For further details on the LV circuit reticulation refer the MDA Consulting Engineers drawings listed

below:


     12059-LV-URD01        LV CONCEPT SHEET 1 OF 5

     12059-LV-URD02        LV CONCEPT SHEET 2 OF 5

     12059-LV-URD03        LV CONCEPT SHEET 3 OF 5

     12059-LV-URD04        LV CONCEPT SHEET 4 OF 5

     12059-LV-URD05        LV CONCEPT SHEET 5 OF 5




Both the HV and LV Concept Master Plan drawings have been submitted to Energex. Energex have

reviewed the concept and has accepted the concept master planning for both the HV and LV for the

proposed development.

3    Communication Services Infrastructure

For the reticulation of the communication network NBN where consulted in relation to their latest

standards and specifications along with the roll out of the NBN Fibre network within the local area.


NBN advised that even though there are no current project that are on the books for the rollout of

the NBN fibre network with the local area a development ofthis size and nature would definitely

meet the criteria for fibre rollout.



NBN also advised that they do not require any input at the development application stage, however

as the   proposed development was of a significant size NBN were of the opinion that it was in their
best interest to review any concept master planning of the communication infrastructure for the

development. NBN advised that for the concept master plan of the communication infrastructure an
underground pit and pipe system would be required to be design in accordance with their standards
and specifications. The future point of connection for the NBN system was determined by NBN to be

on the corner of Eumarella     Road and Walter Hay Drive.


As the proposed communication infrastructure pit and pipe system will be able to share the trench

with the Energex network the majority of the proposed communication. For the full details on the

pit and pipe reticulation for the communication infrastructure refer the MDA Consulting Engineers
drawings listed below:

         12059-NBN01       NBN CONCEPT SHEET 1 OF 8

         12059-NBN02       NBN CONCEPT SHEET 2 OF 8

         12059-NBN03       NBN CONCEPT SHEET 3 OF 8

         12059-NBN04       NBN CONCEPT SHEET 4 OF 8

         12059-NBN05       NBN CONCEPT SHEET 5 OF 8

         12059-NBN06       NBN CONCEPT SHEET 6 OF 8

         12059-NBN07       NBN CONCEPT SHEET 7 OF 8

         12059-NBN08       NBN CONCEPT SHEET 8 OF 8




It must also be noted that the NBN pit and pipe specification is of industry standards which means

that once installed if any other service provider i.e. Telstra, Opticom etc wishes to enter into a



Noosa on Weyba                                                                            Rev 2 23/10/2012
                                                                                               -




Electrical and Communication                          Page 15                              Project No:12059

Used in these records

About this file

File size
2.2 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Part 21 of 37 Appendix 19 - Electrical and Telecommunication Services MCU12_0208.pdf · 2.2 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.