RI Mead
C/- PopovBass
2 Glen Street
MILSONS POINT  NSW  2061

[email protected]

Dear Sir/Madam

Change to an Existing Approval
Sustainable Planning Act 2009

I refer to your request to make a permissible change to an existing approval.  On 20 July 2017, Council decided your requested changes.

Details of the decision are as follows:
application details
Application No:	MCU15/0023.02
Street Address:	44 Seaview Tce SUNSHINE BEACH  QLD  4567
Real Property Description:	Lot 58 RP 81810
Planning Scheme:	The Noosa Plan (28 October 2016)
Decision details
Council on 5 June 2015 decided to issue the following type of approval:
Development Permit for Material Change of Use of Premises - Detached House
In relation to the request to make a change to the existing approval, Council on 20 July 2017 decided to:
Amend the list of approved plans.
Include additional Condition 17.
3.	RELEVANT PERIOD OF APPROVAL

The relevant period for this development approval is 4 years starting the day that this development approval takes effect.

4.	ASSESSMENT MANAGER CONDITIONS

PLANNING
When Conditions must be Complied With
Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to the use commencing, and then compliance maintained at all times while the use continues.
Approved Plans
Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions.
Plan No.	Rev.	Plan/Document Name	Date
0446-DA102	B	Site Plans, prepared by PopovBAss Architects	25.05.2015
0446-DA103	B	Ground Floor Plan, prepared by PopovBAss Architects	25.05.2015
0446-DA104	B	Level 01 Plan, prepared by PopovBAss Architects	25.05.2015
0446-DA105	B	Roof Plan, prepared by PopovBAss Architects	25.05.2015
0446-DA106	B	North + South Elevations, prepared by PopovBAss Architects	25.05.2015
0446-DA107	B	East + West Elevations, prepared by PopovBAss Architects	25.05.2015
0446-DA108	B	Longitudinal Sections, prepared by PopovBAss Architects	25.05.2015
0446-DA109	B	Cross Sections, prepared by PopovBAss Architects	25.05.2015
0446-DA112	B	External Finishes Schedule, prepared by PopovBAss Architects	25.05.2015
LP01	C	Landscape Concept Plan, Spirit Level Designs as annotated by Council	18/05/2015
6532 C200	3	Stormwater Management Plan, prepared by BE Collective	11/05/2015

Building Height
The maximum height of the development must not exceed 8 metres above the natural ground surface and the finished ground level and 2 storeys.
Certification must be submitted to Council from a Licensed Surveyor which certifies that the building does not exceed the maximum height requirement of this Decision Notice.
Performance Bond
Security in the form of a cash bond or trading bank guarantee to the sum of $10,000 must be submitted to Council, to secure performance of all conditions of this approval, prior to the issue of a Development Permit for Building Works.  The cash bond or trading bank guarantee will be returned on performance of the conditions of approval less any costs incurred by Council in respect of enforcing performance of this permit.  Council reserves the right to call upon the bond or guaranteed sum to effect compliance with conditions.
Landscaping
A minimum of 20% of the site must be retained as soft landscaping.
All landscaping works must be undertaken in accordance with the Landscape Concept Package, prepared by Spirit Level Designs and dated 18/05/2015 and with Council’s Planning Scheme Policy PSP3 Landscaping Plants and Guidelines. In this regard:
the landscaped area seaward of the swimming pool must be densely planted and must include the following species:
4 x Allocasuarina equistifolia or Casuarina gluca
1 x Banksia integrifolia
the landscaped area must not include Ice plant or dwarf Jade plant as annotated by Council on the approved landscape plan
the Grass tree and narrow leafed Gardenia must not be used in the rear re-vegetation area but may be used in other areas throughout the site as annotated by Council on the approved landscape plan.
Existing trees on the site and within road reserves must be retained, except where required to be removed to accommodate the approved dwelling.  In this regard,
the removal of vegetation must be in accordance with the Landscape Concept Package, prepared by Spirit Level Designs and dated 18/05/2015.
the Melaluca quinquenervia located in the road reserve must be retained
the Norfolk pine must be retained as indicated on the approved plans.
Trees to be retained must be protected from clearing or construction activities by:
clearly marking vegetation to be retained with flagging tape
installing protective fencing around the drip line of the vegetation
restricting stockpiling, storage and vehicle parking to those areas which are already cleared
using low impact construction techniques around vegetation.
Vehicle crossover
The redundant vehicle crossover must be removed.
Earthworks
Earthworks required on site must be carried out in accordance with Council’s Planning Scheme Policy PSP5 – Engineering Design Standards (The Noosa Plan), so as not to cause the additional ponding of water on any adjoining lands or the blockage of, or interference with, any natural overland flows.
Earthworks carried out on site must not affect the structural integrity of any of the existing fences and/or buildings and/or structures and/or land that border the development site.  Fences that are affected must be replaced prior to the Building Certifier issuing the Certificate of Classification.
Geotechnical
All works must be carried out in accordance with a Geotechnical Report for the site prepared by a qualified person*. The submitted Geotechnical Investigation by Soil Survey Engineering Pty Limited ref: 1-14608,2013-01-15,BR VER0, dated January 2013 must be amended to address the specific issues of the proposed design. The updated report must be submitted prior to the issue of a Building Approval.
Certification must be submitted to Council from a qualified person* which certifies that the site is not at risk from landslide emanating from the site or from other land. *(Refer to Advisory Note)
Coastal Protection
Gates must not be installed along the rear seaward property boundary to gain direct access to the beachfront.
Building Design
External colours and finishes of the building must comprise of muted/environmental tones that blend with the natural environment.
Stormwater management must be in accordance with the Stormwater Management Plan by BE Collective 6532 C200 Revision 3 dated 11 May 2015.
5.	REFERRAL AGENCIES

Not Applicable.

6.	ADVISORY NOTES

The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions:
PLANNING
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries out an activity must take all reasonable and practicable measures to ensure the activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions may also be issued by the Land and Resources Tribunal, and the Minister administering the ACH Act can also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Unit on 07 3247 6212 to discuss any obligations under the ACH Act.
Equitable Access and Facilities
The plans for the proposed building work have NOT been assessed for compliance with the requirements of the National Construction Code - Building Code of Australia (Volume 1) as they relate to people with disabilities.  Your attention is also directed to the fact that in addition to the requirements of the National Construction Code as they relate to people with disabilities, one or more of the following may impact on the proposed building work:
the Disability Discrimination Act 1992 (Commonwealth);
the Anti-Discrimination Act 1991 (Queensland); and
the Disability (Access to Premises – Buildings) Standards.
Development Compliance Inspection
Prior to the commencement of the use, please contact Council's Planning Assessment department to arrange a Development Compliance Inspection.
Qualified Person
For the purpose of preparing a Geotechnical Report, and for certifying geotechnical stability for the development, a qualified person is considered to be a person who:
is a Registered Professional Engineer of Queensland (RPEQ); and
has a degree in civil engineering or engineering geology; and
has a minimum of 5 years experience in the field of geotechnical engineering or engineering geology.
Property Driveway and Vehicle Crossover
The planning scheme declares Operational Work for the construction of a driveway and vehicle crossover to the property to be self-assessable against the Detached House Driveways Code.  If the proposed driveway and vehicle crossover does not comply with each Acceptable Solution contained in the Code, a Development Permit for the work is required to be obtained from Council.

7.	PROPERTY NOTES

Not Applicable.

8.	PRELIMINARY APPROVAL OVERRIDING PLANNING SCHEME

Not Applicable.

10.	SELF ASSESSABLE CODES

The following codes for self-assessable development related to the development approval issued under this Decision Notice must be complied with.
Detached House Driveways Code

13.	RIGHTS OF APPEAL

You are entitled to appeal against this decision.  A copy of the relevant appeal provisions from the Sustainable Planning Act 2009 is attached.

During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval.  If Council agrees or agrees in part with the representations, a “negotiated decision notice” will be issued.  Only one “negotiated decision notice” may be given.  Taking this step will defer your appeal period, which will commence again from the start the day after you receive a “negotiated decision notice”.

14.	OTHER DETAILS

If you wish to obtain more information about Council’s decision, electronic copies are available on line at www.noosa.qld.gov.au, or at Council Offices.

DECISION NOTICE HISTORY Original Decision Notice 5 June 2015 Changes to an Existing Approval 20 July 2017, with an amendment to Conditions1 and include additional condition17

Yours faithfully

Patrick Murphy
Coordinator Planning

Encl. 	Approved Plans/Documents
Appeal Rights

cc	Unitywater

	Appeal Rights SUSTAINABLE PLANNING ACT 2009 & SUSTAINABLE PLANNING REGULATION 2009

The following is an extract from the Sustainable Planning Act 2009 (Chapter 7)

466 	Appeals about decisions relating to permissible changes
(1) 	For a development approval given for a development application, the following persons may appeal to the court against a decision on a request to make a permissible change to the approval—
(a) 	if the responsible entity for making the change is the assessment manager for the application—
(i) 	the person who made the request; or
(ii) 	an entity that gave a notice under section 373 or a pre-request response notice about the request;
(b) 	if the responsible entity for making the change is a concurrence agency for the application—the person who made the request.
(2) 	The appeal must be started within 20 business days after the day the person is given notice of the decision on the request under section 376.
(3) 	Also, a person who has made a request under section 369 may appeal to the court against a deemed refusal of the request.
(4)	An appeal under subsection (3) may be started at any time after the last day the decision on the matter should have been made.

[word/footer1.xml]
Page 4 of 7

[word/footer2.xml]
PO Box 141		P. (07) 5329 6500	[email protected]	
	TEWANTIN  QLD  4565	F. (07) 5329 6501	www.noosa.qld.gov.au
				Page 1 of 7

[word/header3.xml]
MCU15/0023.02

[Attachment: image4.png (image text)]
 
 
 

 
 
 

a
mm

  

NOOSA
COUNCIL

Used in these records

About this file

File size
123 KB (small file)
File type
DOCX

No other editions are linked here.

Original file

Log in to download the original file

Changed Approval MCU15_0023.02.docx · 123 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.