RA6-N SARA reference: 2504-45768 SRA Council reference: MCU25/0038 & OPW25/0056 Applicant reference: 05063 30 April 2025 Chief Executive Officer Noosa Shire Council PO Box 141 Tewantin QLD 4565 [email protected] Attention: Mark Lewis Dear Mr Lewis SARA referral agency response—24 Wesley Court, Noosa Heads (Referral agency response given under section 56 of the Planning Act 2016) The development application described below was confirmed as properly referred by the State Assessment and Referral Agency (SARA) on 28 April 2025. Response Outcome: Referral agency response – with conditions Date of response: 30 April 2025 Conditions: The conditions in Attachment 1 must be attached to any development approval Advice: Advice to the applicant is in Attachment 2 Reasons: The reasons for the referral agency response are in Attachment 3 Development details Description: Development permit Operational work for prescribed tidal works (jetty) South East Queensland (North) regional office Level 4, Foundation Place 3 South Sea Islander Way, Maroochydore Page 1 of 7 PO Box 1129, Maroochydore QLD 4558
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 6 pages
Page 2
2504-45768 SRA
SARA role: Referral agency
SARA trigger: Schedule 10, Part 17, Division 3, Table 2, Item 1 (Planning Regulation
2017)
Development application for operational works within navigable
waterways
SARA reference: 2504-45768 SRA
Assessment manager: Noosa Shire Council
Street address: 24 Wesley Court, Noosa Heads
Real property description: 45N21844
Applicant name: Robert David & Catherine Ellen Martyr
Applicant contact details: 18 Ron Parkinson Crescent
Corbould Park QLD 4551
[email protected]
Human Rights Act 2019 A consideration of the 23 fundamental human rights protected under
considerations: the Humans Right Act 2019 has been undertaken as part of this
decision. It has been determined that this decision does not limit
human rights.
Representations
An applicant may make representations to a concurrence agency, at any time before the application is
decided, about changing a matter in the referral agency response (s.30 Development Assessment
Rules). Copies of the relevant provisions are in Attachment 4.
A copy of this response has been sent to the applicant for their information.
For further information please contact Rosanna Nobile, Planning Officer, on 07 5352 9777 or via email
[email protected] who will be pleased to assist.
Yours sincerely
Tony Croke
Principal Planner
cc Robert David & Catherine Ellen Martyr, [email protected]
enc Attachment 1 - Referral agency conditions
Attachment 2 - Advice to the applicant
Attachment 3 - Reasons for referral agency response
Attachment 4 - Representations about a referral agency response provisions
Attachment 5 - Documents referenced in conditions
State Assessment and Referral Agency Page 2 of 7
Page 3
2504-45768 SRA
Attachment 1—Referral agency conditions
(Under section 56(1)(b)(i) of the Planning Act 2016 the following conditions must be attached to any development
approval relating to this application) (Copies of the documents referenced below are found at Attachment 5)
No. Conditions Condition timing
Development Permit – Operational Work
Schedule 10, Part 17, Division 3, Table 2, Item 1 — Tidal works or work in a coastal management
district—The chief executive administering the Planning Act 2016 nominates the Director-General of
the Department of Transport and Main Roads to be the enforcement authority for the development to
which this development approval relates for the administration and enforcement of any matter relating
to the following conditions:
Approved plan
1. The development must be carried out generally in accordance with At all times
the following plan:
Site plan and water allocation prepared by Marine Structures
dated 4 March 2025 reference MS-05063-01, Revision C
Layout plan prepared by Marine Structures dated 4 March
2025 reference MS-05063-02, Revision B
Lighting
2. (a) Light/mark all vessels, structures, plant and equipment For the duration of
associated with: works and for
i. the works, in accordance with the following operation to be
specifications: maintained at all times
any anchors deployed must be marked with yellow
buoys and fitted with FL yellow lights fitted
lighting provided must not obscure, disguise or
otherwise interfere with the effectiveness of
navigational lighting.
ii. operations, in accordance with the following
specifications:
section 3 of AS4282-1997 Control of the obtrusive
effects of outdoor lighting
(b) Lighting provided must not obscure, disguise or otherwise
interfere with the safe navigation of other vessels, including the
effectiveness of navigational lighting.
Protection of navigable waterways
3. The construction, operation and maintenance of the pontoon and any For the duration of
ship berthed, moored or attached to the structure, must not: works, and at all times
(a) encroach into, pass over or under a navigation corridor
(b) be located in a high-risk maritime zone
(c) impede the safe navigation of other ships or boats
(d) restrict safe access to or from neighbouring structures.
4. Remove and dispose of any debris or similar obstruction For the duration or
encountered whilst undertaking the work at an appropriately licensed works
facility.
5. All piles and/or structure to be demolished both above and below the Prior to the completion
waterline must be completely extracted/removed. of the works
State Assessment and Referral Agency Page 3 of 7
Page 4
2504-45768 SRA
Attachment 2—Advice to the applicant
General advice
1. Terms and phrases used in this document are defined in the Planning Act 2016, its regulation
or the State Development Assessment Provisions (SDAP) (version 3.2). If a word remains
undefined it has its ordinary meaning.
State Assessment and Referral Agency Page 4 of 7
Page 5
2504-45768 SRA
Attachment 3—Reasons for referral agency response
(Given under section 56(7) of the Planning Act 2016)
The reasons for the SARA’s decision are:
The development application is for a development permit for operational work that is prescribed tidal
works for the installation of a jetty.
The development site is located at 24 Wesley Court, Noosa Heads (formally described as Lot 45 on
N21844) within a canal.
The proposed development has been assessed against and complies with State code 7: Maritime
Safety of the SDAP version 3.2, with conditions. In particular, the development:
o does not compromise the viable operation of aids to navigation
o does not compromise the safe operation of vessels in navigable waterways
Material used in the assessment of the application:
the development application material and submitted plans
Planning Act 2016
Planning Regulation 2017
the SDAP (version 3.2), as published by SARA
the Development Assessment Rules
SARA DA Mapping system
section 58 of the Human Rights Act 2019
State Assessment and Referral Agency Page 5 of 7
Page 6
2504-45768 SRA Attachment 4—Representations about a referral agency response provisions (page left intentionally blank) State Assessment and Referral Agency Page 6 of 7
Page 7
2504-45768 SRA Attachment 5—Documents referenced in conditions (page left intentionally blank) State Assessment and Referral Agency Page 7 of 7
Used in these records