2020-01-13 General Committee Meeting Notes
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
RECOMMENDATIONS ONLY – NOT THE FINAL DECISION OF COUNCIL
GENERAL COMMITTEE MEETING 13 JANUARY 2020
Approved Plans
2. Development undertaken in accordance with this approval must generally comply
with the approved plans of development. The approved plans are listed in the
following table unless otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
DA01 18E Site Calculations & Staging Plan, prepared by All 06.11.2019
Design and Drafting (as annotated by Council)
DA02 18E Site Plan, prepared by All Design and Drafting (as 06.11.2019
annotated by Council)
DA03 18E Site Plan – Landscaping and Fencing, prepared by All 06.11.2019
Design and Drafting (as annotated by Council)
DA04 18E Site Elevations, prepared by All Design and Drafting 06.11.2019
DA05 18E Site Elevations, prepared by All Design and Drafting 06.11.2019
DA06 18E Unit Type T1A, prepared by All Design and Drafting 06.11.2019
DA08 18E Unit Type T1B, prepared by All Design and Drafting 06.11.2019
DA09 18E Unit Type T2, prepared by All Design and Drafting 06.11.2019
DA10 18E Unit Type T3, prepared by All Design and Drafting 06.11.2019
DA11 18E Exterior Materials and Colours, prepared by All Design 06.11.2019
and Drafting
ENGINEERING
Site Access and Driveway
14. Vehicular access driveways to serve the development shall be constructed from
the Olivine Street frontages of the site generally in accordance with the final
approved layout plans and as annotated by Council and amended by the
conditions of this permit and in compliance with the applicable engineering
standards and drawings.
15. Two sealed access driveways must be provided from Olivine Street frontages of
the site to all parking and manoeuvring areas of the development generally in
accordance with the final approved layout plans as annotated by Council and
amended by the conditions of this permit. The works must be undertaken in
accordance with an Operational Works approval and must include in particular:
15.1. Driveway crossovers generally in accordance with IPWEAQ standard
drawings R-049 and R-050, and to grades that prevent vehicles from
scraping and/or bottoming whilst also allowing for compliant grades and
levels that match any existing or proposed pathway and grassed verge
without posing trip or safety hazards to the public.
15.2. For pedestrian safety on the footpath and vehicles exiting the site, the
driveway and any associated fencing or vegetation near the driveway must
comply with the minimum sight line requirements as defined in AS/NZ
2890.1, section 3.2.4.
15.3. The proposed driveway must have a maximum width of 6m at kerb line.
15.4. Driveway must have clearance of 1.0m from a power pole and 0.5m from
and any service pit or manhole (e.g. telecommunication pit, water meter)
unless a written approval obtained from the relevant provider.
Page 8 of 12
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.