Minor Change Report MCU22 0087 01 (As Published)

of 34

Page text shows just the words. Original shows the document exactly as it was published.

                    Landscaping Setbacks
                    • Bottlebrush Ave         6 metres          4.5 metres (building)                         X
                                              (building)
                    • Berrima Row                               5.5 metres (building)                         X
                                              6 metres
                                                                1.5metres (swimming pool)                     X
                                              (building)
                                              2 metres
                                              (swimming
                                              pool)

                    Private Open Space        20m² min each     > 20m2 each                                   

                    Carparking                6 covered min 6 covered                                         
                                              inc 1 visitor min
                                              (development
                                              includes        1
                                              small dwelling
                                              and             2
                                              dwellings
                                              >100m² GFA).


               Existing Condition 2
                       Currency Period
               2.      This development approval lapses if the use has not happened by 21 July 2029, unless an
                       application to extend the currency period is approved by Council.
               Applicant’s Request
               The applicant has requested existing Condition 2 be amended and replaced with the following
               amended condition:
               Currency Period
               2.      This development approval lapses if the use has not happened by 21 July 2030, unless an
                       application to extend the currency period is approved by Council.
               Assessment of Request
               Agree
               The applicant requests to amend Condition 2 of the development approval to add an additional
               year to the currency period. The development has not commenced and in order to facilitate the
               development the additional year will allow further time for this to occur. As the applicant requests
               1 year and it is likely to be inconsequential the extension to the currency period is supported.
               Recommendation
               It is recommended existing condition 2 be amended to read as follows:
               Currency Period
               2.      This development approval lapses if the use has not happened by 21 July 2029 2030, unless
                       an application to extend the currency period is approved by Council.




                                                                                                    Page 18 of 34

Document Set ID: 23692796
Version: 12, Version Date: 20/11/2025
Log in to download the original file

Minor Change Report MCU22 0087 01 (As Published).pdf · 6.6 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.