash bond or
trading bank guarantee will be returned on performance of the conditions of approval less
any costs incurred by Council in respect of enforcing performance of this permit. Council
reserves the right to call upon the bond or guaranteed sum to effect compliance with
conditions.
Performance Bond – Demolition
38. Security to the value of $10,000 must be provided to Council’s Building and Plumbing
Services prior to the issue of the development approval for building works (demolition). The
security must be in the form of a cash bond or bank guarantee, for security against
satisfactory completion of works.
Landscaping
39. The development site must be landscaped generally in accordance with the approved plans
and Planning Scheme Policy PSP2 – Landscaping, and the following requirements:
a. A minimum of a 1m wide garden with dense landscaping must be provided to the north,
south and western boundaries within Lot 30.
b. The 1m wide garden must consist of 45 litre pot size native trees planted at 1.5m
centres. Include 1 x 100 litre pot size tree to be planted in each of the following
locations:
i. south east corner; and
ii. half way along the southern boundary; and
iii. to the west of the visitor car space where the lot dog legs.
c. The plantings must grow to an average minimum height of 10m and be suitable native
species for the urban surroundings such as Syzygium, Elaeocarpus, Acronychia.
d. All landscape works must be established and maintained in accordance with the
approved design for the life of the development, and in a manner that ensures healthy,
sustained and vigorous plant growth. All plant material must be allowed to grow to full
form and be refurbished when its life expectancy is reached.
e. Landscape works must be completed prior to the commencement of the use of Lot 30.
40. The Fig tree, Umbrella, Exotic and Palm trees as shown on Plan No. 18-4767AA prepared
by Max Watterson & Associates may be removed within the lot as part of preparing the site
for construction.
41. Any vegetation to be retained must be protected from clearing or construction activities by:
a. clearly marking vegetation to be retained with flagging tape;
b. installing protective fencing around the drip line of the vegetation;
Page 10 of 14
Document Set ID: 22058500
Version: 4, Version Date: 04/08/2022
Page 11
c. restricting stockpiling, storage and vehicle parking to those areas which are already
cleared; and
d. using low impact construction techniques around vegetation.
Privacy
42. The level 1 and level 2 operable timber privacy screens when fully extended must not cover
more than 50% of each of the balconies. The privacy screens on Level 3 must be a minimum
height of 1.7m above the FFL.
43. The balcony located on Level 2 and the roof top terrace must include balustrading (set back
as shown on the approved plans), and fixed external screens (where appropriate), positioned
in such a way to obscure direct views into the habitable room windows or private open space
areas of the adjoining units.
Building Appearance
44. The building must be constructed to be generally in accordance with the material and colour
palette as shown on Plan no. SD.102, Issue P2 and prepared by Gerard Smith Design.
5. REFERRAL AGENCIES
Not applicable.
6. ADVISORY NOTES
Infrastructure Charges
1. All developments and/or changes to existing developments may require payment of
“Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
made pursuant to the planning legislation and regulations current at the time of issue.
Equitable Access and Facilities
2. The plans for the proposed building work have NOT been assessed for compliance with the
requirements of the National Construction Code - Building Code of Australia (Volume 1) as
they relate to people with disabilities. Your attention is also directed to the fact that in addition
to the requirements of the National Construction Code as they relate to people with
disabilities, one or more of the following may impact on the proposed building work:
a. the Disability Discrimination Act 1992 (Commonwealth);
b. the Anti-Discrimination Act 1991 (Queensland); and
c. the Disability (Access to Premises – Buildings) Standards.
Sustainability
3. In line with Noosa Council’s Corporate Plan, Council seeks to encourage sustainable building
design for residential and commercial development. Council encourages the use of
sustainable building materials, energy efficient fittings, solar hot water, photovoltaic systems
(including the use of inverter/charges), water saving devices and rainwater harvesting. For
further information go to http://www.noosa.qld.gov.au/sustainable-homes
Demolition
4. The lodgement of security will attract a separate administration fee which must be paid at the
time of lodgement of the security.
Upon completion of the demolition works, the release of the security will be subject to the
following:
Satisfactory final site inspection by Council;
Confirmation that all relevant conditions have been met;
Receipt of the compliance certificate for the final stage of building work (e.g. Form 21
Final Inspection Certificate); and
Page 11 of 14
Document Set ID: 22058500
Version: 4, Version Date: 04/08/2022
Page 12
Receipt of the Form 4 (Notifiable Works Form).
7. PROPERTY NOTES
Not applicable.
8. VARIATION APPROVAL DETAILS
Not applicable.
9. FURTHER DEVELOPMENT PERMITS REQUIRED
Development Permit for Building Work.
10. SUBMISSIONS
Application – 51983.3225.14
There were 16 properly made submissions about the application. In accordance with the Planning
Act 2016, the name, address and electronic address of the principal submitter for each properly
made submission is provided and attached.
11. RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Planning Act 2016 is attached.
During the appeal period, you as the applicant may suspend your appeal period and make written
representations to Council about the conditions contained within the development approval. If
Council agrees or agrees in part with the representations, a negotiated decision notice will be
issued. Only one negotiated decision notice may be given.
12. OTHER DETAILS
If you wish to obtain more information about the decision, electronic copies are available on line at
www.noosa.qld.gov.au or at Council Offices.
Yours faithfully,
Lisa Pienaar
Development Planner
Enc: Appeal Rights
Approved Plans/Documents
cc. Unitywater
DECISION NOTICE HISTORY
Original Decision Notice – October 1983
Decision Notice – Change to existing approval - 15 June 2006 - with additional conditions
Decision Notice – Change to existing approval - 11 November 2014 - with additional conditions
Decision Notice – Change to existing approval - 12 October 2015 - with change to condition 2.
Decision Notice – Change to existing approval - 17 March 2016 - with change to condition 2.
Decision Notice – Change to existing approval - 12 May 2016 - with change to DA (redevelopment of Unit 15).- include additional
conditions 6-15.
Decision Notice – Change to existing approval - 29 March 2017 - with change to condition 2 (Unit 20).
Page 12 of 14
Document Set ID: 22058500
Version: 4, Version Date: 04/08/2022
Page 13
Decision Notice – Change to existing approval –5 April 2017 - with change to condition 2, in relation to a condition placed on 5 April
2017 approval incorrectly (Unit 13) and agree to remove condition 9 on 10 May 2017
Decision Notice – Change to existing approval –1 August 2017 - with change to condition 2 (Unit 20 & Unit 5)
Decision Notice - Minor – 51983.3225.11 – 27 April 2018 - with an amendment to condition 2 (Unit 21).
Decision Notice - Minor – 51983.3225.12 – 19 November 2020 - with an amendment to condition 2 (Unit 17), with additional
conditions 10-33.
Decision Notice - Minor – 51983.3225.13 – 4 March 2021 - with an amendment to condition 2 (Unit 19) & 18, admin amendments
to conditions 16, 17 & 18 with additional conditions 34, 35 & 36 (Unit 19)
Decision Notice – Other Change – 51983.3225.14 – 21 October 2021 – amend condition 1, include additional conditions 37-44;
amend existing condition 25; include an administrative amendment to existing conditions 12 & 13
Decision Notice – Minor – 51983.3225.15 – 1 August 2022; amend condition 1
Page 13 of 14
Document Set ID: 22058500
Version: 4, Version Date: 04/08/2022
Page 14
Appeal Rights
PLANNING ACT 2016 & PLANNING REGULATION 2017
Chapter 6 Dispute resolution (3) The appellant or, for an appeal to a tribunal, the registrar must,
within the service period, give a copy of the notice of appeal to –
Part 1 Appeal rights
(a) the respondent for the appeal; and
229 Appeals to tribunal or P&E Court
(b) each co-respondent for the appeal; and
(1) Schedule 1 of the Planning Act 2016 states –
(c) for an appeal about a development application under schedule
(a) Matters that may be appealed to –
1, table 1, item 1 – each principal submitter for the
(i) either a tribunal or the P&E Court; or development application; and
(ii) only a tribunal; or (d) for and appeal about a change application under schedule 1,
table 1, item 2 – each principal submitter for the change
(iii) only the P&E Court; and
application; and
(b) The person-
(e) each person who may elect to become a co-respondent for the
(i) who may appeal a matter (the appellant); and appeal, other than an eligible submitter who is not a principal
submitter in an appeal under paragraph (c) or (d); and
(ii) who is a respondent in an appeal of the matter; and
(f) for an appeal to the P&E Court – the chief executive; and
(iii) who is a co-respondent in an appeal of the matter; and
(g) for an appeal to a tribunal under another Act – any other
(iv) who may elect to be a co-respondent in an appeal of the
person who the registrar considers appropriate.
matter.
(4) The service period is –
(2) An appellant may start an appeal within the appeal period.
(a) if a submitter or advice agency started the appeal in the P&E
(3) The appeal period is –
Court – 2 business days after the appeal has started; or
(a) for an appeal by a building advisory agency – 10 business
(b) otherwise – 10 business days after the appeal is started.
days after a decision notice for the decision is given to the
agency; or (5) A notice of appeal given to a person who may elect to be a co-
respondent must state the effect of subsection (6).
(b) for an appeal against a deemed refusal – at any time after the
deemed refusal happens; or (6) A person elects to be a co-respondent by filing a notice of election,
in the approved form, within 10 business days after the notice of
(c) for an appeal against a decision of the Minister, under chapter
appeal is given to the person.
7, part 4, to register premises or to renew the registration of
premises – 20 business days after a notice us published under 231 Other appeals
section 269(3)(a) or (4); or
(1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
(d) for an appeal against an infrastructure charges notice – 20 the Supreme Court decides a decision or other matter under this
business days after the infrastructure charges notice is given Act is affected by jurisdictional error, the decision or matter is non-
to the person; or appealable.
(e) for an appeal about a deemed approval of a development (2) The Judicial Review Act 1991, part 5 applies to the decision or
application for which a decision notice has not been given – matter to the extent it is affected by jurisdictional error.
30 business days after the applicant gives the deemed
(3) A person who, but for subsection (1) could have made an
approval notice to the assessment manager; or
application under the Judicial Review Act 1991 in relation to the
(f) for any other appeal – 20 business days after a notice of the decision or matter, may apply under part 4 of that Act for a
decision for the matter, including an enforcement notice, is statement of reasons in relation to the decision or matter.
given to the person.
(4) In this section –
Note – decision includes-
See the P&E Court Act for the court’s power to extend the appeal
(a) conduct engaged in for the purpose of making a decision; and
period.
(b) other conduct that relates to the making of a decision; and
(4) Each respondent and co-respondent for an appeal may be heard
in the appeal. (c) the making of a decision or failure to make a decision; and
(5) If an appeal is only about a referral agency’s response, the (d) a purported decision; and
assessment manager may apply to the tribunal or P&E Court to
(e) a deemed refusal.
withdraw from the appeal.
non-appealable, for a decision or matter, means the decision or
(6) To remove any doubt. It is declared that an appeal against an
matter-
infrastructure charges notice must not be about-
(a) is final and conclusive; and
(a) the adopted charge itself; or
(b) may not be challenged, appealed against, reviewed, quashed,
(b) for a decision about an offset or refund-
set aside or called into question in any other way under the
(i) the establishment cost of trunk infrastructure identified in Judicial Review Act 1991 or otherwise, whether by the
a LGIP; or Supreme Court, another court, a tribunal or another entity; and
(ii) the cost of infrastructure decided using the method (c) is not subject to any declaratory, injunctive or other order of
included in the local government’s charges resolution. the Supreme Court, another court, a tribunal or another entity
on any ground.
230 Notice of appeal
232 Rules of the P&E Court
(1) An appellant starts an appeal by lodging, with the registrar of the
tribunal or P&E Court, a notice of appeal that- (1) A person who is appealing to the P&E Court must comply with the
rules of the court that apply to the appeal.
(a) is in the approved form; and
(b) succinctly states the grounds of the appeal. (2) However, the P&E Court may hear and decide an appeal even if
the person has not complied with the rules of the P&E Court
(2) The notice of appeal must be accompanied by the required fee.
Page 14 of 14