FIGURE 2.5: FREEBOARD ASSESSMENT 2.2.1.3 Channel and Culvert Scour Protection The maximum velocity in the proposed culvert outlet is 2.10 m/s. As such, scour protection is recommended in accordance with the Queensland Urban Drainage Manual. This guideline recommends rock size D50 = 200mm and extend 3.6m past the outlet. Velocities within the flow path are generally less than 2.0m/s, however, there a section between the foot bridge and Serenity Close, where the velocities are up to 2.30 m/s. It is recommended that reinforced turf is considered in this section of the channel (approx. CH150 to 170). NOOSA CALILE I BBNE01676-0001-REP-001-1 12
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Response to Information Request 10-6-2025 Overland Flow Assessment.pdfRelated documentApplication case desk ↗
About this file
- File size
- 13.3 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.