General: Kerb inlet the imminent rainfall and run-off.
1. Refer drg no. C101, which is to be requested and viewed prior to commencement of15.construction
For kerb inlet standard detail and specification refer to international erosion control association
c. All reasonable and practicable steps have been taken to treat the water within
if not supplied. Australasia (IECA) best practices standard drawing esc-03 kerb inlet sediment traps.
best-practice time frames;
Check dams d. Flocculent has been appropriately applied and the concentration of TSS in the captur
Sediment control
2. All erosion and sediment control measures to be in accordance with international 16. For control
erosion water has already significantly decreased.
check dam standard detail and specification refer to international erosion control association
association (IECA) Australia guidelines and the specifications. Australasia (IECA) best practices standard drawing rcd-01 check dams.
3. Erosion and sediment control details shown are minimum requirements. It is the contractors 27. For all other stormwater releases, flows and discharges from the site, the release limit
responsibility to install additional control measures as deemed necessary throughout
construction. Revegetation prescribed in (1a) above must not be exceeded unless the development is in full complian
4. 17. order
The contractor is responsible to maintain all sediment control devices in a functional For revegetation
and this standard.
standard specification refers to international erosion control association
Australasia (IECA) best practices standard drawing R-01 revegetation general.
replace all blocked sediment devices as required until successful off maintenance of works.
5. Construction of all sediment management devices to the satisfaction of the superintendent. Shall 28. It is recommended that a site-specific relationship between turbidity and suspended solid
be completed and effective prior to: determined for each sediment basin. Once a correlation between suspended solids and tu
a. Stripping of topsoil and grass. Field inlet has been established for a sediment basin, testing stormwater for compliance with relea
limits, prior to release, can be done on site with a turbidity tube or calibrated turbidity
18. For field inlet standard detail and specification refer to international erosion control association
b. Bulk earthworks to the site. This has the advantage of providing immediate assessment to justify a release rather t
Australasia (IECA) best practices standard drawing ESC-02 grated stormwater (field) inlet
c. Services installation. sediment trap. waiting for laboratory results to confirm concentration levels and compliance. Note that
post-release TSS validation is appropriate to demonstrate that the NTU/TSS correlatio
d. Pavement construction. being maintained.
6.
Operation and maintenance
All sediment management measures are to remain in place until instruction is received in writing
from the superintendent to remove all or part of the silt control applications. 19. In accordance with council esc guidelines, all esc measures shall be inspected: 29. Background refers to receiving water quality immediately upstream of the site location r
7. The bulk earthworks and sediment control layout plan shall be read in conjunction20.withAttheleast daily (when work is occurring on site) or weekly (when work is not Occurring point at the time of release. Where there is no immediate upstream receiving water at t
on site)
approved drawings. location and time of release, then the turbidity release limit (NTU) will be equal to the
21. Within 24 hours of expected rain; and limit for 50mg/l total suspended solids (TSS) based upon the onsite correlation between
8. Prior to commencement of construction approval is to be obtained from the superintendent
22. Within for
18 hours of a rainfall event (i.e. An event of sufficient intensity and Duration to
andmobilise
NTU.
the location of the site access point and wash down area which are to be maintained throughout
sediment on site).
the construction period.
9. If erosion and sediment control devices have been found to be different or failed in service,
Contractor
corrective action is to be undertaken immediately which may include amendments' additions
original approved erosion control plans. Such amendments are to be approved by superintendent,
to the Update Requirements
if deemed necessary and relevant. 23. Civil contractor is to provide an updated program of ESC maintenance and control of all stages
of work for approval by the superintendent.
Overall
10. Temporary drainage control flow should be diverted around the work site where possible.
Sediment release guidelines:
11. All drainage, erosion and sediment controls to be installed and be operational before commencing
up-slope earthworks. 24. All releases of stormwater captured onsite, unless otherwise noted in this standard, must not
exceed the following limits:
12. In areas where runoff turbidity is to be controlled, exposed surfaces to be either mulched,
covered with erosion control blankets or turfed if earthworks are expected to be delayed for of total suspended solids (TSS) as a maximum concentration;
a. 50mg/l
more than 14 days.
b. Turbidity (NTU) value less than 10% above background;
Sediment fence c. Ph value must be in the range 6.5 to 8.5 except where, and to the extent that, the natural
13. For sediment fence standard detail and specification refer to international erosion controlreceiving waters lie outside this range.
association Australasia (IECA) best practices standard drawings sf-01 and sf-02 sediment fence.
Temporary construction entry/exit 26. The concentration of TSS released by dewatering may only exceed 50mg/l where it can be
demonstrated and supported through documentation that:
14. For construction entry / exit standard detail and specification refer to international erosion
a. Further significant rainfall is forecast to occur before the TSS concentration is likely to be
control association Australasia (IECA) best practices standard drawings exit-01 and exit-02
reduced
construction exit - rock pad (construction sites only), exit-03 - rock pads for building sites and to 50mg/l;
exit-04 and exit-05 construction exit - vibration grid. b. Releasing a higher concentration of total suspended solids will result in a better
environmental outcome by providing storage for the capture and treatment of run-off from
REV: DESCRIPTION: DATE DRAFT CHECKED APPROVED APPROVED BY: CLIENT: PROJECT: DRAWING TITLE:
13469
PROJECT NUMBER: A3 ORIGINAL
Signed: SIZE
Sunshine Coast Civil Engineers Copyright in the drawings, information and data recorded in this document is the property of Sunshine Coast Civil Engineers Pty Ltd. This document and
DRAWING NUMBER: REVISION:
the information are solely for the use of the authorized recipient and this document may not be used, copied, or reproduced in whole or in part for any
Date: 23/11/24 www.sunshinecoastcivilengineers.com purpose than that for which it was supplied by Sunshine Coast Civil Engineers Pty Ltd. This document shall only be used for construction if stamped and
approved for construction.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Engineering Plans.pdfRelated documentApplication case desk ↗
About this file
- File size
- 5.5 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.