Appendix E - Code Assessment
(c) the total width of the garage does not exceed
60% of the width of the lot.
AO13.4
On lots with a width of at least 12.5 metres but not
exceeding 14 metres the total width of the garage does
not exceed 50% of the width of the lot and garage
doors do not exceed a total width of 6 metres.
AO13.5
On lots with a width of more than 14.0 metres, garage
doors within 10 metres of the front boundary do not
present a combined width of more than 6.7 metres or
40% of the lot width whichever is the lesser.
Editor’s Note— The lot width would be measured at
the frontage unless the lot was irregular in shape being
for example on a bend or at the head of a cul-de-sac,
in which case it would be the width of the lot in line with
the front of the garage.
PO14 AO14 Not applicable.
Basements (including the entry points to them): Basements:
(a) do not dominate the street or building design; (a) are limited to one access a maximum of 6
(b) visually integrates with the residential metres wide; and
building; and (b) do not encroach into boundary setback
(c) do not present as a storey to the street. areas.
Editor's note—refer to figure 6.9.2
PO15 AO15 Complies.
Hard standing driveways and manoeuvring areas are Driveways have a maximum width of 6 metres within
designed so as not to dominate the streetscape nor the property and only one footpath crossing is provided The proposed access handle does not dominate the site’s Butler
adversely impact on the low density residential per property as part of the driveway. Street frontage nor does the driveway adversely impact the
amenity. amenity of the local area.
Roof Design AO16.1 Complies.
With the exception of the reuse or renovation of an
PO16 existing building which does not comply, in areas other The future Dwelling House to be established at proposed Lot 2 will
Roof designs: than the Coastal Communities and Noosa Heads local ensure compliance with the Acceptable Outcomes of this element
(a) contribute positively to the character of the plan areas: at the subsequent Building Approvals stage.
streetscape;
(b) incorporate eaves and roof overhangs; (a) the main roof of buildings has a pitch no less
(c) avoid boxy elevations on the front facade of than 5 degrees; and
the building;
See the original