8. APP G. Engineering RFI Response
Attached to the e-mail MCU14/0102 - Response to Information Request - Email 2 of 2..
Original PDF page 63, section 1. The text section number identifies this passage in the reader.
SPECIFIC OUTCOMES, ACCEPTABLE SOLUTIONS AND PROBABLE SOLUTIONS
FOR THE WATER SENSITIVE DESIGN CODE
SPECIFIC OUTCOMES PROBABLE SOLUTIONS SITE COMPLIANCE
Water reuse S1.1 Complies:
O1 Development complies with - The development
Development uses a the water quality standards includes three
combination of detention in Table 2 of the SEQ bioretention systems
and retention systems to Regional Plan and a detention
capture run-off from areas Implementation Guideline basin to ensure that
on the site No.7 for Water Sensitive peak flow
AND Urban Design; discharges are
mitigated and water
O2 quality is maintained
Water storage devices S2.1
No solution provided - Water detained on
must have sufficient site will not be for
capacity having regard to potable use
local rainfall pattern and S3.1
the catchment area of roof - Site is not within the
Captured water is plumbed Shire Business
or other hard standing to be available for all
surface Centre
external uses including
AND gardening, irrigation,
O3 ponds, filling swimming
Captured water is utilised pools and outdoor
for all non-potable uses on cleaning, as well as all
site; ground floor toilet cisterns
AND and washing machine cold
taps;
O4
On-site detention does not
adversely impact on water AND
requirements downstream S3.2
of the site where the water Where the captured water
is required to sustain the is used for toilet flushing
ecology and hydrology of and/or laundry use, an
downstream systems automatic or manual
(environmental flows); interchange device that
AND allows alternate use of
O5 captured water or the
reticulated water supply is
Within the Shire Business installed to ensure that
Centre site, as shown on there is a continual supply
Map SBC, on-site of water for sanitary
detention measures are flushing and laundry use.
contained within the
developed areas of the S4.1
site, clear of drainage lines No solution provided
and Open Space Precincts. S5.1
No solution provide
Eumundi Stormwaster Code Compliance Page 1
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.