Decision Notice - Approved by Delegation of Authority - OPW25 0073 (As Published) · OPW25/0073
4. ASSESSMENT MANAGER CONDITIONS
APPROVED PLANS
1. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
S4400379 P2 ELECTRICAL RETICULATION INSTALL 1x 28/04/2025
500kVA PMT TRANSFORMER, 4x PILLARS,
Sheet 1 of 7
AND 14x STREET LIGHTS
S4400379 P2 ELECTRICAL RETICULATION INSTALL 1x 28/04/2025
500kVA PMT TRANSFORMER, 4x PILLARS,
Sheet 2 of 7
AND 14x STREET LIGHTS
S4400379 P2 ELECTRICAL RETICULATION INSTALL 1x 28/04/2025
500kVA PMT TRANSFORMER, 4x PILLARS,
Sheet 3 of 7
AND 14x STREET LIGHTS
S4400379 P2 ELECTRICAL RETICULATION INSTALL 1x 28/04/2025
500kVA PMT TRANSFORMER, 4x PILLARS,
Sheet 4 of 7
AND 14x STREET LIGHTS
S4400379 P2 ELECTRICAL RETICULATION INSTALL 1x 28/04/2025
500kVA PMT TRANSFORMER, 4x PILLARS,
Sheet 5 of 7
AND 14x STREET LIGHTS
S4400379 P2 ELECTRICAL RETICULATION INSTALL 1x 28/04/2025
500kVA PMT TRANSFORMER, 4x PILLARS,
Sheet 6 of 7
AND 14x STREET LIGHTS
S4400379 P2 ELECTRICAL RETICULATION INSTALL 1x 28/04/2025
500kVA PMT TRANSFORMER, 4x PILLARS,
Sheet 7 of 7
AND 14x STREET LIGHTS
CURRENCY PERIOD
2. The Currency Period for this development approval lapses if the development has not
substantially started by 12 June 2027, unless an application to extend the currency period is
approved by Council.
Site Specific Conditions
3. Street lighting to be hooded or screened preventing light spill into adjoining properties. The
type of light pole and hood to match existing local road lighting in the area for continuity.
Bonds
4. A site control and/or compliance bond of $2000 must be submitted to Council prior to the
pre-start meeting. The pre-start meeting will only be held once Council's Construction
Engineering Officer has confirmation that the bond monies have been received by Council.
The bond will be refunded less any costs incurred by Council in ensuring compliance with
these conditions or any additional inspections incurred for substandard work or work
undertaken not in accordance with this permit.
Page 2 of 9
Document Set ID: 23811958
Version: 0, Version Date: 01/01/1900
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - Approved by Delegation of Authority - OPW25 0073 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 165 KB (small file)
- File type
No other editions are linked here.