Decision Notice - Approved by Delegation of Authority MCU22 0047
Officer: Mark Lewis Direct Telephone: 07 53296290 Our Reference: MCU22/0047 & OPW22/0088 Your Reference: 04655 26 May 2022 LE McNamara & TB McNamara C/- The Jetty Specialist 18 Ron Parkinson Cres CORBOULD PARK QLD 4551 [email protected] Dear Sir/Madam Decision Notice Planning Act 2016 I refer to your application and advise that on 25 May 2022, Council decided to approve the application subject to conditions. Details of the decision are as follows: application details Application No: MCU22/0047 & OPW22/0088 Street address: 59 Saltwater Ave Noosaville Qld 4566 Real property description: Lot 517 RP 883848 Planning Scheme: Noosa Plan 2020 (25 September 2020) Decision details Council decided to issue the following type of approval: Development Permit for Material Change of Use - Landing Development Permit for Operational Works - Jetty CURRENCY PERIOD of approval The currency period for this development approval is stated in the conditions below. assessment manager conditions Approved Plans Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions. Plan No. Rev. Plan/Document Name Date TJS-04655-01 A Site Plan, layout Plan & Water Allocation prepared by Edge Consulting Engineers 22 February 2022 TJS-04655-02 A Elevation prepared by Edge Consulting Engineers 22 February 2022 JSP-SD-045 E Concrete Insitu Pile Construction 315 & 400 Diameter Reinforced prepared by Edge Consulting Engineers 9 September 2020 Currency Period The Currency Period for this development approval lapses if all conditions have not been complied with, and the plan of survey lodged with Council for endorsement by 25 May 2024, unless an application to extend the currency period is approved by Council. Performance Bond Security in the form of a cash bond or trading bank guarantee to the sum of $2000 must be submitted to Council, to secure performance of all conditions of this approval, prior to the commencement of the works. The cash bond or trading bank guarantee will be returned on performance of the conditions of this approval less any costs incurred by Council in respect of enforcing performance of this permit. Council reserves the right to call upon the bond or guaranteed sum to effect compliance with conditions. General Conditions The maximum number of vessels that may be berthed, moored, attached or stored on the structure must not exceed 2. The use of the jetty must not cause any adverse effects on the amenity of the surrounding areas including changes to light, views, air quality and noise. Vessels berthed/moored at the jetty must be located a minimum of 1.0 metres from the prolongation of the property boundaries. Vessels and boatlifting devices must be connected directly to the jetty, and not located side by side or in tandem with another vessel. All structures must be designed and constructed such that they are free standing within the waterway and are not connected to or behind the revetment wall All structures must have no detrimental effects on stormwater drains and/or easements. Jetties must have a level-walking surface of R.L 1.000 A.H.D or be level with the top of the revetment wall. A rigid handrail must be fitted on one side of the walkway. No posts or vertical supports of the proposed jetty are to extend vertically from the structure unless they provide necessary support for the handrail. No boatlifting devices are to be attached or moored at the jetty structure for the purpose of elevating a vessel above the water without Council approval. There must be no electrical reticulation system carrying electricity in excess of 24 volts beyond the revetment wall unless all switches and power outlets are positioned above the 1%AEP flood level. Lighting associated with the use must be designed, installed, operated, and maintained in accordance with Section 3 of AS4282 Control of the Obtrusive Effects of Outdoor Lighting. Rock scour protection, wrapped in geotextile, extends from 750mm up to approximately 5000mm from the face of the revetment wall in Noosa Waters. Piles are to be: Located clear of this rock protection where applicable, or alternatively Where the scour protection extends beyond 750mm: Prior to driving piles, the rocks are to be removed to expose the geotextile and the geotextile cut neatly to allow it to be turned back. During pile driving, care is to be taken to ensure the geotextile is not damaged. At the completion of pile driving, the fabric is to be turned down around the pile and the rocks replaced around the piles The jetty is to be used for private purposes only with no commercial operations to be undertaken. Boat repair activities are not permitted on site. Wastewater and sullage must only be disposed of at approved pumpout facilities. The mooring facility must not be utilised for live-aboard purposes. Any construction and post construction activity is not to impact on the condition of the waterway and is to be conducted so as not to breach the Environmental Protection Act EPA (1994) and the Environmental Protection (Water) Policy 2009. Certification by a Registered Professional Engineer of Queensland that states that the jetty is constructed in accordance with best practice methods and is structurally sound must be submitted to Council. This certification must be submitted to Council within three (3) months of the completion of the works. A final inspection and approval of the structure by Council’s Inspector is also required. Please contact Council’s Development Assessment Branch on 5329 6500 to arrange the inspection. This approval lapses where the construction of the jetty has not commenced within two (2) years of the date of issue of the approval, unless application is made and approved by Council for an extension. After completion, the proposed works must be maintained in a sound state of repair in accordance with the approved plans referral agencies Not applicable. Advisory notes The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions: General Advisory Notes Council has undertaken an audit check of the Operational Works drawings in relations to the proposed works. A detailed check of the calculations and drawings has not been undertaken, as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of the engineering design. Council reserves the right to require further amendments and/or additions at a later date should design errors become apparent. The approval or conditions do not absolve the owner of the land from complying with all the conditions of this approval and/or relevant Council By-Laws and Policies and/or relevant statues and/or statutory regulations in the execution and/or performance of said works. Council reserves the right to call up any performance bond held or levy charges against the property, should emergency works be required to be undertaken by Council to make the site safe due to inactivity on the development site for extended periods of time. Should any changes or modifications to the approved plans be required as a result of construction constraints, a “Request to change an existing approval” under the Planning Act 2016 must be made. Amended plans clearly indicating the changes must be lodged with this application along with the appropriate fees. Building and Construction Industry (Portable Long Service Leave) Levy The QLeave levy must be paid prior to the issue of a development permit where it is required. Council will not be able to issue a Decision Notice without receipt of details that the Levy has been paid. Aboriginal Cultural Heritage Act 2003 There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act). The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries out an activity must take all reasonable and practicable measures to ensure the activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions may also be issued by the Land and Resources Tribunal, and the Minister administering the ACH Act can also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value of Aboriginal cultural heritage. You should contact the Cultural Heritage Unit to discuss any obligations under the ACH Act. property notes Not applicable. VARIATION approval details Not applicable. further development permits required Not applicable. submissions Not applicable. RIGHTS OF APPEAL You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the Planning Act 2016 is attached. During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval. If Council agrees or agrees in part with the representations, a negotiated decision notice will be issued. Only one negotiated decision notice may be given. OTHER DETAILS If you wish to obtain more information about the decision, electronic copies are available online at www.noosa.qld.gov.au or at Council Offices. Yours faithfully, Mark Lewis Coordinator - Engineering Enc: Appeal Rights Approved Plans/Documents Appeal Rights PLANNING ACT 2016 & PLANNING REGULATION 2017 Chapter 6 Dispute resolution Part 1 Appeal rights 229 Appeals to tribunal or P&E Court (1) Schedule 1 of the Planning Act 2016 states – (a) Matters that may be appealed to – (i) either a tribunal or the P&E Court; or (ii) only a tribunal; or (iii) only the P&E Court; and (b) The person- (i) who may appeal a matter (the appellant); and (ii) who is a respondent in an appeal of the matter; and (iii) who is a co-respondent in an appeal of the matter; and (iv) who may elect to be a co-respondent in an appeal of the matter. (2) An appellant may start an appeal within the appeal period. (3) The appeal period is – (a) for an appeal by a building advisory agency – 10 business days after a decision notice for the decision is given to the agency; or (b) for an appeal against a deemed refusal – at any time after the deemed refusal happens; or (c) for an appeal against a decision of the Minister, under chapter 7, part 4, to register premises or to renew the registration of premises – 20 business days after a notice us published under section 269(3)(a) or (4); or (d) for an appeal against an infrastructure charges notice – 20 business days after the infrastructure charges notice is given to the person; or (e) for an appeal about a deemed approval of a development application for which a decision notice has not been given – 30 business days after the applicant gives the deemed approval notice to the assessment manager; or (f) for any other appeal – 20 business days after a notice of the decision for the matter, including an enforcement notice, is given to the person. Note – See the P&E Court Act for the court’s power to extend the appeal period. (4) Each respondent and co-respondent for an appeal may be heard in the appeal. (5) If an appeal is only about a referral agency’s response, the assessment manager may apply to the tribunal or P&E Court to withdraw from the appeal. (6) To remove any doubt. It is declared that an appeal against an infrastructure charges notice must not be about- (a) the adopted charge itself; or (b) for a decision about an offset or refund- (i) the establishment cost of trunk infrastructure identified in a LGIP; or (ii) the cost of infrastructure decided using the method included in the local government’s charges resolution. 230 Notice of appeal (1) An appellant starts an appeal by lodging, with the registrar of the tribunal or P&E Court, a notice of appeal that- (a) is in the approved form; and (b) succinctly states the grounds of the appeal. (2) The notice of appeal must be accompanied by the required fee. (3) The appellant or, for an appeal to a tribunal, the registrar must, within the service period, give a copy of the notice of appeal to – (a) the respondent for the appeal; and (b) each co-respondent for the appeal; and (c) for an appeal about a development application under schedule 1, table 1, item 1 – each principal submitter for the development application; and (d) for and appeal about a change application under schedule 1, table 1, item 2 – each principal submitter for the change application; and (e) each person who may elect to become a co-respondent for the appeal, other than an eligible submitter who is not a principal submitter in an appeal under paragraph (c) or (d); and (f) for an appeal to the P&E Court – the chief executive; and (g) for an appeal to a tribunal under another Act – any other person who the registrar considers appropriate. (4) The service period is – (a) if a submitter or advice agency started the appeal in the P&E Court – 2 business days after the appeal has started; or (b) otherwise – 10 business days after the appeal is started. (5) A notice of appeal given to a person who may elect to be a co-respondent must state the effect of subsection (6). (6) A person elects to be a co-respondent by filing a notice of election, in the approved form, within 10 business days after the notice of appeal is given to the person. 231 Other appeals (1) Subject to this chapter, schedule 1 and the P&E Court Act, unless the Supreme Court decides a decision or other matter under this Act is affected by jurisdictional error, the decision or matter is non-appealable. (2) The Judicial Review Act 1991, part 5 applies to the decision or matter to the extent it is affected by jurisdictional error. (3) A person who, but for subsection (1) could have made an application under the Judicial Review Act 1991 in relation to the decision or matter, may apply under part 4 of that Act for a statement of reasons in relation to the decision or matter. (4) In this section – decision includes- (a) conduct engaged in for the purpose of making a decision; and (b) other conduct that relates to the making of a decision; and (c) the making of a decision or failure to make a decision; and (d) a purported decision; and (e) a deemed refusal. non-appealable, for a decision or matter, means the decision or matter- (a) is final and conclusive; and (b) may not be challenged, appealed against, reviewed, quashed, set aside or called into question in any other way under the Judicial Review Act 1991 or otherwise, whether by the Supreme Court, another court, a tribunal or another entity; and (c) is not subject to any declaratory, injunctive or other order of the Supreme Court, another court, a tribunal or another entity on any ground. 232 Rules of the P&E Court (1) A person who is appealing to the P&E Court must comply with the rules of the court that apply to the appeal. (2) However, the P&E Court may hear and decide an appeal even if the person has not complied with the rules of the P&E Court [word/footer1.xml] Page 4 of 4 [word/footer2.xml] PO Box 141 P. (07) 5329 6500 [email protected] TEWANTIN QLD 4565 F. (07) 5329 6501 www.noosa.qld.gov.au Page 1 of 4 [Attachment: image3.png (image text)] ee) NOOSA COUNCIL
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.