RACV Noosa – Construction
Management Plan
Contents
Project Details .............................................................................................................................................................................................................2
Site Environmental Management Plan (SEMP) ....................................................................................................................................3
Part A - SEMP Cover Form ................................................................................................................................................................................. 4
Part B - Management Plans...............................................................................................................................................................................7
Part C - Site Rehabilitation Plan ......................................................................................................................................................................7
Tree Management Plan ........................................................................................................................................................................................7
Appendix 1 - Construction Management Plan.......................................................................................................................................7
Appendix 2 - Work Health and Safety Management Plan ............................................................................................................10
Appendix 3 – Pedestrian and Traffic Management Plan ................................................................................................................. 11
Appendix 4 - Emergency Management Plan....................................................................................................................................... 15
P.O. Box 320, Eudlo E. [email protected]
Queensland, 4554, P. 0408 011 584 | ABN 18 766 198 454
Australia www.biodiverse-environmental.com.au
FLORA | FAUNA | REHABILITATION | FIRE | WATER
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 14 pages
Page 2
Project Details
Client details Noosa Council
Site address 94 Noosa Drive, Noosa Heads, Queensland, 4567
Description Tree removal as per the ‘Site Plan – Tree retention vs removal
plan’. Dated 24/11/2025
Access point/s Via Sanctuary drive entrance to RACV resort.
if applicable
Proposed start date February 2026 Completion date April 2026
Biodiverse Environmental Project Manager
Name Kate Seehuusen
Position Principal Botanist and Natural Area Lead
Phone 0400 075 354
Email [email protected]
Authorisation
As a representative of the company in control of the site, I have authorisation to
sign these site plans on behalf of Biodiverse Environmental and take responsibility
for ensuring compliance with our commitment specified herein and any relevant
legislation.
Name and Position Kate Seehuusen – Principal Botanist and Natural Area Lead
Signature
Date 02/02/2026
P.O. Box 320, Eudlo E. [email protected]
Queensland, 4554, P. 0408 011 584 | ABN 18 766 198 454
Australia www.biodiverse-environmental.com.au
FLORA | FAUNA | REHABILITATION | FIRE | WATER
Page 3
Site Environmental Management Plan (SEMP)
Introduction
This Site Environmental Management Plan (SEMP) details the potential environmental impacts of the
proposed use and development and the ways that these impacts may be reduced by management
strategies and practices. The objectives of this SEMP are to address environmental, council guidelines
and rehabilitation requirements and ensure that potential environmental impacts are prevented or
mitigated.
A copy of the SEMP must be kept on site at all times during the construction period.
The following has been submitted as part of the SEMP package:
Part A - SEMP Cover Form
Part B - Attachments - Construction Management Plan, WHS Construction Safety Plan, Traffic
Management Plan
Part C - Site Rehabilitation Plan including rehabilitation areas and other necessary documentation
P.O. Box 320, Eudlo E. [email protected]
Queensland, 4554, P. 0408 011 584 | ABN 18 766 198 454
Australia www.biodiverse-environmental.com.au
FLORA | FAUNA | REHABILITATION | FIRE | WATER
Page 4
Part A - SEMP Cover Form
Site Location
94 Noosa Drive, Noosa Heads, Queensland, 4567
Project Description
The scope of works includes tree clearing as per the ‘Site Plan – Tree retention vs removal plan’. Dated
24/11/2025
Project Management
Biodiverse Environmental Kate Seehuusen Phone 0400 075 354
Construction Schedule
Identify correct location of all boundaries and services prior to commencement of works
Locate and identify trees to be removed according to the tree plan
Remove and chip trees using a suitably qualified arborist under supervision to be completed
within 1 month after OPW permit being issued
Construction Techniques/Activities
Suitably qualified arborist team will be engaged to remove trees identified by the Site Plan – Tree
retention vs removal plan’. Dated 24/11/2025.
Climbing arborists will be utilised to ‘piece down’ trees to ensure that there is no off target damage to
retained trees.
A mobile chipping truck (approx. 12m3) and potentially an EWP (Elevated Work Platform) will be used to
complete the tree removal works. A grab will be used to move logs to the chipper.
P.O. Box 320, Eudlo E. [email protected]
Queensland, 4554, P. 0408 011 584 | ABN 18 766 198 454
Australia www.biodiverse-environmental.com.au
FLORA | FAUNA | REHABILITATION | FIRE | WATER
Page 5
Site Safety and Environmental Risks
RISK MEASURES TO ADDRESS RISK
Outdoor work and work in public Set up exclusion zones, signs and spotters
spaces
Sun safe clothing and correct PPE
Water and amenities available
Take adequate break in the shade
First Aid kit and qualified first aid provider onsite
Exclude public from site – barriers/cones
Using powered tools – brush Set up exclusion zones, signs and spotters
cutters, whippers, blowers,
chainsaws etc. Use the most appropriate tool for the task
Induction/training for use
Rotate the task to reduce fatigue and share the heavier
work around
Use correct PPE
Check maintenance of plant and equipment
Clean up and make the area safe at the end of the job
Follow all relevant SWMS
Working with/near heavy Inspect site prior to work commencing to identify and
machinery
remove hazards
Ensure operators are licensed
Follow work plans and instructions, ensure pre-start
meeting
Use UHF radios to maintain positive communication
Where practical, eliminate the need for people working
within heavy machinery zone, or if unavoidable have
pre-arranged signals and knowledge of movements
and maintain direct liaison between relevant parties
Work up-wind or out of fume/dust range
Only approach machinery at a standstill and never
from the rear
Working with/near animals Provide appropriate animal handling training
Site Environmental Values
As per Site Plan – Tree retention vs removal plan’. Dated 24/11/2025
As per Weed Management Plan.
P.O. Box 320, Eudlo E. [email protected]
Queensland, 4554, P. 0408 011 584 | ABN 18 766 198 454
Australia www.biodiverse-environmental.com.au
FLORA | FAUNA | REHABILITATION | FIRE | WATER
Page 6
Project Monitoring
Photographs will be taken of the site at times prior to, during and following the construction period and
supplied to the responsible authority on request to demonstrate compliance with the SEMP. Progress
reports and photographic recordings are to be taken from locations determined by Site Supervisor and
Project Manager.
Declaration
I agree to ensure that:
All site and environmental protection measures outlined within the approved SEMP will be adhered
to.
All endorsed plans will be adhered to.
All site rehabilitation and revegetation works will be undertaken in accordance with the approved
SEMP.
Prior to construction personnel commencing work, the site supervisor will ensure:
An appropriate site induction has been undertaken
Equipment/Plant will be serviced off-site.
All equipment will be cleaned and free of vegetation, soil and seed prior to being brought on to the
site.
Advice will be obtained from the ‘Dial Before You Dig’ service to determine the location of existing
services onsite.
Kate Seehuusen
Full Name Signature
Date: 02/02/2026
P.O. Box 320, Eudlo E. [email protected]
Queensland, 4554, P. 0408 011 584 | ABN 18 766 198 454
Australia www.biodiverse-environmental.com.au
FLORA | FAUNA | REHABILITATION | FIRE | WATER
Page 7
Part B - Management Plans
Construction Management Plan: See Appendix 1
WHS Management Plan: See Appendix 2
Pedestrian and Traffic Management Plan: See Appendix 3
Emergency Management Plan: See Appendix 4
Part C - Site Rehabilitation Plan
Erosion and sedimentation controls where applicable will be managed in accordance with local
authority requirements to prevent sediment-laden water from entering any sewer, drainage system or
natural waterway.
Controls will be implemented to protect pollution of watercourses from spoil and to prevent creation of
dust nuisance to adjoining neighbours. Construction work will be arranged such that exposed surfaces
are kept to a minimum at all times. Measures will be implemented to minimise the spread of mud on
vehicle tyres on adjoining roadways, including provision for on-site clean up if necessary.
Root balls will remain intact so soil disturbance is minimal. If deemed necessary, a mulch berm may be
installed to prevent any overland flow however due to the topography of the site and the removal
method being low impact this is likely a precautionary measure.
Tree Management Plan
The tree management plan identifies all trees within the project footprint which are to be retained or
removed. Trees to be removed will be identified using fluro marker paint in the form of a X. Trees will be
‘pieced down’ by climbing arborists and /or an EWP. Root balls will remain in the ground and heads will
be chipped.
Appendix 1 - Construction Management Plan
Construction works
Is construction in stages? Yes No
If Yes, give details of stages for demolition/excavation/construction
Identify correct location of all boundaries and services prior to commencement of works
Locate and identify trees to be removed according to the tree plan
Remove and chip trees using a suitably qualified arborist under supervision
Is a building permit required for the works? Yes No
P.O. Box 320, Eudlo E. [email protected]
Queensland, 4554, P. 0408 011 584 | ABN 18 766 198 454
Australia www.biodiverse-environmental.com.au
FLORA | FAUNA | REHABILITATION | FIRE | WATER
Page 8
Construction matters and measures to be implemented
Chemical Storage
Storage of Control measures for chemical storage to be implemented include:
chemicals such as Storing all chemicals in sealed containers in weatherproof lockable
herbicides, fuels storage
and surfactants Storing copies of SDS’ for all chemicals
Removing chemicals at the end of each day and safely storing them off
site
Providing spill kits onsite
Dust
Airborne Dust Dust control measures may include:
Earth moving management
Covering loads
Limiting cleared area
Site traffic control
Soil compaction
Watering sprays
Vegetative stabilisation
Noise
Noise associated Construction work that makes audible noise must be carried out under the
with construction following conditions:
including vehicles, Between the hours of 7am and 5pm, Monday to Friday
voices, workers Noise control measures to be implemented may include:
and radios etc. Maintaining all machinery and equipment in good working order
Locating noisy site equipment, where possible, being structures that act
as barriers or at a distance from noise sensitive areas
Orienting equipment so that noise emissions are directed away from
noise sensitive areas
RACV to give prior notification to the community and adjoining property
holders when noisy operations are to be conducted
RACV to implement complaint management process and procedures
Noise associated Regulated devices include such items as lawnmowers, generators, power tools
with regulated and compressors:
devises Are not to be operated before 7am and after 5pm, Monday to Friday or
on any other day at any time
Noise control measures to be implemented may include:
Maintaining all regulated devices in good working order
Orienting regulated devices so that noise emissions are directed away
from noise sensitive areas
Protection of Council assets (streets, footpaths, laneways and reserves)
Protection of Control measures to protect council assets such as streets, footpaths, laneways
Council assets and reserves include:
(streets, footpaths, Planning site usage to restrict vehicles from crossing gutters and
laneways and footpaths
reserves) Not overloading vehicles and ensuring gutters and footpaths are not
subject to potentially damaging loads
Protecting pavements and gutters with barriers
P.O. Box 320, Eudlo E. [email protected]
Queensland, 4554, P. 0408 011 584 | ABN 18 766 198 454
Australia www.biodiverse-environmental.com.au
FLORA | FAUNA | REHABILITATION | FIRE | WATER
Page 9
Parking
Near site parking Control measures to manage parking near site include:
Providing staff and contractors with details of available parking sites
(including a map if applicable) during works
RACV to provide parking for staff and contractors. Machinery will be
within the project footprint and away from pedestrians and vehicles
Signage
Signage Signage will be installed in prominent locations on the boundaries of the
site advising of the proposed development, the expected time frames
and the site contact details
Stormwater and sediment control
Stormwater and Stormwater and sediment control measures to implement include:
sediment laden Establishing and maintaining minimum number of entry/exit points for
runoff along roads, stabilized site access. Ideally this will be a single entry/exit point
drains and Establishing and maintaining barriers to divert rainwater from upslope,
footpaths etc. above the site, away from development area
Traffic Management
Road, Lane See Traffic Management Plan
Closures and
Mobile Cranes on
Council Land
Pedestrian and See Traffic Management Plan
cyclist access
around the site
and traffic on
adjoining roads.
Movement of See Traffic Management Plan
heavy vehicles to
and from the site
Trees and Vegetation
Protection of trees Control measures to protect trees and vegetation onsite include:
and vegetation Identifying all trees and vegetation to be protected during construction
onsite and performing a survey of these before and after works have taken
place
Establishing ‘no go’ areas with barriers
Tagging trees and plants that are to be protected
Waste Management
Waste material Control measures to manage waste material onsite include:
onsite Avoiding products that are over packaged to reduce waste
Minimising over estimation of materials required to reduce waste
Performing site clean-up, at least daily, to remove any litter/debris and
prevent building waste from blowing off site
Removal of Not applicable
hazardous waste
from site (if
applicable)
P.O. Box 320, Eudlo E. [email protected]
Queensland, 4554, P. 0408 011 584 | ABN 18 766 198 454
Australia www.biodiverse-environmental.com.au
FLORA | FAUNA | REHABILITATION | FIRE | WATER
Page 10
Appendix 2 - Work Health and Safety Management
Plan
Work Health and Safety matters and measures
Chemical Management
Chemical Risks associated with chemical use will be managed by:
Storage and Storing chemicals in accordance with relevant legislation and regulations
Use Using chemicals as per their label or approved off label usage
Ensuring all staff using chemicals have adequate and relevant training
Locating Safety Data Sheets (SDS) for all chemicals used are located in all
vehicles accessing the site
Emergency Procedures
Emergency An emergency evacuation plan has been developed, and a copy of this plan is
evacuation located on site
plan See Appendices for Emergency Plan Map
Emergency An emergency contact list has been developed, and a copy of this list is located on
contacts site
See Appendices for Emergency Plan Map
Emergency All vehicles are equipped with fire extinguishers. These are tested by an approved
equipment provider every 6 months.
Equipment
Use of Risks associated with equipment use will be managed by:
equipment Maintaining equipment in good working order
Tagging unsafe equipment and withdrawing them from service
Ensuring staff are licensed where required
Providing staff with required PPE
First Aid and injury management
First aid kits A maintained first aid kit is located in all vehicles and buildings
First aid kit locations are signed
First aid officers All site supervisors are trained to administer basic first aid
Seeking In the event that medical care must be sought the nearest doctor’s surgery
medical care is:
Clinic Name: Noosa Heads Medical
Address: Unit 1/16 Lanyana Way, NOOSA HEADS QLD 4567
Contact Number: 07 5489 8066
In the event that urgent medical care must be sought the nearest hospital is
located at:
Hospital: Noosa Hospital
Address: 111 Goodchap Street, NOOSAVILLE QLD 4566
Contact Number: 07 5455 9200
In the case of an emergency requiring an ambulance call 000
P.O. Box 320, Eudlo E. [email protected]
Queensland, 4554, P. 0408 011 584 | ABN 18 766 198 454
Australia www.biodiverse-environmental.com.au
FLORA | FAUNA | REHABILITATION | FIRE | WATER
Page 11
Incident Reporting
Reporting a Incident reporting is managed by:
hazard, injury Completing incident report forms if any hazard/injury/incident occurs, this
or incident includes near misses
Reporting incidents to site supervisors and SEMP Manager
Ensuring incident report forms are located in all vehicles accessing the site
Risk Assessment
Risk Risk is managed by a system of:
Management Workplace assessment
Hazard identification
Remedial action
Updating WHS
Documentation and reports that will be used in this process include:
Biodiverse Environmentals Job Safety analysis forms
Safe Work Method Statement - SWMS
Training and Induction
Documentation Training records will be maintained as evidence of training delivery and assessment
of competence
Generic WHS All staff have the skills and knowledge acquired from:
training General induction training
Using JSA forms
Risk specific Staff required to conduct activities with a specific health and safety risk have
WHS training completed relevant training for:
• First aid
Task specific Staff required to conduct activities with a specific health and safety risk have
WHS training completed training relevant to the project such as:
• Agricultural chemical use
• Chainsaw use
Appendix 3 – Pedestrian and Traffic Management Plan
Traffic matters and safety measures to be implemented
Traffic Management
Traffic If a formal traffic management plan is identified as being required for tree
Management Plan clearing works it will include the following:
i. a Traffic Management Control Plan in accordance with the Manual of Uniform
Traffic Control Devices (MUTCD) detailing all temporary signage and traffic
control measures prior to construction;
ii. maintenance of safe vehicle and pedestrian access for the areas affected by
the works during and after daily construction has ceased;
iii. proposed fencing to the site during the construction phase of the
development;
P.O. Box 320, Eudlo E. [email protected]
Queensland, 4554, P. 0408 011 584 | ABN 18 766 198 454
Australia www.biodiverse-environmental.com.au
FLORA | FAUNA | REHABILITATION | FIRE | WATER
Page 12
iv. approval of the Traffic Management Control Plan by the Department of
Transport and Main Roads (DTMR) for any works on State controlled roads; and
v. provision for worker car parking.
Council owned land
Work on road Permission will be sought from the relevant local Council if work is to be carried
reserves or out on a road reserve or Council owned land
council owned
land
Deliveries
Deliveries to site Safety measures to be implemented to ensure deliveries to the site are
undertaken in a safe manner include:
• Locating the delivery drop off point/s so that delivery vehicles do have to
cross the site
• Delivery drop off points to be clearly marked
• Deliveries to be scheduled outside of peak traffic and pedestrian times in
the area
Emergency Vehicle Access
Ambulance or Measures to be implemented to ensure emergency vehicles movement is not
fire vehicle impeded include:
access • Notifying emergency services of any road or lane closures
Hours of Operation
General Hours of Access to site by construction vehicles must be carried out between the hours of
Operation 7am and 5pm Monday to Friday.
Peak Measures to be implemented to ensure periods of peak vehicle and pedestrian
traffic/pedestrian traffic in the area adjoining the site include:
hours • Limiting vehicle access to the site during peak pedestrian traffic in the area
specifically on a business day between 7am and 5pm.
• Limiting vehicle access to the site during peak vehicle traffic in the area
specifically on a business day between 7am and 5pm
Parking
Parking for Control measures to manage parking near and onsite include:
workers and site • RACV to provide staff and contractors with details of available parking sites
visitors (including a map if applicable) during works
• Staff to commute together, limiting vehicles onsite
• Heavy machinery to park within the project footprint
Pedestrian and Cyclist Management
Pedestrian and Safety measures to be implemented to protect the safety of pedestrians onsite
cyclist access to include:
and onsite • Designated clearly marked pedestrian only walkways that are kept clear
• Designating and clearly signing ‘no-go’ zones into the site
• Implementing safe work distances
• Ensuring all workers and visitors wear high visibility clothing onsite
Public Transport
Effects on public Not applicable – Neither the construction of the site or the resultant traffic are
transport expected to affect public transport services or access to public transport services
services
P.O. Box 320, Eudlo E. [email protected]
Queensland, 4554, P. 0408 011 584 | ABN 18 766 198 454
Australia www.biodiverse-environmental.com.au
FLORA | FAUNA | REHABILITATION | FIRE | WATER
Page 13
Speed
Management of Measures to be implemented to ensure onsite vehicle speeds include:
onsite vehicle • Worksite speed limits set at 10km/h, or as indicated onsite
speed
Vehicle Movements
Heavy vehicle Measures to be implemented to ensure safe heavy vehicle access include:
access and • Assess site and trim low lying branches
mobile cranes • Spotter to guide machinery in and out of site.
Licensing and Measures to be implemented to ensure safe operation of vehicles include:
qualifications • Checking licenses and qualifications when recruiting drivers/operators or
hiring contractors
Site access Measures to be implemented to ensure safe access of vehicles include:
• Following entry and exit signage to the site
• Ensuring drivers driving out onto public roads can see both ways along a
footpath before they move onto it
• Ensuring vehicle access is staggered to prevent queuing on roads and
unnecessary disruption to traffic
Road and lane Road closures are not anticipated to be necessary as all of the works are contained
closures within the project footprint
Consultation with the project arborist will identify any needs for traffic control
and/or lane closures
Reversing Measures to be implemented to reduce the need for vehicles to reverse include:
vehicles • Installing a turning circle so vehicles can turn without reversing
When it is necessary to reverse:
• Using reversing sensors, cameras, mirrors and warning devices such as
reversing alarms
• Ensuring workers and site visitors are familiar with reversing areas
• Ensuring drivers who cannot see clearly behind have another person
directing them before reversing
Codes of Practice and Legislation applicable to this Plan
Legislation and Regulations
• Agricultural Chemicals Distribution Control Act 1996 and Regulation 1998
• Chemical Usage (Agricultural and Veterinary) Control Act 1998 and Regulation 1999
• Environmental Protection Act 1994
• Environment Protection and Biodiversity Conservation Act 1999 (Federal)
• Environment Protection and Biodiversity Regulations 2019 (Federal)
• Land Protection (Pest and Stock Route Management) Act 2002
• Local Government Act 2009
• Nature Conservation Act 1992
• Nature Conservation (Administration) Regulation 2017
• Nature Conservation (Wildlife) Regulation 2006
• Nature Conservation (Plants) Regulation 2020
• Nature Conservation (Animal) Regulation 2020
• Nature Conservation (Wildlife Management) Regulation 2006
• Nature Conservation (Protected Are Management) Regulation 2017
• Work Health and Safety Act 2011
• Work Health and Safety Regulation 2011
• Marine Safety (Domestic Commercial Vessel) National Law Act 2016 (National)
• Queensland Building and Construction Commission Act 1991 and Regulation 2003
P.O. Box 320, Eudlo E. [email protected]
Queensland, 4554, P. 0408 011 584 | ABN 18 766 198 454
Australia www.biodiverse-environmental.com.au
FLORA | FAUNA | REHABILITATION | FIRE | WATER
Page 14
• Transport Operations (Marine Safety) Regulation 2016
• Transport Operations (Marine Safety) Act 1994
• Transport Operations (Road Use Management) Act 1995 and Regulation 2009
• The Animal Care and Protection Act 2001
Codes of Practice
• First Aid in the Workplace Code of Practice 2021
• Hazardous Manual Tasks Code of Practice 2021
• How to Manage Work Health and Safety Risks Code of Practice 2021
• Managing Noise and Preventing Hearing Loss at Work Code of Practice 2021
• Managing Risks of Plant in the Workplace Code of Practice 2021
• Managing the Risk of Falls at Workplaces Code of Practice 2021
• Managing the Work Environment and Facilities Code of Practice 2021
• Occupational Diving Work Code of Practice 2005
• Preparation of Safety Data Sheets for Hazardous Chemicals Code of Practice 2021
• Traffic Management for Construction or Maintenance Work Code of Practice 2008
• Work Health and Safety Consultation, Co-operation and Co-ordination Code of Practice 2021
• Working near Overhead and Underground Electric Lines (worksafe.qld.gov.au)
SWMS Applicable to this Work Health and Safety Plan
SWMS Bush Regeneration
P.O. Box 320, Eudlo E. [email protected]
Queensland, 4554, P. 0408 011 584 | ABN 18 766 198 454
Australia www.biodiverse-environmental.com.au
FLORA | FAUNA | REHABILITATION | FIRE | WATER
Page 15
Appendix 4 - Emergency Management Plan
EMERGENCY EVACUATION PLAN
94 Noosa drive, Noosa Heads
Fire Extinguisher
First Aid Kit
Emergency Evacuation
Point
Important Numbers
Emergency: 000
Non-emergency: 13 74 68
Closest Doctor: Noosa Heads Medical (07) 5489 8066
Closest Hospital: Noosa Hospital (07) 54 559200
Poison Information Centre: 13 11 26
P.O. Box 320, Eudlo E. [email protected]
Queensland, 4554, P. 0408 011 584 | ABN 18 766 198 454
Australia www.biodiverse-environmental.com.au
FLORA | FAUNA | REHABILITATION | FIRE | WATER
Used in these records
Attachment 3 - Construction Management Plan.pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.3 MB (small file)
- File type
No other editions are linked here.