Skip to the record
NoosaWatch™: The source of truth.

Council archive · source document

Attachment 16- Amended Stormwater Management Plan MCU12/0208

of 66

Check the original when the exact wording matters.

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
Noosa on Weyba
Stormwater Management Plan




4              Integrated Water Cycle Management Plan

An Integrated Water Cycle Management Plan (IWCMP) has been prepared by Gilbert and Sutherland as part
of the Noosa on Weyba development (refer IWCMP, Gilbert and Sutherland, August 2012).
The ICWMP considered several servicing options for the development. The Gilbert and Sutherland report
recommends Option 4 as the preferred servicing strategy. In summary:
“Option 4 assumes sewage is treated off-site at the Noosaville STP and maximises rainwater harvesting at
each residence. It is typical of IWCWMP systems in high rainfall areas which achieve a reasonable reduction
in potable water demands.
     Domestic water supply: sourced from the municipal supply and domestic rain tanks (for toilet cisterns
      and laundry);
     Wastewater management: sewerage from development precincts to the Noosaville STP;
     Domestic garden irrigation supplied from the domestic rain tanks;
     Roof tank overflow and stormwater flows through bio-retention swales and basins, prior to creek
      discharge.”
The recommendations of the IWCMP will be adopted as part of the WSUD strategy for the site. Rainwater
harvesting will be maximised through the connection of all available roof area to the tank and the utilisation
of rainwater tank sizes around twice the size prescribed by the Queensland Development Code (QDC).
Collected rainwater will be used for irrigation, toilet flushing and laundry purposes. This will significantly
reduce the potable water demand of the site. The MUSIC modelling has conservatively assumed that the
tanks would only be used for domestic irrigation purposes for standard residential precincts and open space
irrigation of the other communal precincts. Due to the large size of the rainwater tanks being proposed they
could also be used to irrigate the remaining open space areas on site, which would further reduce the
potable water demand and reduce the volume of stormwater being discharged from the site.
The installation of water efficient devices and appliances has also been assumed.
Stormwater flows will be treated to the required WQOs prior to being released into the gullies and waterway
corridors located within the site. These areas will be rehabilitated and will provide some additional polishing
of stormwater prior to release into Lake Weyba.




Northbrook Corporation Pty Ltd                     Version 4                                  16 September 2013
SMP_v4.docx                                  Commercial in Confidence                                   Page 6

Used in these records

About this file

File size
10.0 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment 16- Amended Stormwater Management Plan MCU12_0208.pdf · 10.0 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.