4.14 Is the work for gravity diversion from a watercourse?
D No . Continue to question 4.15
D Yes . A development permit is required and this application will be assessed by OSOIP’s SARA as
assessment manager or concurrence agency against the Sustainable management of water
resources state code in the SOAP.
. You must complete IDAS form 15-Gravity diversion from a watercourse
. If this is the only aspect of taking or interfering with water proposed, then that is the end of part 4 of
this checklist
. If there are other aspects of taking or interfering with water proposed, then continue to question 4.15
4.15 Is the work for a watercourse diversion?
D No . Continue to question 4.16
D Yes . A development permit is required and this application will be assessed by OSOIP’s SARA as
assessment manager or concurrence agency against the Sustainable management of water
resources state code in the SOAP.
. You must complete IDAS form 17-Watercourse diversion
. If this is the only aspect of taking or interfering with water proposed, then that is the end of part 4 of
this checklist
. If there are other aspects of taking or interfering with water proposed, then continue to question 4.16
4.16 Is the work for other work for taking or inte erlng with water?
D No . Continue to question 4.17
D Yes . A development permit is required and this application will be assessed by OSOIP’s SARA as
assessment manager or concurrence against the Sustainable management of water resources state
code in the SOAP.
. You must complete IDAS form 21-0ther work in a watercourse
. If this is the only aspect of taking or interfering with water proposed, then that is the end of part 4 of
this checklist
. If there are other aspects of taking or interfering with water proposed, then continue to question 4.17
4.17 Does any of the proposed operational work Involve taking or inte ering with artesian water as defined
under the Water Act200O, schedule 4 (otherthan using a water truck to pump water)?
D No . Go to question 4.20
D Yes . Continue to question 4.18
4.18 Is any part of the proposed works on land to which a property development plan under the WIld Rivers
Act20fJSappIies?
D No . A development permit is required and this application will be assessed by OSOIP’s SARA as
assessment manager or concurrence agency against the Sustainable management of water
resources state code in the SOAP.
. You must complete IDAS form 12-Taking or interfering with artesian or sub-artesian water
. If this is the only aspect of taking or interfering with water proposed, then that is the end of part 4 of
this checklist
. If there are other aspects of taking or interfering with water proposed, then continue to question 4.20
D Yes . Continue to question 4.19
Checklist 4-Operational work
Version 3.0-1 July 2013
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Development Application part 1Related documentApplication case desk ↗
About this file
- File size
- 28.6 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.