Stormwater Management Plan




6              Proposed WSUD Strategy

6.1            Summary
The proposed WSUD features are shown in Figures 3, 4 and 5. In summary the WSUD strategy for the site
included:
     Community Education. The most effective treatment measure is to reduce the source of pollutants.
      Therefore community education is proposed so that residents are informed about what they can do to
      reduce their impact on their surrounding environment. Information signs will be located at stormwater
      devices. An information leaflet will be distributed to each residence prior to the wet season each year.
      An example of the information leaflet is contained in Appendix C. As the development is a Community
      Title Scheme the body corporate will also be able to instigate appropriate measures to reduce pollutant
      loads from communal areas.
     Reducing Potable Water Demand. Water efficient devices and appliances will be installed in each
      residence. Drought tolerant gardens will also be recommended.
     Providing an Alternative Water Source. All practically available roof area will be connected to
      rainwater tanks that will be larger than QDC requirements, so as to maximise rainwater harvesting on
      site, minimise potable water demand and reduce the volume of stormwater discharged from site.
      Rainwater tanks will be used for toilet flushing, laundry and irrigation purposes.
     Bio-retention Basins. Bio-retention basins are located at the end of the stormwater line, upstream of
      the point of discharge from the site. Stormwater ponds in the basins before slowly percolating through
      the vegetated filtration media and being treated through bio-filtration processes. Filtered stormwater is
      collected by perforated pipes and the discharged from site. Coarse sediment forebays will be located at
      the inlet points to capture sediment and prevent blockage of the filter media.
     Bio-retention Gardens.      Bio-retention gardens are small bio-retention basins that double as
      landscaped areas within the road reserve. They will treat runoff through bio-filtration before it is
      discharged to the stormwater system. Bio-retention gardens are suitable is relatively flat areas.
     Bio-retention Tree Pits. Bio-retention tree pits are trees located within filter media within the road
      reserve. They can provide some pre-treatment of runoff from the road prior to it being discharged to the
      stormwater system. Additional treatment will be required downstream. Tree-pits can be located in
      moderately sloped areas.
     Bio-retention Swales. Bio-retention swales are like standard vegetated swales but with a filter media
      layer to provide additional treatment of stormwater. They are typically located along road-sides and can
      be used in flat to moderately sloped areas (around 2 percent).
     Vegetated Swales. Vegetated swales will be used where underdrainage or slope requirements make
      the use of bio-retention swales impractical.
     Litter Baskets. Bio-retention basins and gardens are generally sufficient to capture any gross
      pollutants or litter from urban areas. However, as an additional treatment measure litter baskets will be
      installed on the field inlets of bio-retention gardens, swales and basins, as well as any other stormwater
      outlet discharging to the receiving waterways.
     Revegetation of Lake Weyba Buffer Area. A 40 metre wide lake buffer will be located along Lake
      Weyba. This will provide additional treatment of stormwater that may overflow from the adjacent bio-
      retention swales located in the 10 metre stormwater treatment zone. The buffer area, which has mostly
      been cleared of vegetation for use as cattle grazing, will be revegetated, which will improve its
      performance as a buffer treatment area, and improve bank stabilisation.




Northbrook Corporation Pty Ltd                     Version 4                                   16 September 2013
SMP_v4.docx                                  Commercial in Confidence                                   Page 13

Used in these records

About this file

File size
10.0 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment 16- Amended Stormwater Management Plan MCU12_0208.pdf · 10.0 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.