PLANNING & ENVIRONMENT COMMITTEE MEETING 6 JUNE 2023
Nil
Finance
Funding of $500,000 under the Federal Government’s Community Batteries for Household Solar -
Delivery of Election Commitments Stream 1, subject to acceptance of the Grant Agreement.
Risk & Opportunities
Program Risks Mitigation
Council does not have the expertise to The TCP mitigates this risk by utilising the expertise of YEF
go directly to market and assess
tenders
Project does not meet the required The TCP has been identified as the most expedient method
timeframes stipulated in the grant to achieve the timelines stipulated in the grant funding
agreement agreement by direct engagement with YEF.
The TCP has been identified as the most likely method to
Project deliverables deviate from
achieve the deliverables of the grant agreement as YEF has
those stipulated in the grant
experience and expertise in delivering a community battery
agreement
in accordance with grant deliverables
Financial Risks Mitigation
Indicative costs of similar projects informed the grant
Installation of the Noosaville
application. The TCP enables the opportunity to engage YEF
community battery exceeds grant
to deliver the project in accordance with the budget and
allocation funding
deliverables stated in the grant application
All other jurisdictions in Australia have trial battery tariffs.
Commercial returns not realised and Energex is currently determining their battery tariffs to
community benefit fund limited accommodate the forthcoming community batteries into Qld.
The financial risk is low.
Insurance Cost of battery could Insurance will be provided as part of Council’s general
exceed budget and therefore insurance for assets.
community benefit fund could be
limited
Resource Risks Mitigation
The TCP enables direct engagement of YEF to manage
resources and subcontractors in accordance with the project
Quality, safety, and service are plan stated in the grant application. YEF is a highly
affected due to resource shortages experienced team with experience in implementing
community batteries for community benefit and emission
reduction.
Legislative Compliance Risks Mitigation
The Tender Consideration Plan is an appropriate
procurement exception under the Regulation, for a
Compliance issues
procurement of this nature, including due to this being a pilot
project for Council.
Safety Risks Mitigation
Page 6 of 67
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.