RFI - 20220156 Kauri St SWMP Rev B

of 70

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

 RESIDENTIAL TOWNHOUSE DEVELOPMENT
 9 KAURI STREET, COOROY, QLD 4563
 Lot 2 on RP840262
 CIVIL WORKS

NOTE:                                                                                                         VIBRATION EQUIPMENT, TRENCH SHORING ETC AS REQUIRED.
THE FOLLOWING INSPECTIONS MUST BE COMPLETED BY RECOR ENGINEERS BEFORE                                   11. PRIOR TO THE CONTRACTOR COMMENCING ANY WORKS DETAILED ON THESE DRAWINGS,
ENGINEERING CERTIFICATION WILL BE ISSUED. THE CONTRACTOR IS TO PROVIDE A                                    THE CONTRACTOR IS TO NOTIFY RECOR AND RECEIVE WRITTEN CONFIRMATION THAT
                                                                                                            WORKS CAN COMMENCE.
MINIMUM OF 72 HOURS NOTICE TO RECOR FOR REQUIRED INSPECTIONS. SHOULD THE
CONTRACTOR FAIL TO REQUEST AN INSPECTION, THE CONTRACTOR WILL BE                                        12.   CONTRACTOR TO PROVIDE AS CONSTRUCTED DRAWINGS FOR ALL CONSTRUCTED WORKS
RESPONSIBLE FOR ALL COSTS TO ALLOW FOR THE WORKS TO BE INSPECTED TO THE                                       IN ACCORDANCE WITH LOCAL GOVERNMENT REQUIREMENTS. UNLESS OTHERWISE
SATISFACTION OF RECOR. ANY INSPECTIONS THAT FAIL ARE TO BE RE-INSPECTED WITH                                  ADVISED BY RECOR CONTRACTOR TO NOTE COUNCILS ADAC REQUIREMENTS.
ALL REINSPECTION COSTS TO BE PAID BY THE CONTRACTOR.                                                    13.   CONTRACTOR TO UNDERTAKE ALL WORKS IN ACCORDANCE WITH RELEVANT APPROVALS.
                                                                                                        14.   CONTRACTOR TO ALLOW TO LIASE/CO-ORDINATE WITH ELECTRICAL, LANDSCAPE AND
      a.     PRESTART                                                                                         OTHER SERVICE CONTRACTORS THROUGHOUT CIVIL CONSTRUCTION.
      b.     EARTHWORKS - FINAL STRIPPING OF TOPSOIL, INSTALLATION OF SEDIMENT AND                      15.   CONTRACTOR TO ORGANISE ALL DEMOLITION PERMITS PRIOR DEMOLITION WORKS
             EROSION CONTROL MEASURES UNSUITABLE GROUND                                                       COMMENCING ON SITE.
      c.     SIDE AND CUT OFF DRAINS                                                                    16.   CONTRACTOR TO ALLOW TO DEMOLISH ALL EXISTING STRUCTURES, ROADS AND
      d.     STORMWATER PIPE LAID ON BEDDING PRIOR TO BACKFILL                                                SERVICES WITHIN LIMIT OF WORKS AND REMOVE FROM SITE U.N.O.

      e.     STORMWATER TRENCH BACKFILLED PRIOR TO PAVEMENT PLACEMENT                                   17.   CONTRACTOR TO UNDERTAKE DILAPIDATION REPORT FOR ADJOINING PROPERTIES AND
                                                                                                              COUNCIL ROADS AND VERGES PRIOR TO COMMENCEMENT OF ANY WORKS ON SITE.
      f.     STORMWATER STRUCTURE BASE SLABS
                                                                                                        18.   CONTRACTOR TO CLEAR AND GRUB ALL VEGETATION ON SITE AS IDENTIFIED IN THE
      g.     SEWER RETICULATION                                                                               APPROVED VEGETATION MANAGEMENT PLAN. CONTRACTOR TO ENSURE ALL TREE ROOTS
      h.     WATER RETICULATION                                                                               AND STUMPS ARE COMPLETELY REMOVED AND BACKFILLED TO LEVEL 1 SUPERVISION.
                                                                                                              CONTRACTOR TO ALLOW TO MULCH ALL CLEARED VEGETATION AND STOCKPILE ON SITE
      i.     PAVEMENT SUBGRADE                                                                                OR REMOVE FROM SITE AS DIRECTED.
      j.     PAVEMENT REINFORCING                                                                       19. DRAWINGS TO BE READ IN CONJUNCTION WITH THE FOLLOWING
      k.     PAVEMENT PRIOR TO SEALING (PRESEAL)                                                            CONSULTANTS/CONTRACTORS DRAWINGS:

      l.     RETAINING WALL FOOTING REINFORCING                                                                     SURVEYOR:           DSQ LAND SURVEYORS

      m.     RETAINING WALL BLOCKWORK PRIOR TO CORE FILL                                                             ARCHITECT:         AND DESIGN                                                                                                LOCALITY PLAN

      n.     STEEL REINFORCEMENT OF CONCRETE STRUCTURES                                                             HYDRAULICS:         TBC                                                                                                       NOT TO SCALE
      o.     PRACTICAL COMPLETION                                                                                   STRUCTURAL:         RECOR CONSULTING

      p.     ON MAINTENANCE                                                                                         LANDSCAPE:          TBC

      q.     OFF MAINTENANCE                                                                            20. CONTRACTOR TO PREPARE AND HAVE APPROVED BY RELEVANT AUTHORITY: ROAD

      r.     ANY OTHER INSPECTION AS SPECIFIED BY LOCAL COUNCIL (REFER DEVELOPMENT
                                                                                                            OPENING PERMIT AND TRAFFIC MANAGEMENT PLAN FOR ALL WORKS WITHIN COUNCIL
                                                                                                            ROAD RESERVES. CONTRACTOR TO ALLOW FOR ALL COSTS ASSOCIATED WITH
                                                                                                                                                                                                                                        DRAWING SCHEDULE
             APPROVAL)                                                                                      IMPLEMENTATION OF THE TMP.
      s.     ANY OTHER INSPECTION AS REQUIRED BY UNITY WATER AND WHERE RELEVANT TO
                                                                                                                                                                                             DRAWING NUMBER                                       DRAWING TITLE                                    REVISION
                                                                                                        21. ALL WORKS TO BE COMPLETED IN ACCORDANCE WITH ALL LOCAL AUTHORITY APPROVALS
             THEIR CERTIFICATION SCHEME                                                                     RECEIVED FOR THE PROJECT
                                                                                                        22. CONTRACTOR TO UNDERTAKE ALL WORKS IN ACCORDANCE WITH OPW APPROVALS BY
                                                                                                                                                                                                         C01                        COVER SHEET AND LOCALITY PLAN                                         B
                                                                                                            COUNCIL.
GENERAL NOTES                                                                                                                                                                                           C10                       EXISTING SITE SERVICES LAYOUT PLAN                                      B
                                                                                                        23. NO WORKS ARE TO BE UNDERTAKEN ON LAND OUTSIDE OF THE SITE BOUNDARY WITHOUT
1.         ALL DIMENSIONS SHOWN ARE IN METERS UNLESS OTHERWISE SHOWN.
                                                                                                            FORMAL APPROVAL BY THE OWNER/CUSTODIAN OF THAT LAND INCLUDING BUT NOT
2.         ALL SETOUT ON SITE IS THE SOLE RESPONSIBILITY OF THE CONTRACTOR. CONTRACTOR                      LIMITED TO PRIVATE PROPERTY, ROAD RESERVE, PARKS/OPENSPACE, EASEMENTS.                      C20              EROSION AND SEDIMENT CONTROL LAYOUT PLAN AND DETAILS                             B
           TO ALLOW FOR ALL MEANS NECESSARY TO ACCURATELY SETOUT THE WORKS.
                                                                                                        24. THE CONTRACTOR SHALL HAVE AN APPROVED SET OF CONSTRUCTION DRAWINGS AND
3.         ALL WORKS TO BE CONSTRUCTED IN ACCORDANCE WITH PROJECT SPECIFICATIONS AND                        APPROVALS ON SITE AT ALL TIMES.
                                                                                                                                                                                                        C30                          BULK EARTHWORKS LAYOUT PLAN                                          B
           WHERE FURTHER DETAILS ARE REQUIRED THE CONTRACTOR SHALL REFER TO NOOSA
           SHIRE COUNCIL DEVELOPMENT GUIDELINES, LOCAL WATER AUTHORITY GUIDELINES,
                                                                                                        25. ALL WATER AND SEWER RETICULATION WORKS TO BE CONSTRUCTED IN ACCORDANCE
                                                                                                            WITH THE SEQ WATER SUPPLY AND SEWERAGE DESIGN AND CONSTRUCTION CODE (2013).
                                                                                                                                                                                                         C31                           BULK EARTHWORKS SECTIONS                                           B
           ASSOCIATED STANDARD DRAWINGS AND SPECIFICATIONS U.N.O.
4.         SHOULD ANY OF THE CONSTRUCTED WORKS BE CONSTRUCTED OUTSIDE OF THE                                                                                                                            C32                          BULK EARTHWORKS SECTIONS #2                                          B
           TOLERANCES SPECIFIED WITHIN THE PROJECT SPECIFICATION AND LOCAL AUTHORITY
           REQUIREMENTS, THE CONTRACTOR WILL RECTIFY AT THEIR COST INCLUSIVE OF ANY                                                                                                                     C33                           BULK EARTHWORKS SECTION #3                                          B
           ADDITIONAL COSTS INCURRED BY RECOR.
5.         EXISTING SERVICES HAVE BEEN PLOTTED FROM SUPPLIED DATA AND AS SUCH THEIR                                                                                                                     C40                      STORMWATER CATCHMENT LAYOUT PLANS                                        B
           ACCURACY CANNOT BE GUARANTEED. NO RESPONSIBILITY IS TAKEN BY RECOR OR THE
           PRINCIPAL FOR THE ACCURACY AND COMPLETENESS OF THIS INFORMATION. IT IS THE
           RESPONSIBILITY OF THE CONTRACTOR TO ACCURATELY ESTABLISH THE LOCATION AND
                                                                                                                                                                                                        C50                        ROADS AND DRAINAGE LAYOUT PLAN                                         B
           LEVEL OF ALL EXISTING SERVICES PRIOR THE COMMENCEMENT OF ANY WORKS. ANY
           DISCREPANCIES SHALL BE REPORTED TO THE SUPERINTENDENT. CONTRACTOR TO                                                                                                                          C51                           ROADS AND DRAINAGE DETAILS                                         B
           LOCATE AND PROTECT SERVICES AS REQUIRED DURING PROPOSED WORKS.
6.         THE CONTRACTOR IS TO CHECK THROUGH LOCATING, POTHOLING AND SURVEY ALL                                                                                                                        C52                          ROADS AND DRAINAGE DETAILS #2                                        B
           CRITICAL CONNECTION POINTS FOR ALL CIVIL WORKS SHOWN ON THE DRAWINGS
           INCLUDING ANY POTENTIAL EXISTING SERVICES CLASHES PRIOR TO COMMENCEMENT OF                                                                                                                   C53                        ROAD AND DRAINAGE LONG SECTIONS                                        B
           CIVIL WORKS. CONTRACTOR TO IMMEDIATELY REPORT ANY DISCREPANCIES TO RECOR
           AND AWAIT FORMAL DIRECTION PRIOR TO COMMENCING CIVIL WORKS.
                                                                                                                                                                                                        C54                      ROAD AND DRAINAGE LONG SECTIONS #2                                       B
7.         ON COMPLETION OF SERVICES INSTALLATION, ALL DISTURBED AREAS SHALL BE
           RESTORED TO ORIGINAL LEVEL, INCLUDING KERBS, FOOTPATHS, CONCRETE AREAS,                                                                                                                      C55                             TYPICAL DRIVEWAY SECTIONS                                         B
           GRAVEL AREAS, GRASSED AREAS AND ROAD PAVEMENTS.
8.         CONTRACTOR SHALL BE RESPONSIBLE FOR REPAIR OF ANY DAMAGE TO                                                                                                                                  C56                             RETAINING WALL ELEVATIONS                                         B
           AUTHORITY/COUNCIL'S INFRASTRUCTURE. SUCH REPAIR OR REINSTATEMENT TO BE
           CARRIED OUT IMMEDIATELY TO THE SATISFACTION OF INFRASTRUCTURE
           OWNER/MANAGER / AUTHORITY/COUNCIL.
                                                                                                                                                                                                        C57                          RETAINING WALL TYPICAL DETAIL                                        B
9.         CONTRACTOR TO UNDERTAKE ALL WORKS IN ACCORDANCE WITH ALL WORKPLACE
           HEALTH AND SAFETY REQUIREMENTS.
                                                                                                                                                                                                        C60                             VEHICLE SWEPT PATHS 1 OF 3                                        C
10.        WHERE ANY EXCAVATION OR CONSTRUCTION WORKS ARE TO BE IN CLOSE PROXIMITY TO                                                                                                                    C61                            VEHICLE SWEPT PATHS 2 OF 3                                        C
           NEIGHBOURING LOT BOUNDARIES OR INFRASTRUCTURE, CONTRACTOR TO ALLOW IN
           SCOPE OF WORKS TO PROVIDE ALL MEASURES NECESSARY TO ENSURE THE INTEGRITY
           OF EXISTING BOUNDARIES AND INFRASTRUCTURE. THIS MAY INCLUDE THE USE OF LOW                                                                                                                   C62                             VEHICLE SWEPT PATHS 3 OF 3                                        C

                                                                                                                                         CLIENT DETAILS:                                     PROJECT ADDRESS:                      APPROVED BY:                   PROJECT NAME:

                                                                                                                                                                                                                                                                  PROPOSED RESIDENTIAL DEVELOPMENT
                                                                                                                                                     SUNSHINE GROVE PTY LTD                                                                                       TITLE:                STATUS:

                                                                                                                                                                                                           9 KAURI STREET                                         COVER SHEET AND      MATERIAL CHANGE OF USE
                    © ABN 89 647 469 707
                                                            B    28/10/22   RFI ISSUE                             BRP             BRP
                                                                                                                                                                                                          COOROY, QLD, 4563                  BEN PARRY            LOCALITY PLAN        AND
                                                                                                                                                                                                                                             RPEQ: 28084
                       37 MARY ST
                   NOOSAVILLE, QLD 4566
                                                            A    10/08/22   COMBINED MCU AND OP WORKS ISSUE       JAC     BRP     JB     SCALE:
                                                                                                                                                                                                                                             CPEng NER
                                                                                                                                                                                                                                                                                       OPERATIONAL WORKS
                      +61 7 5211 1003                      REV    DATE                  DESCRIPTION              DWN     CHK      APP
                                                                                                                                                               AS INDICATED                                                                 DATE: 28/10/22
                                                                                                                                                                                                                                                                  DRAWING NUMBER:       PROJECT NUMBER:       SHEET REV:
                                                                                                                                                                                                                                                                                                               SIZE:
                  RECORCONSULTING.COM                                                       REVISIONS
                                                                                                                                                             DO NOT SCALE, IF IN DOUBT ASK
                                                                                                                                                                                                                                                                  C01                   20220156              A1 B
Log in to download the original file

RFI - 20220156 Kauri St SWMP Rev B.pdf · 8.2 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.