SUPERSEDED Minor Change Existing Approval MCU21/0117 01 & OPPW21/0199.01 · MCU21/0117.01
92. The erosion and sediment control measures must be designed, installed and maintained in
accordance with the supervising engineer instructions and the current best practice
standards * (Refer to Advisory Note).
93. The developer must ensure non-essential exposure of soil is prevented by restricting the
extent of disturbance and minimising the duration of soil exposure to adverse weather
conditions and effectively turf, cover or stabilise any disturbed area without delay and prior
to rainfall occurring.
94. The developer must ensure sediment does not leave the site or enter onto adjoining
properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or
machinery. It is essential to implement appropriate approved erosion and sediment control
measures throughout the site during all phases of construction including vehicle shakedown
pad/grid (or similar) at the access to the construction site. Where sediments or other
contaminants are deposited on a road, they must be removed so as not to enter Council’s
drainage system or waterways.
95. Prior to the completion of the development and commencement of use, all site surfaces must
be effectively stabilised using methods which have achieved effective short-term stabilisation
and which will continue to achieve effective stabilisation in the medium to long-term. For the
purpose of this condition, an effectively stabilised surface is defined as one that does not, or
is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or
lead to sedimentation, or lead to water contamination.
Damage to Services and Assets
96. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. Where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. Where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
Landscaping
97. The development site must be landscaped. The works must be undertaken in accordance
Noosa Plan PSP 2 – Landscaping and generally in accordance with the approved
Landscaping Plans and in particular:
a. A dense 2m minimum landscaped setback to the full length of the site’s frontage to
Pearl Street (excluding access, fence and bin enclosure).
b. A dense 2m minimum landscaped setback to the full length of the site’s frontage to Elm
Street.
c. A dense 1m minimum landscaped setback to all side boundaries (excluding stormwater
infrastructure).
d. Retention of all existing street trees.
98. Deleted
99. The finished level of all mulch in garden beds and landscaped medians is to be a minimum
of 50mm below the level of the adjacent top of kerb. All landscaping is to be constructed in
accordance with Council’s Planning Scheme Policy PSP2 Landscaping.
100. Suitable root barriers must be installed where proposed trees are adjacent to paths,
pavement etc in accordance with Council’s Planning Scheme Policy PSP2 Landscaping.
Page 15 of 31
Document Set ID: 23112081
Version: 5, Version Date: 17/07/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED Minor Change Existing Approval MCU21/0117 01 & OPPW21/0199.01Related documentApplication case desk ↗
About this file
- File size
- 936 KB (small file)
- File type
No other editions are linked here.