Skip to the record
The first. The best. The only NoosaWatch™.

Original source · versioned page text

2020-01-13 GC Agenda - Item 6 - Attachment 1 - Noosa District Sports Complex Master Plan

of 48

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
Table 5: Facility improvements as shown on Concept master plan
 Plan Ref       Zone                    Facility Description                                                                                  Priority
 A              Rugby League            Upgrade playing fields:                                                                               Short - Medium
                                        • 2 x rectangular rugby league fields, located to accommodate pedestrian and roadway realignments
                                        • Irrigation and improved field drainage
                                        • Re-sow surface to high-wear turf species
                                        • Replace fittings (as required) with 150 lux LED lights
                                        • Accessible point – emergency access (ambulance)
                                        • Extend existing pathways to provide a 3m wide pedestrian path around the main (eastern) field for
                                        pedestrian and cycle access to rugby league fields and clubhouse (northside of the viewing mound)
                                        • Viewing mound to be maintained.
 B                                      Redevelopment and expansion of rugby league building to:                                              Medium
                                        • Provide indoor spaces that can accommodate for community programming and training facilities,
                                        allied health provision, fitness equipment and function area.
                                        • Provide upgraded amenities and change rooms in line with NRL guidelines, DDA compliant and
                                        accommodating the needs of female players and visitors.
                                        • Provision of seating areas – some undercover (100-150 pax)
                                        • Add solar panels and water harvesting infrastructure (including tanks)
                                        • Grounds maintenance store
 C              Netball                 Upgrade netball courts:                                                                               Short
                                        • Ensure adequate runoff 3.05m
                                        • Replace fittings (as required) with (min) 100 lux LED lights
 D                                      Resurface 1 x grass courts to hardcourt surface                                                       Short
 E                                      Resurface 4 x asphalt courts to hardcourt surface                                                     Short
 F                                      Resurface courts remaining 7 x hardcourt                                                              Medium - Long
                                        Fencing to perimeter of courts area
 G                                      Redevelop/ reconfigure/ expand netball amenities/ administration building to 300m2                    Short - Medium
                                        • Improve provision of amenities for players
                                        • Add solar panels and rainwater collection tanks for reuse
                                        • Improve drainage between Internal road and netball building
 H              Cricket                 Second oval:                                                                                          Medium
                Main Complex            • 52.5m radius from outer most of 4 corners of wicket block
                                        • 4 x 3.05m turf pitches
                                        • 2.74m min safety runoff (boundary to fence) or 2m between playing field boundaries
                                        • Improved field drainage
                                        • Lighting to 300-500 lux outfield




Noosa Council  Noosa District Sports Complex Master Plan 2020-2030  Final                                                                            Page 30
Log in to download the original file

2020-01-13 GC Agenda - Item 6 - Attachment 1 - Noosa District Sports Complex Master Plan(PDF, 8MB).pdf · 8.7 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.