    General:                                                                                Kerb inlet                                                                                    the imminent rainfall and run-off.
    1.   Refer drg no. C101, which is to be requested and viewed prior to commencement of15.construction
                                                                                               For kerb inlet standard detail and specification refer to international erosion control association
                                                                                                                                                                                       c. All reasonable and practicable steps have been taken to treat the water within
         if not supplied.                                                                      Australasia (IECA) best practices standard  drawing esc-03  kerb inlet sediment  traps.
                                                                                                                                                                                          best-practice time frames;
                                                                                            Check dams                                                                                   d. Flocculent has been appropriately applied and the concentration of TSS in the captur
    Sediment control
    2.   All erosion and sediment control measures to be in accordance with international 16.    For control
                                                                                            erosion                                                                                          water has already significantly decreased.
                                                                                                      check dam standard detail and specification refer to international erosion control association
         association (IECA) Australia guidelines and the specifications.                         Australasia (IECA) best practices standard drawing rcd-01 check dams.
    3.   Erosion and sediment control details shown are minimum requirements. It is the contractors                                                                                 27. For all other stormwater releases, flows and discharges from the site, the release limit
         responsibility to install additional control measures as deemed necessary throughout
         construction.                                                                      Revegetation                                                                                 prescribed in (1a) above must not be exceeded unless the development is in full complian
    4.                                                                                      17. order
         The contractor is responsible to maintain all sediment control devices in a functional  For revegetation
                                                                                                       and                                                                               this standard.
                                                                                                                   standard specification refers to international erosion control association
                                                                                                 Australasia (IECA) best practices standard drawing R-01 revegetation general.
         replace all blocked sediment devices as required until successful off maintenance of works.
    5.   Construction of all sediment management devices to the satisfaction of the superintendent. Shall                                                                           28. It is recommended that a site-specific relationship between turbidity and suspended solid
         be completed and effective prior to:                                                                                                                                            determined for each sediment basin. Once a correlation between suspended solids and tu
         a. Stripping of topsoil and grass.                                                 Field   inlet                                                                                has been established for a sediment basin, testing stormwater for compliance with relea
                                                                                                                                                                                         limits, prior to release, can be done on site with a turbidity tube or calibrated turbidity
                                                                                            18. For field inlet standard detail and specification refer to international erosion control association
         b. Bulk earthworks to the site.                                                                                                                                                 This has the advantage of providing immediate assessment to justify a release rather t
                                                                                                 Australasia (IECA) best practices standard drawing ESC-02 grated stormwater (field) inlet
         c. Services installation.                                                               sediment  trap.                                                                         waiting for laboratory results to confirm concentration levels and compliance. Note that
                                                                                                                                                                                         post-release TSS validation is appropriate to demonstrate that the NTU/TSS correlatio
         d. Pavement construction.                                                                                                                                                       being maintained.
    6.
                                                                                            Operation and maintenance
         All sediment management measures are to remain in place until instruction is received in writing
         from the superintendent to remove all or part of the silt control applications. 19. In accordance with council esc guidelines, all esc measures shall be inspected: 29. Background refers to receiving water quality immediately upstream of the site location r
    7.   The bulk earthworks and sediment control layout plan shall be read in conjunction20.withAttheleast daily (when work is occurring on site) or weekly (when work is not Occurring point      at the time of release. Where there is no immediate upstream receiving water at t
                                                                                                                                                                                             on site)
         approved drawings.                                                                                                                                                                  location and time of release, then the turbidity release limit (NTU) will be equal to the
                                                                                          21. Within 24 hours of expected rain; and                                                          limit for 50mg/l total suspended solids (TSS) based upon the onsite correlation between
    8.   Prior to commencement of construction approval is to be obtained from the superintendent
                                                                                          22.    Within for
                                                                                                          18 hours  of a rainfall event (i.e. An event of sufficient intensity and Duration to
                                                                                                                                                                                             andmobilise
                                                                                                                                                                                                  NTU.
         the location of the site access point and wash down area which are to be maintained throughout
                                                                                                 sediment    on site).
         the construction period.
    9.   If erosion and sediment control devices have been found to be different or failed in service,
                                                                                          Contractor
         corrective action is to be undertaken immediately which may include amendments' additions
         original approved erosion control plans. Such amendments are to be approved by superintendent,
                                                                                                       to the Update Requirements
         if deemed necessary and relevant.                                                23. Civil contractor is to provide an updated program of ESC maintenance and control of all stages
                                                                                                 of work for approval by the superintendent.
    Overall
    10. Temporary drainage control flow should be diverted around the work site where possible.
                                                                                         Sediment release guidelines:
    11. All drainage, erosion and sediment controls to be installed and be operational before commencing
        up-slope earthworks.                                                             24. All releases of stormwater captured onsite, unless otherwise noted in this standard, must not
                                                                                              exceed the following limits:
    12. In areas where runoff turbidity is to be controlled, exposed surfaces to be either mulched,
        covered with erosion control blankets or turfed if earthworks are expected to be delayed   for of total suspended solids (TSS) as a maximum concentration;
                                                                                              a. 50mg/l
        more than 14 days.
                                                                                              b. Turbidity (NTU) value less than 10% above background;
    Sediment fence                                                                             c. Ph value must be in the range 6.5 to 8.5 except where, and to the extent that, the natural
    13. For sediment fence standard detail and specification refer to international erosion controlreceiving waters lie outside this range.
        association Australasia (IECA) best practices standard drawings sf-01 and sf-02 sediment fence.

    Temporary construction entry/exit                                                      26. The concentration of TSS released by dewatering may only exceed 50mg/l where it can be
                                                                                                demonstrated and supported through documentation that:
    14. For construction entry / exit standard detail and specification refer to international erosion
                                                                                                a. Further significant rainfall is forecast to occur before the TSS concentration is likely to be
        control association Australasia (IECA) best practices standard drawings exit-01 and exit-02
                                                                                                    reduced
        construction exit - rock pad (construction sites only), exit-03 - rock pads for building sites and to 50mg/l;
        exit-04 and exit-05 construction exit - vibration grid.                                 b. Releasing a higher concentration of total suspended solids will result in a better
                                                                                                     environmental outcome by providing storage for the capture and treatment of run-off from

REV: DESCRIPTION:               DATE        DRAFT   CHECKED    APPROVED APPROVED BY:                                                                                                                    CLIENT:                                      PROJECT:                                     DRAWING TITLE:


                                                                                 13469
                                                                                                                                                                                                                                                                                                  PROJECT NUMBER:   A3 ORIGINAL
                                                                          Signed:                                                                                                                                                                                                                                   SIZE
                                                                                                     Sunshine Coast Civil Engineers    Copyright in the drawings, information and data recorded in this document is the property of Sunshine Coast Civil Engineers Pty Ltd. This document and
                                                                                                                                                                                                                                                                                                  DRAWING NUMBER:   REVISION:
                                                                                                                                       the information are solely for the use of the authorized recipient and this document may not be used, copied, or reproduced in whole or in part for any
                                                                          Date: 23/11/24           www.sunshinecoastcivilengineers.com purpose  than that for which it was supplied by Sunshine Coast Civil Engineers Pty Ltd. This document shall only be used for construction if stamped and
                                                                                                                                       approved for construction.

Used in these records

About this file

File size
5.5 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Engineering Plans.pdf · 5.5 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.