i. dimensions, grades, crossfalls, swale drains, etc; and
b. the extent of earthworks required to carry out the proposed works.
Items for Clarity/Confirmation
Following onsite inspection, there were discussions in relation to:
• Providing a pedestrian bridge over the creek. This is necessary to be included in the
application as it would intersect a watercourse and likely require clearing.
• Should the development be desired to be staged, there is the ability to do so however
this is to be detailed in a part of the application and will be conditioned appropratiely.
• Reducing the length of the internal track to avoid the extent of track to be upgraded
due to the slope of the track?
3. DUE DATE FOR RESPONSE TO FURTHER ADVICE
Council requests your agreement to further extend the decision-making period to allow for
ample time to respond to the Further Advice and for assessment of the application.
Email your response to [email protected] and cc in the relevant Development Planner.
4. OTHER DETAILS
Should you have any further queries in relation to the above, please do not hesitate to contact
me on the number above.
Yours faithfully,
Georgina Schramm
Development Planner
Page 3 of 3
Document Set ID: 22435177
Version: 2, Version Date: 26/06/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
ECM_22435177_v2_Further Advice Assessment Manager MCU22 0052.pdfRelated documentApplication case desk ↗
About this file
- File size
- 103 KB (small file)
- File type
No other editions are linked here.