Skip to the record
The only place to find full transcripts.

Original source · versioned page text

TIA - Application decision - s62A (PA) - Approval_1

Attached to the e-mail MCU23/0079 - SARA approval.

of 12

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

No. Conditions of Development Approval                                   Condition Timing

2    (a) Road access works comprising a vehicle crossing –               (a) & (b) Prior to commencement of
     residential driveway, must be provided at the permitted road        use and to be maintained at all
     access location, in particular:                                     times.
          The crossover must be 5.5m wide at the property
            boundary, extending from the pavement edge of Cooroy
            Connection Road to a minimum of 6m within the property
            boundary.

     (b) The road access works must be designed and constructed in
     accordance with Department of Transport and Main Roads:
          Institute of Public Works Engineering Australasia
            (IPWEA), Standard Drawing RS-049 & RS-050.
          Department of Transport and Main Roads' Road
            Planning and Design Manual, 2nd Edition.
3    Direct access is not permitted between Cooroy Connection            At all times.
     Road and Lot 22C5605, at any location other than the permitted
     access locations identified in Condition 1.



    Reasons for the decision
    The reasons for this decision are as follows:
       a) Vehicular access must not compromise safety of the users of the state-controlled road
           network.
       b) The safety of users of the state-controlled road network is the primary consideration for all
           works in a state-controlled road corridor.

    Please refer to Attachment A for the findings on material questions of fact and the evidence or
    other material on which those findings were based.

    Information about the Decision required to be given under section 67(2) of TIA
    1. There is no guarantee of the continuation of road access arrangements, as this depends on
        future traffic safety and efficiency circumstances.

    2. In accordance with section 70 of the TIA, the applicant for the planning application is bound by
       this decision. A copy of section 70 is attached as Attachment B, as required, for information.

    Further information about the decision
    1. In accordance with section 67(7) of TIA, this decision notice:
           a) starts to have effect when the development approval has effect; and
           b) stops having effect if the development approval lapses or is cancelled; and
           c) replaces any earlier decision made under section 62(1) in relation to the land.

    2. In accordance with section 485 of the TIA and section 31 of the Transport Planning and
       Coordination Act 1994 (TPCA), a person whose interests are affected by this decision may
       apply for a review of this decision only within 28 days after notice of the decision was given




                                                                                                 Page 2 of 12
Log in to download the original file

TIA - Application decision - s62A (PA) - Approval_1.pdf · 406 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.