51987.3790.03 - Applicant's Response

of 8

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

23rd March 2022

Our Ref: 002396
Council’s Ref: 51987.3790.03

Noosa Shire Council
The Chief Executive Officer
9 Pelican Street
Tewantin QLD 4565
Via email: [email protected]


ATTENTION: Georgina Schramm


Response to Council’s Further Advice – Change to the Conditions specified within the Decision
Notice (Minor Change)

Unit 17/185-187 Gympie Terrace, Noosaville Qld 4566 (The Islander Noosa)
Lot 17 on GTP 2026


Dear Georgina,

In relation to the abovementioned property and development application (51987.3790.03), on behalf of
Catherine Ann Parry-Moule and Roderick Douglas McLennan, we hereby submit the following information as
requested in Council’s Further Advice dated 10th March 2022.

In accordance with section 13.2 of the Development Assessment Rules, we wish to advise that the applicant
is providing all of the information requested.

The following attachments are enclosed within this response:

         • Attachment 1 – Historic Drainage Plans, and
         • Attachment 2 – Photographs of Premises.


Information Required by Council

1. Provide an assessment against the Flood Hazard Overlay Code to assist in the assessment of the
development application.

        1.1. Identify the existing drainage patterns on the site, and demonstrate what implications the increase
        in floor area will have on overland flow paths.

        1.2. Identify internal stormwater infrastructure on the premises.

RG Strategic                                                         PO Box 1818       07 5474 3873
                                                                     Noosa Heads       [email protected]
                                                                     QLD 4567          rgstrategic.com.au
Full text of the other 7 pages

Page 2

Applicant’s Response

The proposed minor change to Unit 17 will have no negative implications on the existing drainage patterns or
network. The additional Site Cover and Gross Floor Area does not alter the retention of stormwater nor
increase the velocity of stormwater on site.

Refer to Attachment 1 Historic Drainage Plans and the below photographs of the existing drainage patterns
on site. The existing drainage patterns on the site occur either by capturing rainwater via roofed areas and
discharging into the stormwater network, or by the overland flow paths. The paved pedestrian footpaths
throughout The Islander Resort have been designed to direct the overland flow into the stormwater network.

As indicated in the Historic Drainage Plans (Attachment 1) and the below Photographs 1 and 2, a stormwater
pit is located directly adjacent to Unit 17. The pit is located at the lowest section of the paved pedestrian
footpath. The stormwater pit is approximately 300-500mm below the floor level of Unit 17 (and adjoining and
nearby units).

The proposed redesign of the unit (an increase in Site Cover by approximately 10m2) will result in a continuation
of the living areas, and as such is at the same floor level of the existing unit. The minor increase in Site Cover
(roofed area) will greater assist the drainage network of the resort as water will be captured and directly
discharged into the stormwater network rather than an overland flow path.

The internal stormwater infrastructure on the premises is identified in Attachment 1 Historic Drainage Plans.




Photograph 1: Stormwater Pit adjacent to Unit 17       Photograph 2: Inside Stormwater Pit and Connection to Network




                                                                      PO Box 1818          07 5474 3873
                                                                      Noosa Heads          [email protected]
                                                                      QLD 4567             rgstrategic.com.au

Page 3

Refer to the below assessment of the proposed renovation against the Flood Hazard Overlay Code.

Flood Hazard Overlay Code - Table 8.2.6.3


       Performance Outcomes                        Acceptable Outcomes                   Applicant’s Response

 PO1                                        AO1
                                                                                    Complies
 Development provides that for all          The finished flood level is not less
 flood events up to and including           than the minimum design levels          The proposed renovation will
 the DFE :                                  specified in Table 8.2.6.4              maintain the existing floor
 a) the safety of people on the                                                     levels of the unit. No change
     site is protected; and                                                         to the existing floor level of
 b) the risk of damage to                                                           the unit is occurring.
     property on the site is
                                                                                    As demonstrated by the
     avoided or minimised as far
                                                                                    photographs taken during the
     as practicable.
                                                                                    recent flood events of
                                                                                    February/March 2022
                                                                                    (Attachment 2), Unit 17 is sited
                                                                                    above the flood level.
 PO2                                        AO2
                                                                                    Not applicable
 All lots have sufficient area that is      The minimum area above flood
 above the DFE flood level or               level (flood free area) for each lot,   The proposed minor change is
 where modelling is not available,          is in accordance with Table 8.2.6.5.    in relation to a renovation of
 the highest recorded flood level,                                                  an existing unit.
 to safely and adequately
 accommodate the intended use.
 PO3                                        AO3
                                                                                    Not applicable
 For reconfiguring a lot or                 Development areas are not filled
 operational works, development             to reduce flood risk.                   No filling or earthworks are
 is undertaken in a manner that                                                     proposed. The proposed
 ensures:                                                                           minor change is in relation to a
 a) natural hydrological systems                                                    renovation of an existing unit.
      are protected from erosion,
      scour or flood damage on the
      premises or other premises;
 b) natural landforms and
      drainage lines are
      maintained to protect the
      hydraulic performance of
      waterways and flood plain;
      and
 c) development integrates with
      the natural landform rather
      than modifying the landform
      to suit the development as
      far as practicable.
 PO4                                        AO4.1
                                                                                    Not applicable
 For reconfiguring a lot,                   Development provides an
 development does not                       effective evacuation route that         The proposed minor change is
 compromise the safety of people            remains passable, with sufficient       in relation to a renovation of
 resulting from the flood risk              flood warning time, to enable           an existing unit.
 associated with events                     people to progressively evacuate
 exceeding the DFE.                         to safe areas above the PMF in
                                            the face of advancing flood or
                                            waters for events that exceed the
                                            DFE.

                                            OR



                                                                           PO Box 1818       07 5474 3873
                                                                           Noosa Heads       [email protected]
                                                                           QLD 4567          rgstrategic.com.au

Page 4

    Performance Outcomes                  Acceptable Outcomes                  Applicant’s Response

                                   AO4.2
                                   Development provides for an area
                                   of sufficient size and dimensions
                                   on site above the PMF that allows
                                   for safe congregation and refuge.

                                   AO4.3
                                   Where the existing roads servicing
                                   a development provide a specific
                                   flood immunity (as determined by
                                   the Qld Transport Road and
                                   Drainage Design Manual,
                                   Queensland Urban Drainage
                                   Manual and the Australian Rainfall
                                   and Runoff Guide), all lots have
                                   access to the flood free area
                                   identified in Table 8.2.6.5 that
                                   matches the road immunity.
PO5                                AO5
                                                                          Not applicable
For reconfiguring a lot or         In the Flood Hazard Overlay, or in
operational works, development     areas otherwise determined to be       The proposed minor change is
does not directly, indirectly or   subject to the DFE or DSTE,            in relation to a renovation of
cumulatively alter the flood       development ensures:                   an existing unit.
characteristics external to the    a) there is no loss of on-site flood
development site for all flooding       storage capacity;
and inundation events up to and b) all changes to level, depth,
including the DFE or DSTE based         duration and velocity of
on:                                     floodwaters are contained
a) current climate conditions;          within the site for all flood
    and                                 events up to and including the
b) incorporating an appropriate         DFE based on current climate
    allowance for the predicted         and predicted impacts of
    impacts of climate change.          climate change at 2100;
                                   c) there is no acceleration or
                                        retardation of flows, or any
                                        retardation in flood warning
                                        times, elsewhere on the
                                        floodplain and to any overland
                                        flow paths; and
                                   d) there is no increased
                                   stormwater ponding on sites
                                   upstream, downstream or in the
                                   general vicinity of the site.
PO6                                AO6.1
                                                                          Not applicable
Development ensures that           Buildings are designed to
building design and building form: integrate well with the street level   The proposed minor change is
a) accounts for potential flood    and the levels of adjoining            in relation to a renovation of
    risk;                          properties to facilitate pedestrian    an existing unit. The
b) is resilient to flood events;   flows and visual and physical          renovation results in a minor
    and                            connectivity between the footpath      increase in site cover and
c) maintains a functional and      and ground floors.                     marginal increase of gross
    attractive street address                                             floor area.
    appropriate to the intended    AO6.2
                                                                          The proposed redesign will
    use.                           Buildings incorporate appropriate
                                                                          have no impact on adjoining
                                   screening to ensure that any
                                   under-storey is not visible from the   commercial land uses.
                                   street, where such screening does
                                   not impede flood water flows.

                                                                PO Box 1818        07 5474 3873
                                                                Noosa Heads        [email protected]
                                                                QLD 4567           rgstrategic.com.au

Page 5

    Performance Outcomes                   Acceptable Outcomes                    Applicant’s Response


                                     AO6.3
                                     Residential buildings minimise risk
                                     from flooding by providing parking
                                     and other low intensive, non-
                                     habitable uses at ground level,
                                     rather than habitable uses.

                                     AO6.4
                                     Non-residential buildings and
                                     structures are oriented to the
                                     street by activating the street
                                     frontage with appropriate uses
                                     and urban design treatments such
                                     as recessed wall treatments,
                                     screening or landscaping, whilst
                                     allowing for flow through of flood
                                     waters on the ground floor.

                                     AO6.5
                                     Basements and underground car
                                     parking areas are designed to
                                     drain and function safely during a
                                     flood event and power failure.
PO7                                  AO7.1
                                                                             Not applicable
Development supports, and does       Development is located to support
not unduly burden, disaster          self-evacuation of people and           The proposed minor change is
management response or               ensure sufficient warning time for      in relation to a renovation of
recovery capacity or capabilities.   the nature of the use.                  an existing unit.

                                     AO7.2
                                     Development does not:
                                     a) increase the number of people
                                        calculated to be at risk from
                                        flooding;
                                     b) increase the number of people
                                        likely to need evacuation;
                                     c) shorten flood warning times for
                                        other uses in the floodplain; or
                                     d) impact on the ability of traffic
                                        to use evacuation routes, or
                                        unreasonably increase traffic
                                        volumes on evacuation routes.

                                     AO7.3
                                     Materials stored on site:
                                     a) are readily able to be moved
                                         in a flood event to a flood free
                                         area; or
                                     b) are contained in order to
                                         minimise movement in times of
                                         flood.
PO8                                  AO8
                                                                             Not applicable
Essential network infrastructure     Essential network infrastructure
maintains effective function         that is likely to fail to function or   The proposed minor change is
during and immediately after         may result in contamination when        in relation to a renovation of
flood and storm tide inundation      inundated by flood water (e.g.          an existing unit. There will be
events.                              water supply pipeline air valves        no impact on the existing

                                                                   PO Box 1818        07 5474 3873
                                                                   Noosa Heads        [email protected]
                                                                   QLD 4567           rgstrategic.com.au

Page 6

    Performance Outcomes                   Acceptable Outcomes                   Applicant’s Response

                                     and the like) is located above the     infrastructure as a result of
                                     DFE level (or where the DFE has not    the minor increase in site
                                     been modelled for the area, above      cover.
                                     the highest recorded flood level for
                                     the area).
PO9                                  AO9.1
                                                                            Not applicable
Essential community                  Essential community infrastructure
infrastructure is able to function   is sited and constructed to ensure     The proposed minor change is
effectively during and               that flood levels comply with flood    in relation to a renovation of
immediately after flood events.      immunity requirements specified in     an existing unit.
                                     Table 8.2.6.4.

                                   AO9.2
                                   Essential community infrastructure
                                   which is located below the
                                   specified flood immunity
                                   requirements:
                                   a) is designed and constructed
                                         to function effectively during
                                         and immediately after the
                                         recommended flood level
                                         event; and
                                   b) has direct access to low
                                         hazard evacuation routes or
                                         an emergency rescue area
                                         above the PMF, if it is for
                                         emergency services (including
                                         emergency shelters, police
                                         facilities, hospitals and
                                         associated facilities).
PO10                               AO10
                                                                            Not applicable
Excavation and filling for         Filling, other than accessways:
operational works only occur       a) does not extend more than             No earthworks are proposed.
where they:                              the equivalent of 3 metres
a) result in the protection,             around the main building,
   rehabilitation and repair of          measured from the outer walls
   ecologically important areas,         of the building;
   watercourses, drainage lines b) is limited to a maximum of
   and wetlands;                         500m2; and
b) do not adversely impact on      c) does not impact on the local
   the overall hydrology,                drainage of adjoining
   hydraulics and flood capacity         properties.
   of a waterway;
c) do not directly, indirectly or
   cumulatively cause adverse
   impacts external to the site;
d) do not cause increased
   flooding, which adversely
   affects the safety or use of
   any land upstream or
   downstream;
e) do not cause ponding of
   water on the site or nearby
   land;
f) do not result in a reduction in
   flood storage capacity;
g) do not adversely affect the
   flow of water in any overland

                                                                  PO Box 1818        07 5474 3873
                                                                  Noosa Heads        [email protected]
                                                                  QLD 4567           rgstrategic.com.au

Page 7

      Performance Outcomes                   Acceptable Outcomes                   Applicant’s Response

     flow path; and
 h) do not adversely affect the
     privacy or visual amenity of
     surrounding property.
 PO11                                 AO11.1
                                                                              Not applicable
 Development ensures that public      Materials manufactured or stored
 safety and the environment are       on site are not hazardous or            The proposed minor change is
 not adversely affected by            noxious, or do not comprise             in relation to a renovation of
 avoiding the release of              materials that may cause a              an existing unit. No hazardous
 hazardous materials into flood       detrimental effect on the               materials are kept within the
 waters and the environment.          environment if discharged in a          Unit.
                                      flood event.

                                      OR

                                      AO11.2
                                      If a DFE is adopted, structures
                                      used for the manufacture or
                                      storage of hazardous material are
                                      located above the DFE level.



This ends my client’s response to matters raised by Council within their Further Advice.

We ask that Council proceeds with the assessment of this application under section 13.3 of the Development
Assessment Rules, effectively ending our applicant’s response period.

Should you require any additional information or have any queries please to not hesitate to contact us.




Kind Regards,




Russell Green APIA MQELA
Managing Director
RG Strategic




                                                                    PO Box 1818        07 5474 3873
                                                                    Noosa Heads        [email protected]
                                                                    QLD 4567           rgstrategic.com.au

Page 8

STRATEGIC SOLUTIONS,
CREATIVE THINKING

Used in these records

About this file

File size
767 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

51987.3790.03 - Applicant's Response.pdf · 767 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.