98.      The development site must be provided with an Emergency Bushfire
         Evacuation Route connecting to Council’s “Road 176”. The emergency route
         is to be used for emergencies only and is not to be used for deliveries or
         general access. The works must be undertaken in accordance with an
         Operational Works approval and Section 5.5 of North Coast Environmental
         Services’ Bushfire Hazard Assessment and Management Plan (J001061, v.4)
         dated 11 September 2024, and include, but not be limited to:
                a.    a design prepared by a suitably qualified person (RPEQ) that is
                      to an acceptable standard for infrequent use to cater for a HRV,
                      14.5m rigid vehicle (i.e., bus) and appropriate firefighting
                      appliances in the event of a fire emergency only;
                b.    a design that allows for unbroken access for a HRV, 14.5m rigid
                      vehicle (i.e., bus) and appropriate fire-fighting appliances
                      through the site (i.e., from “Road 176” to all parking and
                      manoeuvring areas and through to Kabi Road);
                c.    a design that includes passing bays and turning areas;
                d.    the emergency route, all internal roads and associated
                      manoeuvring areas must not exceed a gradient of 12.5%;
                e.    the emergency route must have a maximum cleared width of
                      10.0 metres and a minimum cleared width of 6.0 metres; and
                f.    the necessary upgrades to “Road 176” and associated
                      drainage infrastructure, which must be maintained by the
                      applicant during the life of the development.
                g.    Consultation must occur with the existing resident(s) that
                      access “Road 176” in relation to the proposed works.

--------------------------------------------------------------------------------------------------------------------

If you have any further queries in relation to the above, please do not hesitate to contact
myself.


Regards,




Jack Lewis B.Sc Hons UNSW M.Plan Otago RPIA
Planner/Director
Pivotal Perspective Pty Ltd
0406 334 227
Log in to download the original file

Change Representations - CYC 2025 (version 2 19.01.25).pdf · 801 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.