6.2 Proposed Drainage
The proposed site drainage is detailed in drawings SCG 31131- SW1.1 thru SW1.5 (Appendix D) and
is discussed below.
6.2.1 Catchments
Roof Catchment
1. Runoff from catchment A, consisting of the roof area of buildings containing units 17-22
and unit 1 will flow via downpipes to an internal drainage network where it will be
directed to an underground rainwater tank for re-use. The tank will then overflow to the
Eumundi Noosa Road kerb and channel (lawful point of discharge).
2. Runoff from catchment B, consisting of the remaining roof areas of the site, will flow via
downpipes to an internal drainage network where it will be directed to the on-site bio
retention/detention basin prior to discharging to the existing inter-allotment drainage
network located in Lot 99–101 on SP106085 (lawful point of discharge).
Ground Catchment
Surface runoff from the hardstand and landscaping areas will be directed to a series of entry pits and an
underground pipe network to the on-site bio retention/detention basin. The treated/detained runoff is
then discharged to the existing inter-allotment drainage network located in Lot 99–101 on SP106085
(lawful point of discharge).
6.2.2 Peak Flow Mitigation
As shown in Table 6.3 Stormwater peak discharge will increase as a result of the proposed development.
Therefore, it is proposed to utilise an OSD system to mitigate the peak stormwater discharge rates from
SCG Consulting Engineers Page 18 SCG Ref: 31131(SWMP)
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (RFI - SWMP.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.