Response to Information Request - MCU24-0074 · MCU24/0074

of 12

Text shows just the words. Original shows the document exactly as it was published.

Figure. 13 – Parking and manoeuvring plans

     34.     Provide supporting stormwater quality modelling (e.g. MUSIC) that
             demonstrates the proposed treatment train complies with the
             requirements of Performance Outcomes 1 & 6 of the Water Quality
             Drainage Code and achieves pollutant reduction targets of the State
             Planning Policy 2017.
     35.     Provide Standard Drawings and SQUIDEP certification for all proposed
             proprietary stormwater devices.
     36.     Amend the SMP to address Performance Outcome 2(a) of the Water
             Quality and Drainage Code which requires the development to
             “incorporate allowance for increased flood risk and tidal inundation
             through pipework as a result of climate change and sea level rise”.
     37.     Do not directly, indirectly or cumulatively cause adverse impacts external
             to the site.
     38.     Do not cause increased flooding, which adversely affects the safety or use
             of any land upstream or downstream.
     39.     Do not cause ponding of water on the site or nearby land.
     40.     Provide finished levels demonstrating that a suitable transition can be
             provided without impacting vehicle access to both sites.
     41.     Provide owner’s consent for all works in adjoining properties or
             easements.
     42.     Provide a preliminary ASS investigation and soil analysis according to the
             National Acid Sulfate Soils Guidance prepared by a suitably qualified
             person.

A detailed response to the engineering items is provided by Recor under sperate cover.

----------------------------------------------------------------------------------------------------------------------

Pursuant to the Development Assessment Rules, the applicant has given the assessment
manager the information requested. Please proceed with the processing of the application
at your earliest convenience.

If you have any further queries in relation to the above, please do not hesitate to contact
myself.

Regards,




Jack Lewis B.Sc Hons UNSW M.Plan Otago RPIA
Planner/Director
Pivotal Perspective Pty Ltd
                                                                                                      Page 12 of
                                                                                                      12

Used in these records

About this file

File size
5.9 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Response to Information Request - MCU24-0074.pdf · 5.9 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.