Original source · versioned page text
20181085-ASC12 - Ballada Pty Ltd v North Point Brisbane & Anor [2013] QCATA 184
Attached to the e-mail Operational Works Application OPW20/0114 - Email 4 of 4 -Engineering Certificate - Engineering Drawings - QCAT Appeal - 4 Portside Crt, Noosaville.
5KIPGFD[#WUV.++
4
[9] The present appeal is governed by s 146 of the Queensland Civil and
Administrative Tribunal Act 2009 (“the QCAT Act”). Such an appeal,
which is on a question of law only, is confined to the evidence that was
obtained by or presented to the Adjudicator.
[10] The material attached to the application for appeal contains a quantity of
documents, and seeks to raise some issues that were not raised before
the Adjudicator. There was adequate opportunity for the parties to raise
the issues about which they were in dispute, and to present all relevant
material during that procedure. The appeal must of course be confined to
the evidence and issues that were presented to the Adjudicator.
[11] The ultimate issue is whether the Adjudicator has shown to have erred on
a question of law that affected the outcome.
Facts
[12] Until 2011 the air conditioning system for the building was a “water based”
system operated from a cooling tower on the roof, with individual unit
systems in each unit which, upon failure, would be replaced or repaired by
individual owners.
[13] At the Annual General Meeting of 19 April 2011 it was unanimously
resolved to discontinue the current water cooling air-conditioning system
and install an individual system for each lot, with ownership of those
systems to be transferred to each lot owner. The minutes noted that the
work would be conducted on the lower levels as the first measure. Neither
applicant voted on the issue.
[14] Further planning and negotiation with contractors led the management
committee to the view that some variation of the original planning was
necessary. Proposals for the updated changes, including full quotations
and specifications concerning the system upgrade were notified for
consideration at an EGM on 12 July 2011. Notice was sent to all owners
dated 20 June 2011 of the resolutions that were considered necessary in
order for the matter to proceed. The agenda included 8 motions, 4 of
which were listed as motions requiring resolution without dissent.
[15] The applicant Ballada acted at material times through Mr Kildey, an
architect. The initial dispute the subject of his application was his claim
that he cast a valid postal vote against the proposals, and that it was
never acknowledged or counted.
[16] The relevant circumstances surrounding this issue are canvassed in some
detail in the reasons for judgment of the Adjudicator dated 7 August 2012,
particularly at paragraphs [24] to [30], and [37] to [44].
[17] Mr Kildey stated that he personally posted voting papers to the body
corporate manager (Stewart Silver King & Burns) on 7 July 2011. On the
other hand, the body corporate manager provided evidence that no such
4GVTKGXGFHTQO#WUV.++QP/CTEJCV 8GTKH[XGTUKQP
[OCR of page images]
Signed by AustLll
[9]
[10]
[11]
The present appeal is governed by s 146 of the Queensland Civil and
Administrative Tribunal Act 2009 (“the QCAT Act’). Such an appeal,
which is on a question of law only, is confined to the evidence that was
obtained by or presented to the Adjudicator.
The material attached to the application for appeal contains a quantity of
documents, and seeks to raise some issues that were not raised before
the Adjudicator. There was adequate opportunity for the parties to raise
the issues about which they were in dispute, and to present all relevant
material during that procedure. The appeal must of course be confined to
the evidence and issues that were presented to the Adjudicator.
The ultimate issue is whether the Adjudicator has shown to have erred on
a question of law that affected the outcome.
Facts
[12]
[13]
[14]
[15]
[16]
[17]
Until.2011 the air conditioning system for the building was a “water based”
system operated from a cooling tower on the roof, with individual unit
systems in each unit which, upon failure, would be replaced or repaired by
individual owners.
At the Annual General Meeting of 19 April 2011 it was unanimously
resolved to discontinue the current water cooling air-conditioning system
and install an individual system for each lot, with ownership of those
systems to be transferred to each lot owner. The minutes noted that the
work would be conducted on the lower levels as the first measure. Neither
applicant voted on the issue.
Further planning and negotiation with contractors led the management
committee to the view that some variation of the original planning was
necessary. Proposals for the updated changes, including full quotations
and specifications concerning the system upgrade were notified for
consideration at an EGM on 12 July 2011. Notice was sent to all owners
dated 20 June 2011 of the resolutions that were considered necessary in
order for the matter to proceed. The agenda included 8 motions, 4 of
which were listed as motions requiring resolution without dissent.
The applicant Ballada acted at material times through Mr Kildey, an
architect. The initial dispute the subject of his application was his claim
that he cast a valid postal vote against the proposals, and that it was
never acknowledged or counted.
The relevant circumstances surrounding this issue are canvassed in some
detail in the reasons for judgment of the Adjudicator dated 7 August 2012,
particularly at paragraphs [24] to [30], and [37] to [44].
Mr Kildey stated that he personally posted voting papers to the body
corporate manager (Stewart Silver King & Burns) on 7 July 2011. On the
other hand, the body corporate manager provided evidence that no such
Retrieved from AustLII on 30 March 2020 at 16:29:45
Verify version
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.