Council archive · source document
OPW16/0094 Conditions
1. APPLICATION DETAILS Application No: OPW16/0094 Street Address: 9 Duke St SUNSHINE BEACH QLD 4567 Real Property Description: Lot 204 RP 48113 Planning Scheme: The Noosa Plan (16 September 2013) 2. DECISION DETAILS The following type of approval has been issued: Development Permit for Operational Work - Stormwater, Earthworks, Roadworks & Landscaping 3. RELEVANT PERIOD OF APPROVAL The relevant period for this development approval is 2 years starting the day that this development approval takes effect. 4. ASSESSMENT MANAGER CONDITIONS APPROVED PLANS Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions. Plan No. Rev. Plan/Document Name Date 25464-OW3 - Driveway and Access, prepared by SCG Consulting Engineers March 2016 25464-OW5 - Site Benching & Retaining Walls, prepared by SCG Consulting Engineers March 2016 25464-SW1 Stormwater Management, prepared by SCG Consulting Engineers March 2016 1511 Land_01 n/a Landscape and Site Plan prepared by Yardart Undated 1511 Land_02 n/a Landscape and Site Plan prepared by Yardart Undated PRIOR TO COMMENCEMENT OF WORKS Engineering Council must be contacted at least 5 working days prior to any works commencing to organise a prestart. The contact number to arrange a pre-start meeting is 5329 6244. The pre-start meeting must include the relevant parties for the following aspects of the works: Civil engineering works; Landscape works; Erosion and sediment control works; Copies of the approved plans, duly signed by the consultant Registered Professional Engineer of Queensland (RPEQ) must be provided to Council’s Engineering Officer Construction at the “prestart” meeting. A condition report including photographs of the frontage of the site must be completed and submitted to Council at the prestart meeting. A condition report including photographs of all fences bordering the site and any buildings, structures, pathways, landscaping features etc on adjoining properties that could potentially be impacted on by the proposed earthworks and construction works (including piling works) must be completed and submitted to Council at the prestart meeting. The principal contractor must have all the appropriate insurance and public liability documentation to carry out the works. The principal contractor is also responsible to ensure that any subcontractors also have the appropriate insurance and public liability documentation. Certificates demonstrating currency of public liability insurance and works insurance covering the works must be submitted to Council prior to the prestart meeting. A Construction Management Plan must be submitted to Council for approval prior to the prestart meeting and must specifically address the following: Traffic Management during all aspects of the construct phase including: A Traffic Management Control Plan in accordance with Manual of Uniform Traffic Control Devices (MUTCD) detailing all temporary signage and traffic control measures prior to construction. Maintenance of safe pedestrian access across the frontage of the site both during daily construction and after daily construction has ceased. Closure of road verge during the construction of the new concrete pathway. Proposed fencing to the site during the construction phase of the development. Adequate parking arrangements for trucks, machineries and construction workers. No queuing of trucks is permitted on residential streets, especially prior to 7.00am. Further parked trucks must have engines turned off Maintenance and protection of water quality and existing drainage lines through the construction site through the implementation of appropriate erosion and sediment control measures. Works programme identifying key components of the works and their respective durations. Identification of complaint management procedures including: Contact details for the on-site manager. Dispute resolution procedures. Any changes to the details associated with the supervising RPEQ or Principal Contractor during construction, must be notified to council in writing within five business days of the change occurring. Any conflict between the development and an existing or proposed service must be referred to the relevant service authority for determination prior to commencement of works. DURING CONSTRUCTION General The developer must meet any costs to repair damage to any Council asset during construction, where damage is a result of the development works. Damage to assets must be repaired immediately where it creates a hazard to the community. In circumstances where the damage does not create a hazard to the community, it must be repaired immediately on completion of the works associated with the development. All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ) who is independent of the Developer and Principal Contractor, and they must certify that all works conform to the Operational Works permit. Where municipal works are involved, such confirmation must be submitted for the respective hold points prior to any site inspection by Council Officers. All works must be constructed and work procedure undertaken in accordance with: The approved plans and conditions detailed in this Decision Notice. The relevant conditions of the higher order Material Change of Use approval File MCU16/0018 to which this approval relates. All relevant Noosa Council Planning Scheme Policies, standard drawings, standard specifications and guidelines. The latest version of the Healthy Waterways document “Water Sensitive Urban Design Technical Design Guidelines for South East Queensland” for all water quality devices to be constructed on site. New Kerb and Road Pavement Resurfacing Any new kerb and channel must be provided generally in accordance with the approved plans, standard drawing SEQ R-080 and consistent with the adjoining kerb sections. Any required reinstatement to the road pavement must be in accordance with standard drawing SEQ R-170. Any new subsoil drains must be provided in accordance with standard drawing SEQ R-140. Where required any road pavement resurfacing must consist of a minimum depth of 50mm of an approved hot mixed asphaltic concrete. Driveway Driveway crossovers must be constructed in accordance with the approved plans and be generally in compliance with IPWEA Standard Drawings RS-049 and RS-050. Where there is adjoining a pedestrian path (existing or proposed), a matching crossfall must be provided for the driveway on the alignment of the path, for the full width of the path. Any existing unnecessary or redundant property accesses must be removed, and the kerb, footpath and verge area reinstated to match the existing footpath and/or verge treatments. Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed or turf, and must be maintained by the developer until established. The following must be complied with during the construction of the required crossover/driveway: The driveway surfacing must consist of either an approved hot mixed asphaltic concrete or patterned/plain concrete and must have a slip resistant surface The driveway must be constructed so as not to concentrate stormwater runoff or ponding onto other properties. Where applicable, underground service conduits for water supply, electricity and any other services must be provided as part of the access driveway works. Any stormwater kerb outlet in close proximity to the edge of the new driveways must be provided with an approved kerb adaptor. Have a minimum clearance of 500mm from any Unitywater/Telstra asset, unless a written approval is obtained from Unitywater/Telstra and submitted to Council. Have a minimum clearance of 1m from any power pole, unless a written approval is obtained from Energex and submitted to Council. Pavement Design and Construction Pavement design for privately owned works must be undertaken in accordance with the relevant standards. Structural integrity of the driveway and car park areas will remain the responsibility of the property owner/developer and must be certified by an RPEQ. Works within Road Reserve and Reinstatement Works Safe pedestrian access on all streets in the vicinity of the development must be maintained at all times. Should footpath/road closures be necessary to carry out construction works, Council’s Engineering Officer must be notified prior to the proposed closure and all requirements complied with. Any existing damaged kerb and/or channel along the frontage of the site must be replaced by the developer to the reasonable satisfaction of Council. All frontage works (eg kerb & channel, new concrete footpath) must match neatly with existing road and verge/footpath features. Additional works beyond the frontage of the site may be required to provide an acceptable transition to existing road, kerb & channel and verge/footpath profiles. Any existing kerb & channel and concrete footpath sections requiring removal due to the new works must be saw-cut and removed to allow for a smooth and neat finish with the new works. Any new kerb and/or channel must be provided generally in accordance with the approved standard drawing SEQ R-080 and consistent with the adjoining kerb sections. Any reinstated road pavement must be in accordance with IPWEA standard drawing RS- 170 with road pavement resurfacing to consist of a minimum depth of 50mm of an approved hot mixed asphaltic concrete. Pathways All pathways must be constructed in accordance with the following requirements: Be generally in accordance with the approved plans and in compliance with the higher order approval conditions and IPWEA standard drawing RS-065. Footpath alignment shall be amened where necessary to avoid conflict with any existing obstructions (eg electricity power pole, mature trees to be preserved). All paths must have a slip resistant surface. Expansion and contraction joints must provide a flush finish. Installation of joints by saw cutting is preferred to ensure a smooth ride for cyclists. The works include any modifications to existing service covers to ensure the footpath finishes flush with all services and the like, so as not to create a pedestrian safety hazard. For public safety, new pathway must terminate in a manner that ensures smooth transition to existing surfaces (eg grassed verge). Be designed and constructed to comply with the Disability Discrimination Act (DDA), Access to Premises Standard, Austroads and relevant sections of AS1428 Design for access and mobility. Construction hold point(s) with Council’s delegate must be established once the pathway is ready for concreting and/or as may be agreed to at the prestart meeting. Earthworks All earthworks must be undertaken in accordance with the provisions of AS 3798 Guidelines on Earthworks for Commercial and Residential Development, with geotechnical supervision and testing undertaken in accordance with Section 8 of the Standard, and to a minimum of ‘Level 2’ as defined in Appendix B. All Earthworks and construction works must be carried out taking into consideration the protection of any existing above and below surface services, and the stability and protection of any structures on the adjoining properties. Stormwater Drainage Appropriate scour protection must be provided at the outlet of all stormwater pipes including temporary outlets. Works associated with this permit must not adversely impact on the existing drainage conditions on other properties (eg by blocking or interfering with natural overland flows). Construction of all internal stormwater drainage works must comply with the relevant section/s of Australian Standard AS/NZS 3500.3. Environment – Erosion & Sediment Control Prescribed Water Contaminants (as defined in the Environmental Protection Act 1994) must not be released from the site or to waters within the site, or be likely to be released should rainfall occur, unless all reasonable and practicable measures are taken to prevent or minimise the release and concentration of contamination. Erosion and sediment control measures must be installed and maintained to minimise erosion on the site and to minimise the export of sediment and associated pollutants from the site. The erosion and sediment control measures must be designed, installed and maintained in accordance with the supervising engineer instructions and the current best practice standards (refer to advisory notes). Prior to the commencement of the use all site surfaces must be effectively stabilised using methods which have achieved effective short-term stabilisation and which will continue to achieve effective stabilisation in the medium to long-term (refer to advisory notes). For the purpose of this condition, an effectively stabilised surface is defined as one that does not, or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or lead to sedimentation, or lead to water contamination. LANDSCAPING Clearing Vegetation Prior to approved vegetation clearing, all trees are to be checked for wildlife (i.e. koalas, possums, birds etc.). If wildlife is present, the tree must not be felled or pruned until the wildlife has left the tree. Vegetation clearing must: Conclude with the area being stabilised against erosion and landscaped. Rectification to the finished surface levels and materials. No damage to other vegetation for retention. Legal disposal of all removed vegetation and debris. Protected Vegetation All trees and vegetation identified for retention must be protected in accordance with AS 4970, Protection of trees on development sites. A “no clearing zone” must be established and maintained over the critical root zones of the Bloodwoods in the rear of the site on the Approved Plans and included adequate temporary fencing. The following activities must not be carried out within the no clearing zone: clearing, cutting down, poisoning, lopping or pruning of native vegetation which is indigenous to, or planted within, the zone soil/spoil dumping and/or compacting soil excavation, other than for planting indigenous native plants. The following exceptions apply: declared plants under the Land Protection (Pest and Stock Route Management) Act 2002 and sub-ordinate Regulation 2003, and any Council Listed Environmental Weeds, Exotic Grasses and other plants identified in writing by Council Trees which pose a well-founded threat to persons or property as approved in writing by Council. Where trees have to be removed as a result of construction damage a minimum 100 L replacement trees of a local native species must be provided. Landscaping Works The development site must be landscaped in generally accordance with the works shown on the approved Landscape plan. Declared plants under the Land Protection (Pest and Stock Route Management) Act 2002 and sub-ordinate Regulation 2003, and any Council Listed Environmental Weeds, Exotic Grasses and other plants identified in writing by Council in the rear of the site must be controlled in a manner that does not cause instability of the slope and existing local native vegetation and prevents further spread of declared and environmental weeds. All landscape works must be established and maintained in accordance with the approved design for the life of the development, and in a manner that ensures healthy, sustained and vigorous plant growth. All plant material must be allowed to grow to full form and be refurbished when its life expectancy is reached. All landscape works must be maintained generally in accordance with the approved Landscape plan for the life of the development. Landscaping must be located in a position that will not adversely affect Council infrastructure or access to municipal infrastructure. Landscape works must not interfere with vehicle and pedestrian sight distances. Landscaping must be in accordance with the approved landscaping plans and planted and maintained in accordance with Planning Scheme Policy 3 – Landscaping Plants and Guidelines. Grassed areas must be: Rolled, top dressed and joined smoothly with adjoining surfaces. Of species sustainable for local and design conditions and do not require irrigation. Free of disease, pest, weeds, rock and debris. New street tree plantings must: Meet NATSPEC Guidelines: Specifying Trees requirements for quality. Be pruned in accordance with AS 4373, Pruning of Amenity Trees. Be of the approved plan species. Be pest and disease free. Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions. Damage to Services and Assets Any damage caused to existing services, streetscape and assets as a result of the development works must be repaired at no cost to the asset owner at the following times: Where the damage would cause a hazard to pedestrian or vehicle safety, immediately; or Where otherwise, upon completion of the works associated with the development. Any repair work which proposes to alter the alignment or level of existing services and assets must first be referred to the relevant service authority for approval. FOLLOWING CONSTRUCTION Certification Upon completion of the work a certificate must be issued by an RPEQ certifying that the works have been constructed in accordance with the Operational Works permit. As Constructed Plans Prior to acceptance of civil works to become Council assets “On Maintenance”, the lodgement of satisfactory “As Constructed” records must be submitted to Council. The “As Constructed” information must include: Drawings and data certified by a qualified experienced Civil Engineer (RPEQ) for design intent, and certified by a Licensed Surveyor in regard to the cadastre and the location, level and type of all services and structures. The data must be in accordance with Council’s – Planning Scheme Policy 5 – Engineering Design Standards – Roads, Drainage and Earthworks, and fully detail levels for all engineering works including but not limited to drainage structures, finished ground levels and pavement surface levels. The data must be submitted in hardcopy form or in digital format (Asset Design and As Constructed (ADAC)) in GDA94 Zone 56 coordinate values. Guidelines on the use of ADAC are available at www.adac.com.au. On Maintenance All municipal works must be accepted ‘On Maintenance’ by Council in accordance with Council’s relevant Planning Scheme Policy prior to the commencement of the use. To achieve ‘On Maintenance’, the supervising RPEQ must submit to council: Certification that all works have been undertaken and completed in accordance with the requirements of this Permit As Constructed details in accordance with Council’s Planning Scheme Policy Off Maintenance Prior to requesting an Off Maintenance inspection the developer must provide a written request for the Off Maintenance inspection. A re-inspection fee in accordance with Council’s Fees and Charge Register will be charged where: A Council inspection reveals works do not comply with approval requirements. Submitted certification falsely states works comply with approval requirements. 5. REFERRAL AGENCIES Not Applicable. 6. REFERENCED DOCUMENTS Not Applicable. 7. ADVISORY NOTES The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions: General Advisory Notes Council has undertaken an audit check of the Operational Works drawings in relations to the proposed works. A detailed check of the calculations and drawings has not been undertaken, as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of the engineering design. Council reserves the right to require further amendments and/or additions at a later date should design errors become apparent. Council reserves the right to call up any performance bond held or levy charges against the property, should emergency works be required to be undertaken by Council to make the site safe due to inactivity on the development site for extended periods of time. Amendments to plans, in accordance to the relevant conditions, and/or any requested changes to the conditions of this decision notice must be made within the appeal period or the suspended/extended appeal period. Alternatively, an application for “Request to change an existing approval” under the Sustainable Planning Act 2009 must be made along with Council’s applicable fees. In order to mitigate the potential of public liabilities due to trip and similar hazards, Council does not permit any unauthorized works within the road reserve such as steps, sleeper steppers, hazardous landscaping and the like. Prestart, On and Off Maintenance Inspections Request Contact Council on 5329 6244 to arrange a prestart or an inspection giving a minimum of 5 business days notice of preferred inspection time. It should be noted prior to arranging a pre-start meeting the Right of Appeal Period of 20 business days should have been passed or the applicant has have confirmed by a letter or an email that he/she has accepted the conditions of Decision Notice and waived his/her appeal right. If Council officers are required to undertake additional inspections of the same works, a re-inspection fee will be applicable in accordance with Council’s Fees and Charges register applicable at the time. A minimum maintenance period of 12 months will apply to all municipal works and thereafter until such time as the works are performing in accordance with the approved design unless noted otherwise. Environmental Advisory notes The Environmental Protection Act 1994 states that a person must not carry out any activity that causes, or is likely to cause, environmental harm unless the person takes all reasonable and practicable measures to prevent or minimise the harm. Environmental harm includes environmental nuisance. In this regard persons and entities, involved in the civil, earthworks, construction and landscaping phases of this development are to adhere to their ‘general environmental duty’ to minimise the risk of causing environmental harm. Erosion and Sediment Control Accepted best practice standards include: the Sunshine Coast Regional Council Manual for Erosion and Sediment Control V1.2 or other superseding document subsequently adopted by Council; Best Practice Erosion and Sediment Control, International Erosion Control Association (2008) As a general rule, a site is determined to have achieved effective short-term stabilisation if at the completion of the works: Methods of stabilisation are: appropriate for slopes and slope lengths; and are consistent with best practice environmental management practices such as in the Manual for Erosion and Sediment Control or the IECA Manual; and Stormwater runoff from the site is not currently, and is not likely to result in visible evidence of sedimentation or erosion, or lead to water contamination. If at the time of the completion of the works, the method of short-term stabilisation has not achieved a level of stability that Council's Officers believe will have a high probability of achieving long term stability (i.e. until house construction has occurred on all lots), Council Officers may take the following matters into consideration in determining whether the site is capable of achieving medium to long-term stability: Evidence that the site has been effectively stabilised in the short term; Evidence that soil has been adequately ameliorated; Evidence that seed of annual and perennial grass species has been applied at an adequate rate; and That grass seed has germinated at a density that is likely to achieve an effective grass cover. Aboriginal Cultural Heritage Act 2003 There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain approvals pursuant to the Aboriginal Cultural Heritage Act 2003. The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries out an activity must take all reasonable and practicable measures to ensure the activity does not harm Aboriginal cultural heritage.” It is an offence to fail to comply with the duty of care. Substantial monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions may also be issued by the Land and Resources Tribunal, and the Minister administering the Act can also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value of Aboriginal cultural heritage. You should contact the Cultural Heritage Co-ordination Unit on 07 3239 3647 to discuss any obligations under the ACH Act. 8. PROPERTY NOTES Not Applicable. 9. PRELIMINARY APPROVAL OVERRIDING PLANNING SCHEME Not Applicable. 10. FURTHER DEVELOPMENT PERMITS REQUIRED Not Applicable 11. SELF ASSESSABLE CODES Not Applicable. 12. SUBMISSIONS Not Applicable. 13. REASONS / GROUNDS FOR APPROVAL DESPITE CONFLICT WITH SCHEME Not Applicable. 14. RIGHTS OF APPEAL You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the Sustainable Planning Act 2009 is attached. During the appeal period (normally 20 business day), you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval. If Council agrees or agrees in part with the representations, a “negotiated decision notice” will be issued. Only one “negotiated decision notice” may be given. Taking this step will defer your appeal period, which will commence again from the start the day after you receive a “negotiated decision notice”. 15. OTHER DETAILS If you wish to obtain more information about Council’s decision, electronic copies are available on line at www.noosa.qld.gov.au, or at Council Offices. Yours faithfully Monkeith Kadhum Development Engineer Enc: Approved Plans Appeal Rights cc Unitywater
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
OPW16/0094 ConditionsRelated documentApplication case desk ↗
About this file
- File size
- 54 KB (small file)
- File type
- DOCX
No other editions are linked here.