                                                                                      2009/1490



7.    A verification survey of the building is to be carried out by a Licensed Surveyor and a
      certificate lodged with Council at completion of the work confirming compliance with the
      maximum allowable building height as required by either the conditions of approval or the
      Planning Scheme.
Security Bond and Contributions
8.    Monetary contributions shall be paid to Council towards the cost of providing and/or upgrading
      various infrastructure at the rates applicable at the time of payment. An estimate only of the
      contribution amounts under the current Council policies and requirements is outlined in the
      table below:

          Contribution Required For:                                                 Amount:
          PSP20 – Pathway Trunk Network Contributions                                $727
          TOTAL Contribution Amount =                                                $727
          Please note that these amounts are all subject to variations in the Consumer Price Index,
          All Groups Brisbane from September 2009 until the date of payment.

      All contributions must be paid prior to commencement of the use.
9.    Security in the form of a cash bond or trading bank guarantee to the sum of $1,500 must be
      submitted, to secure performance of all conditions of this approval, prior to the issue of a
      Development Permit for building works. The cash bond or trading bank guarantee will be
      returned on performance of the conditions of approval less any costs incurred by Council in
      respect of enforcing performance of this permit.
General
10.   Deleted.
11.   The development must be undertaken and operated in a manner that causes no detrimental
      effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
      lighting nuisance or other emissions.
Earthworks and Sediment Control
12.   Earthworks required on site shall be carried out in accordance with Council’s Planning
      Scheme Policy PSP5 Engineering Design Standards, so as not to cause the additional
      ponding of water on any adjoining lands or concentrate or direct overland flow on to an
      adjoining property.
13.   Sediment and erosion control measures must be in place prior to building works. If such
      measures are not in place or are not satisfactory, ‘on the spot’ fines may be issued. Such fines
      can be issued if sediments from the site are found to enter or have the potential to enter
      Council’s stormwater system or natural waterways.

5     REFERRAL AGENCY CONDITIONS
Not applicable.

6     APPROVED PLANS/DOCUMENTS

The approved plans and / or documents for this development approval are listed in the following
tables:




                                                                                     Page 3 of 7

Used in these records

About this file

File size
52 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Permissible Change Decision Notice Approval or App in Part - 010.2009.00001490.002 [As Published].pdf · 52 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.