DERM Referral Agency response 132006.1168.02
ecoaccess and permits
SCHEDULE E - LAND APPLICATION
Release of Contaminants to Land
(El) Except as otherwise provided by the conditions of the land application schedule of this development
approval the environmentally relevant activity must be carried out by such practicable means
necessary to prevent or minimise the release or likelihood of release of contaminants to land.
(E2) At the approved place, the only contaminants allowed to be released are reclaimed waters from the
sewage treatment plant.
Opportunistic Reuse of Treated Sewage Effluent
(E3) Reclaimed waters are only permitted to be used at the approved places, for various types of reuse
purposes such as dust suppression on road works and irrigation of gardens, provided the reclaimed
water reuse is carried out in accordance with the latest edition of the Queensland Water Recycling
Guidelines December 2005, including the required level of treatment, effluent quality, effluent
monitoring and monitoring frequency and the specified controls and requirements.
(E4) The contaminants released must also comply with the following qualitative characteristics:
(i) The release must not have any properties nor contain any organisms or contaminants in
concentrations or which, in the opinion of the administering authority, are capable of causing
environmental harm or an environmental nuisance.
(E5) Public access to any contaminant release area on land at the approved place must be denied if the
reclaimed water does not comply with the Queensland Water Recycling Guidelines December 2005
for public contact.
(E6) Spray from any release of contaminants to land must not drift beyond the boundaries of the approved
place.
(E7) The irrigation of reclaimed waters must be carried out in a manner such that:
- vegetation is not damaged;
- soil erosion and soil structure damage is avoided;
- there is no surface ponding of reclaimed water;
- percolation of reclaimed water beyond the plant root zone is minimised;
- the capacity of the land to assimilate nitrogen, phosphorous, salts, organic matter as measured
by oxygen demand and water is not exceeded; and
- the quality of groundwater is not adversely affected.
(E8) The contaminant release areas must be maintained in a proper and efficient manner so as to provide
adequate assimilation, percolation, evaporation and transpiration of the wastes released to the
disposal areas.
(E9) The release of contaminants to land must be carried out in such a manner that there is no ponding or
pooling of contaminants on the surface of the contaminant release area(s) nor seepage of
contaminants from the contaminant release area(s) to any waters or stormwater drain.
(E10) Reclaimed waters must not be released to the contaminant release area(s) during and immediately
after rainfall.
(Ell) Where applicable, crop cover must be regularly harvested and removed from contaminant release
areas.
' Permit includes licences, approvals, permits, authorisations, certificates, sanctions Page 12 of 21
or equivalent/similar as required by legislation administered by the
Department of Environment and Resource Management
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
DERM Referral Agency response 132006.1168.02Related documentApplication case desk ↗
About this file
- File size
- 2.5 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.