Service Outputs – Detailed Activity Listing
Activity Service Level/Standard
Stormwater system maintenance & operations
[Includes inspections and routine maintenance/repairs of culverts, pipes, inlet pits & outlets, subsoil drains,
open channels, retardation basins, retention basins and gross pollutant traps to ensure the stormwater drainage
network is operating effectively]
Cyclic Inspections1 Culvert/pipes inlets & outlets Six monthly
Major GPTs at Sunshine Beach, 4 times per year (quarterly)
Noosa Junction, Hastings St,
Cooyar St.
Minor GPTs 3 times per year (tri-annual)
Note: Audit done on bio-retention
basins and data validated. Program
being developed to bring these assets
to standard and then operating costs
will need to be funded in budget for
routine maintenance work. Currently
not done – service gap.
Park Road slip area (beginning of
Boardwalk to First Point):
• Subsoil drainpipe camera check Annually
• Dipping points checked/cleaned Quarterly
• During intense rainfall Weekly
Scheduled Work As identified from inspections (defects & proactive interventions) to maintain
free flow of stormwater with specific requirements as follows:
GPTs (major) 4 times per year (quarterly)
Note: Audit done on bio-retention
basin and data validated. Program
being developed to bring these assets
to standard and then operating costs
funded in budget for routine
maintenance work.
GPTs(minor) 3 times per year (tri-annual)
De-silting of stormwater lines As required
Reactive work 2 All requests 20 business days (target days for
completion)
Stormwater “as constructed” search 2 business days
Flood alert & mitigation maintenance and operations
[Works to maintain, repair and operate the flood alert system and flood mitigation infrastructure]
Cyclic inspections Flood alert towers/structures Annual
Flood alert stations (telemetry) Annual (with BOM technician)
Flood maximum height gauges (static Annual
measuring tool in event of telemetry
failure)
Daintree Estate3 flood mitigation &
drainage inspections check:
• Concrete and earth levee (qualified Annual (September)
professional)
• Level of debris/blockages along Annual pre-wet season + as
levee wall required
• culverts and ensure clear of debris
blockage Annual pre-wet season + as
required
143 of 173
Page 347 of 392
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (190f110f82.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.