20222109 Stop the Clock
Attached to the e-mail MCU22/0094 - Stop current period to 28.10.22.
Notice to stop the current period Section 32 of the Development Assessment Rules MCU22/0094 [application reference number] Stockwell Development Group Pty Ltd [applicant’s name] PO Box 3144, South Brisbane QLD 4101 / [email protected] [contact address/email address] 0403181767 [contact number] 28/09/2022 [notice date] Noosa Council [name of assessing authority/authorities notice is being Managing Development Assessor: Kerri Coyle given to] Coordinator Planning: Patrick Murphy PO Box 141, TEWANTIN QLD 4565 [address of assessing authority/authorities notice is being Delivered via email to [email protected] given to] RE: Development application for: Material Change of use for childcare centre Noosa Civic 28 Eenie Creek Road, Noosaville QLD 4566 Lot 3 SP 246584 (Proposed Lot 4) Dear Kerri Coyle and Patrick Murphy, We wish to exercise a stop the clock for the following reasons. We require additional time to respond to the information request dated 28 June 2022 which requires a response by 30 September 2022 To provide sufficient time for these actions to occur, Stockwell proposes to immediately stop the current period, being the Information Request part (Part 3), pursuant to Section 32.4 of the DA Rules. Section 32.4 (b) of the DA Rules states that the application must: (i) Have been accepted as a properly made application; and (ii) Not be in the public notification period. The application was properly made on 31 May 2022. Regards, Leanne Porter Stockwell Development The Planning Act 2016 is administered by the Department of Local Government, Infrastructure and Planning, Queensland Government. Page 1 Applicant template 9.0 Version 1.0—3 July 2017
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 1 page
Page 2
In accordance with section 32 of the Development Assessment Rules, please be advised I am stopping
the following current period:
Part 3 – Information Request Period
[Identify the period in the
development assessment process under the Development Assessment Rules
that is being stopped by this notice.]
This current period will be stopped for the following period:
28 September 2022 to 28 October 2022 Identify period for stop to apply.]
Upon giving this notice, the number of business days remaining in the cumulative period under
section 32.6(b) of the Development Assessment Rules is:
100 days remain
If you wish to discuss this matter further, please contact me on the above telephone number.
Yours sincerely
Leanne Porter 28/09/2022 [applicant, signature and date]
cc: Assessment manager [where notice is being given to a referral agency]
Page 2
Planning Act Form 2 – Decision notice (approval)
Version 1.0—3 July 2017