MCU14/0056 - Attachment G - Engineering Report & Stormwater Management Plan

of 103

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
                              Corner Myall Street & Ferrells Road Cooroy, QLD 4563
                                                         Water Supply & Sewerage Reticulation Code



Water Supply & Sewerage Reticulation Code
Specific Outcomes                                    Acceptable Solutions/Probable Solutions                           Compliance
                                                                                                                       AS3500.
                                                                                                                       Water reticulation will be designed
                                                                                                                       and constructed in accordance with
                                                                                                                       SEQ D & C Code and PSP6 Engineering
                                                                                                                       Design Standards – Water and
                                                                                                                       Sewerage.
O4 Water supply infrastructure is provided with      No solution provided.                                             The proposed development works will
all supporting technical documentation                                                                                 comply with this requirement.
O5 Where buildings or other structures are in        S5.1 The footing of any building or structure is located clear    Not applicable, as no buildings are
proximity to State or Council’s water supply         of the zone of influence but no closer than 1.5m (measured        proposed adjacent to existing
infrastructure, provision is made to protect the     horizontally) from infrastructure including sewers, water         infrastructure.
infrastructure from physical damage and to allow     mains and stormwater structures; AND
ongoing maintenance by Council.
                                                     S5.2 A registered easement in favour of Council is created        Not applicable, as no buildings are
                                                     over all underground infrastructure located in private            proposed adjacent to existing
                                                     property; AND                                                     infrastructure.
                                                     S5.3 The width of the easement is the greater of 3m or the        Not applicable, as no buildings are
                                                     width of the zone of influence; AND                               proposed adjacent to existing
                                                                                                                       infrastructure.
                                                     S5.4 The easement is centred over the centreline of the           Not applicable, as no buildings are
                                                     infrastructure.                                                   proposed adjacent to existing
                                                                                                                       infrastructure.
O6 Alignment of water supply infrastructure          S6.1 Infrastructure is designed and constructed on the            The proposed development works will
allows for easy access for the ongoing               preferred alignments in accordance with PSP6 Engineering          comply with this requirement.
maintenance by Council.                              Design Standards – Water and Sewerage.
O7 Any alterations or repairs to infrastructure as   S7.1 Any alterations or repair to infrastructure as a result of   The proposed development works will
a result of the development are made at no cost      the development are completed at the developer’s                  comply with this requirement.
Log in to download the original file

MCU14_0056 - Attachment G - Engineering Report & Stormwater Management Plan.pdf · 9.8 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.