• If not, then consider issue (3). A land owner or regulator may require that the
developer obtain an authority to discharge as described in (3) in order for the
stormwater to ultimately flow to a location described in (2).
3. An authority to discharge over affected properties will be necessary. In descending order
of certainty, an authority may be in the form of:
• Dedication of a drainage reserve or park
• A registered easement for stormwater discharge/works
• Written discharge approval.
Note: Some authorities may not accept a written approval from a current land owner
because a subsequent purchaser will not be bound by the previous owner’s letter or
contract (refer to Section 3.10).
If the proposed development maintains pre-development flow conditions, the lawful point of discharge
for the subject site is the existing stormwater drainage infrastructure within Lot 99, 100 and 101 on
SP106085, east of the site and the Eumundi Noosa Road kerb and channel. The proposed lawful point
of discharge is considered to be compliant with the criteria outlined in QUDM 2017 see below: -
1. The proposed development stormwater discharge will not alter the existing site’s
stormwater discharge characteristics.
2. The location of the proposed discharge point is under the lawful control of the local
government.
3. Authority to discharge over affected properties will not be required as the proposed
development will discharge as per existing drainage conditions.
SCG Consulting Engineers Page 7 SCG Ref: 31131(SWMP)
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (RFI - SWMP.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.