NOOSA SHIRE COUNCIL

PLANS APPROVED

 

2.0, Scope of Works

The scope of refurbishment works are indicated on the plans in Appendix A and are
described as follows:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Administration Not | General Ensure efficient $10 000
marked | Administration management and
administration of project
Undertake A Amend boundary | Building is partly located | $8000
boundary . : over adjacent parcel of Negotiations with
alteration land adjacent land owner,
Survey, Applications to
Council and Title
Office,
Undertake Not | Undertake other Statutory compliance $55 000
required planning, | marked | required planning, ’ | Planning consultancy,
building health building health architectural
applications applications consultancy, application
: fees, see
Building works Not | Engage building Statutory:compliance $5000
certification marked | certifier :
Removal of stored |" Not | Remove To allow use of theatre to | $8000.
items marked | unnecessary stored | full extent. Labour, Hire of skips
: items from theatre . ‘ :
Re-roofing of B Re~roof existing | Existing roof is in poor $70 000
building . building with state. Materials, labour
custom orb roofing
Includes
“superstructure” to
: correct bow in roof
Completion of : Not | Completion of Ensure stability of $40 000
restumping. marked | restumping building foundations Materials, labour
Completion of Not | Completion of Ensure electrical safety $30 000
rewiring marked | rewiring . Materials, labour
Reconstruction of Cc Reconstruct and Allows better functioning | $60 000
roof over stage raise roof over stage area Materials, labour
stage area , ; ,
Raise floor level D Raise floor level to | Allows better functioning | $40 000
at south of match rest of off stage area Materials, labour
existing stage theatre . 1
Reconstruct E Reconstruct Allows functioning of $5000
loading dock at ° decking and install | rear loading dock. Materials, labour
se tte nde Teen Font 3

 

 

 

Used in these records

About this file

File size
1.7 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

0-Response to Objection Received during Public Notification Period.pdf · 1.7 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.