PEREGIAN BEACH ACTIVE STREET - STAGE 1 PROGRESS UPDATE AND NEXT STEPS (Deferred from the Ordinary Meeting dated 19 March 2026 - Item 12.2) · Report

of 16

Page text shows just the words. Original shows the document exactly as it was published.

GENERAL COMMITTEE MEETING                                                               9 JUNE 2026


7.1         PEREGIAN BEACH ACTIVE STREET - STAGE 1 PROGRESS UPDATE
            AND NEXT STEPS (Deferred from the Ordinary Meeting dated 19 March
            2026 - Item 12.2)


Author            Project Officer, Lindsay Egeskov
                  Major Projects & Transport | Infrastructure Services Department
Index             ECM / TRANSPORT / PATHWAYS AND BICYCLE TRANSPORT
Attachments       1.   Confidential Attachment 1_Engagement Activities Feedback -
                       Confidential IAW Section 254D(3) of the LG Regulation 2012
                  2.   Confidential Attachment 2 - Customer Request Summary -
                       Confidential IAW Section 254D(3) of the LG Regulation 2012
                  3.   Confidential Attachment 3 - Petition lodged 30 Sep 25 - Confidential
                       IAW Section 254D(3) of the LG Regulation 2012
                  4.   Confidential Attachment 4 - Community Led Proposed Adjustments -
                       Confidential IAW Section 254D(3) of the LG Regulation 2012
                  5.   Confidential Attachment 5 - Facebook Poll Results - IAW
                       Section 254D(3) of the LG Regulation 2012
                  6.   Confidential Attachment 6 - Correspondance of Support - Confidential
                       IAW Section 254D(3) of the LG Regulation 2012
                  7.   Confidential Attachment 7 - Resident One on One Meeting Minutes -
                       Confidential IAW Section 254D(3) of the LG Regulation 2012
                  8.   Attachment 8 - Project Program - Peregian Active Street


EXECUTIVE SUMMARY
This report provides a project status update and recommendation for the Peregian Beach Active
Street – Stage 1 project, including background to the project, an outline of findings from recent
community engagement and current project parameters. The project is funded through the South
East Queensland Liveability Fund and the Active Transport Fund.

The report recommends continuing to proceed with the project with a series of design modifications
in response to recent community feedback.

The report includes extensive attachments in the form of community feedback on the proposal, this
feedback contained in Attachments 1 to 7 has been provided as confidential attachments due to the
inclusion of personal information that has at best efforts been redacted however may still contain
information that could identify a person or address. Therefore, if required, in accordance with
Section 254J (3) of the Local Government Regulation 2012, the meeting will be permitted to be
closed to the public for discussion on this business relating to the following:
(f) matters that may directly affect the health and safety of an individual or a group of individuals.

As a result of the extensive consultation and ensuing feedback a number of changes have been
proposed to the initial designs. The following notes the suggested refinements to the design and
ongoing investigations:
   1. Improved Local Area Traffic Management (LATM) measures on surrounding streets to
      improve vehicle speed and safety;
Log in to download the original file

Report.pdf · 290 KB (small file)

Full text of the other 15 pages

Page 2

GENERAL COMMITTEE MEETING                                                                   9 JUNE 2026


    2. Investigation into increasing formalised parking yield across the Peregian Beach South area
       including within Victory Park and along Lorikeet Drive. Ongoing investigations include, but
       are not limited to: one way circulation through Victory Park; angled parking within Victory
       Park, parallel parking on Lorikeet Drive adjacent high density residential zone and formalised
       parking at the eastern end of Pitta St;
    3. Investigation into a softer colour palette and/or a reduction in perceived over development to
       lesser impact, village scale raised intersections, priority crossings, chicanes, speed bumps
       and overrun areas where possible within statutory traffic requirements;
    4. Widening of the existing boardwalk through Lorikeet Park along the current alignment as well
       as inclusion of speed management device to control bike speeds on approach to shared path
       and boardwalk through Lorikeet Park;
    5. Improvements to Victory Park to least impactful carparking layout but including no-parking
       zone in front of the two beach entrances, provision of limited long vehicle parking bays
       and end-of-trip facilities such as improved water points and bike racks.
    6. Inclusion of additional street tree planting;
    7. Investigate additional signage for user behaviour at key locations and nodes;
    8. Investigation into Lorikeet Dr and Pitta St intersection design to accommodate vehicle turn
       around movements.
    9. Investigation into land tenure south of Lorikeet Park bridge to facilitate the continued use and
       upgrade of the pathway on the existing alignment.
The report also seeks in-principle support for continuing to invest in Stage 2, subject to future budget
allocation, to achieve connectivity to the Peregian Beach Village, and an investment in a broader
education and awareness program on the benefits of active transport to support delivery of the shire
wide Coastal Pathway Corridor, a key component of Council's Cycling and Walking Strategy.

RECOMMENDATION
That Council:
A. Note the report by the Project Officer to the General Committee meeting dated 16 March 2026
   regarding the Peregian Beach Active St - Stage 1 project status including key findings from the
   community consultation activities and proposed design amendments;
B. Delegate authority to the CEO to finalise, negotiate and award the construction contract for the
   Peregian Beach Active Street – Stage 1 Project, including approval of all contract variations within
   the approved project budget, for the purpose of expediting delivery enabling project completion
   by the required State and Federal grant funding timeframes;
C. Note that whilst the project is grant funded, financial reconciliation is not finalised, with additional
   costs arising from additional community engagement and project scope changes;
D. Support the development of an “Active Street” and “Coastal Pathway” awareness and education
   campaign across the shire to raise awareness of the safety and active transport benefits
   associated with Active Streets and the ultimate delivery of the Noosa Cycling and Walking
   Strategy and Noosa Transport Strategy;
E. Support the CEO to submit available grant funding applications for Stage 2 of the Active
   Street/Coastal Pathway extension to commence design and construction as soon as practicably
   possible.


REPORT

Page 3

GENERAL COMMITTEE MEETING                                                               9 JUNE 2026


1. Background and Strategic Foundations

Highest Priority Cycle Route Corridor Study (HPCR)

In 2021, Noosa Council completed the Coastal Pathway Corridor Study or Highest Priority Cycle
Route Corridor Study (HPCR) to plan safer, more connected walking and cycling routes between
Peregian Beach and Tewantin, including a link to the Sunshine Coast Coastal Pathway. The study
reviewed existing paths, identified safety gaps, and assessed possible routes. To ensure community
alignment, Council formed a Project Reference Group (PRG) with community members, local
associations, and walking and cycling groups. The PRG members were nominated and endorsed by
Noosa Council.

Three segments were identified on Corridor 1, Tewantin to Noosa Heads, and 6 segments on
Corridor 2, Noosa Head to Peregian for options analysis and further design work.

Engagement activities were undertaken with the PRG at key milestones and decision points
throughout the project. Specifically, this included engagement at the route selection, design
treatment selection and concept design review stages

For Peregian Beach South (Segment 6 of Corridor 2), four route options, as indicated in figure 1
below, were assessed against the following criteria:
•   Safety
•   Comfort
•   Directness and Coherence
•   Connectivity
•   Strategic alignment; and
•   Feasibility.




                   Figure 1 – Route Options Analysis

Route B (Lorikeet Drive) scored the highest or equal to the highest across all criteria and ranked the

Page 4

GENERAL COMMITTEE MEETING                                                               9 JUNE 2026


highest in both total unweighted and weighted scoring. Key differentiators in scoring between Route
A (David Low Way) and Route B (Lorikeet, Shearwater, Piper, Plover) were Connectivity, Strategic
Alignment and Feasibility. Route A considered pathways on alternate sides of David Low Way,
whereas Route C and partially Route D considered pathway locations in the coastal foreshore
reserve. Route B was considered to connect with more attractors, align closer to the coast, be
easiest to implement and the lowest cost.

Several design treatments were also explored, including a Cycle St (Active Street), Advisory Bicycle
Lanes and a Shared Path. The treatment types were scored against the following criteria:
   •   Safety
   •   Connectivity
   •   Feasibility; and
   •   Impact.
The Active Street concept - supported by TMR - performed best for safety and feasibility.

The Peregian Beach south project was given a high priority (on a scale of low to very high) and
tentatively scheduled for 2023/24 and 2024/25 financial years in a draft implementation plan within
the final report. The priority ranking was based on:
   •   High existing and potential walking and cycling demand.
   •   Its ability to close gaps in the local network and connect key destinations.
   •   Logical sequencing with other current and planned projects to build a safer, continuous
       corridor.
   •   Proximity to key attractors such as local schools, beaches, shops, and community facilities.
Further community consultation was proposed to be undertaken on a project-by-project basis, noting
that some of the projects identified within the Corridor Study may never proceed. The results of the
corridor study were incorporated into the Noosa Cycling and Walking Strategy, which was being
undertaken concurrently, and consequently endorsed by Council.

These key background documents to the Noosa Cycling and Walking Strategy, being the 'Noosa
High Priority Cycle Route Corridor Study and Concept Design’ (Corridor 2) were made public on
Council's website in early 2026 due to an expression of interest from the South Peregian Beach
community during the Peregian Beach Active Street Stage 1 Consultation phase.

The Noosa Cycling and Walking Strategy and Implementation Plan (NCWSIP)

Council adopted the Noosa Cycling and Walking Strategy and Implementation Plan 2020 – 2040 on
15 July 2021. The Strategy and Plan re-established Council’s vision for bike riding and walking
across Noosa Shire for the next 20 years with the vision to get ‘more people riding a bike and walking
for health, transport, tourism and the environment’. Council’s goal is to make riding a bike and
walking so convenient and safe that it is the preferred mode of transport for the Shire's residents and
visitors. The Plan has been guiding Council’s planning, development and promotion of bike riding
and walking networks.

Engagement activities were undertaken during the development of a draft plan with the same Project
Reference Group as nominated and endorsed by Council for the HPCR project.

During the ”Your Say” consultation period for the NCWSIP (19 March to 16 April 2021), 260
submissions were received from the community on the draft Strategy. The information gathered from
this process provided local insights and helped to identify additional missing links and route
refinements, which have been adopted in the Plan. Feedback also defined barriers to bike riding and
walking, reiterating those already identified in the Strategy.

Page 5

GENERAL COMMITTEE MEETING                                                               9 JUNE 2026



The proposed use of existing streets throughout the Shire for improved safe shared vehicle, cyclist
and pedestrian movements, such as an Active Street, is a consistent approach in the Noosa Cycling
and Walking Strategy due to unavailability of other routes due to environmental constraints and
construction costs.

The Peregian Beach Active St project (Project ID 361) was scored in the 201-300 priority band
(moderate) within the Walking and Cycling Strategy. It was initially not scheduled in the 10- year
implementation plan, however opportunistic grant funding to align with regional liveability and active
transport provided impetus for grant submission.

Further analysis of the project scoring indicates that if the project is combined with Project IDs 359
and 360 (continuation through to the village) that the project would score a ranking of 28.

2. Customer Requests

South Peregian residents have long raised concerns about speeding, pedestrian safety and difficult
driveway and waste service access compounded by unmarked parking bays and lane congestion
arising from parking on both sides of the narrow roadway. A key design consideration for the
proposed Active Street is to address these issues through a dedicated pedestrian pathway, improved
kerb and channel, reduced-speed signage, formalised parking, landscaping and road resurfacing.
Together, these upgrades will deliver a safer, greener and more attractive active transport
experience for users.

Grant Funding Opportunity

The project's high priority in the State funded corridor study, along with the community concerns
raised regarding speeding and pedestrian safety along and around Lorikeet Drive, made it an
excellent candidate for external funding. The project is 100% Grant funded through the South East
Queensland Liveability Fund and the Active Transport Fund.

The SEQ Liveability fund is Supporting Local Government projects that create liveable, creative,
sustainable and healthy communities. Projects funded will be of a regional or sub-regional scale
that leave a legacy in the community. The funding through the SEQ Liveability grant covers design
and construction works.

The Active Transport Fund (ATF), provides funding for the design and construction of new or
existing bicycle and walking pathways to encourage the use of active transport.
The focus areas for the program are:
   •   road safety
   •   reducing transport emissions
   •   active and liveable communities
The ATF grant funding for this project is specific to construction only.


3. Program

The project program is governed by Council's Annual Capital Works Programs and two separate
external funding agreements as outlined below.

SEQ Liveability
The last possible dates for milestones as listed in the executed SEQ Liveability funding agreement,

Page 6

GENERAL COMMITTEE MEETING                                                               9 JUNE 2026


are:

Milestone                         Last Possible Date (as per        Status
                                  Program Guidelines)
Completion of                     30 Jun 2027                       At risk
Construction
Final Reporting                   Dec 2027                          Achievable

Active Transport Fund
The last possible dates for milestones as listed in the executed ATF funding agreement, is:
Milestone                         Last Possible Date (as per        Status
                                  Program Guidelines)
Commencement of Construction 25 Mar 2026                            At risk
Completion of                     25 Mar 2028                       Achievable
Construction
Acceptance of                     25 Jun 2028                       Achievable
Post-Completion Report

Current Project Program
The current program, not accounting for any further delays as a result of this report, narrowly meets
the critical project construction end date of 30 June 2027. With no remaining float/program
contingency, this is a significant risk for the project.

Table 1 below indicates current forecast milestone dates as per the project program.

Milestones                              Deadline
Council S&O Decision                    10 March 2026
IFC Design                              30 March 2026
Award Tender                            27 May 2026
Practical Completion                    22 April 2027
Handover – final report & funding claim20 May 2027
Table 1: Program Milestones

Program risk mitigation - extension of time
Anecdotal advice received from ATF and SEQ Liveability Funding authorities have indicated that
both would be amenable to an extension of time request provided clear rationale is included in the
submission. The project team is working through extension of time requests with the grant funding
bodies.

The full program, including additional project consultation activities contributing to the extension of
time required is provided at attachment 8.

4. Community Engagement Findings

From March 2025 to February 2026, the Peregian Beach Active Street Project team undertook
targeted community engagement throughout the concept and detailed design stages, focusing on
residents of South Peregian as well as key community and stakeholder groups. Wider community

Page 7

GENERAL COMMITTEE MEETING                                                                 9 JUNE 2026


consultation on previous planning studies is provided in the ‘Background and Strategic Foundations’
section of the report. Project specific engagement activities are summarised below:

Activity Type Description
Councillor
               Multiple workshops and briefings (14 March, 7 April, 18 August ‘25)
Briefings
               Dedicated page created 8 April ‘25 with project updates, FAQs,
Project
               Project News, and a document repository including case studies,
Webpage
               educational videos and traffic and corridor studies.
Direct         Letterbox drops, direct mail, and digital notifications to residents and
Notification   stakeholders
Public    town
               Peregian Beach Community Road Safety Forum (13 May 2025)
hall meetings
               Boreen Point Ordinary Meeting (20 Nov 2025)

Public Pop-    Concept design stage (17 & 30 April ’25)
Ups            Developed design stage (21 & 29 Jan ’26)
Walkshop       Site-based review of detailed design (18 Feb ’26)
               One-on-one meetings with representative groups including ZEN,
Briefings
               BUG, PBCA and several impacted residents (appendix G)
           Between 10 June ‘25 and 20 February ‘26, Council recorded,
CRM
           monitored and responded to 37 CRM enquiries relating directly to the
Management
           project.

Key Findings from Community Engagement
Feedback on the Peregian Beach Active Street Project was mixed. While many residents and
stakeholders supported the project’s core objectives - slower traffic, safer pedestrian movements,
and improved walking and cycling connections - concerns were also raised. This was evident at pop-
up sessions where the majority of questions and points raised by residents in group discussion were
harshly negative towards the project whilst the underlying objectives of the project were still
supported.

Submissions from active transport groups (Sunshine Coast Bicycle User Group (SCBUG) and Zero
Emissions Noosa (ZEN) highlighted alignment with Council’s strategic transport framework and the
broader Coastal Pathway vision.

The report includes extensive attachments in the form of community feedback on the proposal, this
feedback has been provided as confidential attachments due to the inclusion of personal information.
Whilst they have been redacted to protect personal information, the documents have continued to
be marked as confidential as an extra precaution to ensure privacy is maintained.

Engagement activities at the developed design stages - including pop-up sessions at Victory Park
and the Walkshop - revealed several consistent themes:

Parking Impacts
   •   Loss and redistribution of on-street parking, particularly on Lorikeet Drive
   •   Flow-on effects for nearby residents, including higher-density areas
   •   Concerns from dog owners and volunteer marine wildlife responders regarding access and
       proximity parking
   •   Requests for resident permit parking or other measures to maintain accessibility

Page 8

GENERAL COMMITTEE MEETING                                                                9 JUNE 2026


Traffic Access, Property Access & Displacement
   •   Concerns about vehicles diverting to neighbouring streets, including Oriole Avenue
   •   Desire for mitigation measures to reduce rat-running and maintain local access
   •   Difficulty accessing properties with boats and trailers (including 7m trailers)
   •   Concerns about reversing movements near traffic calming devices and U-turn maneuvers
   •   Requests to widen driveways or adjust kerb clearances where required
Safety, Speed & E-Bikes
   •   Broad support for slower traffic and a 30 km/h speed environment, particularly where paired
       with traffic calming
   •   Concerns about interactions between fast-moving e-bikes, pedestrians and vehicles
   •   Vehicles driving in bike lanes and through roundabouts
   •   Preference for clearly marked pedestrian crossings (e.g. zebra crossings) or higher-contrast
       shared zones
   •   Requests for education and enforcement to support compliance
Vegetation, Drainage & Neighbourhood Character
   •   Strong preference to retain mature trees, including pandanus
   •   Desire to minimise visual and environmental impacts
   •   Concerns about stormwater runoff and drainage near driveways
   •   Noise concerns associated with overrun areas (described as rumble strips) and raised
       treatments and increased cyclist use
Design Alternatives & Route Considerations
   •   Some residents suggested relocating cycling infrastructure to David Low Way or adjusting
       pathway alignment (including the western side).
   •   Requests for wider pathways (suitable for two cyclists side-by-side)
   •   Desire to extend pathway connections fully to the village
   •   CPTED issues associated with the boardwalk and path diversion at Lorikeet Park
Other Key Feedback
   •   Support for stormwater upgrades and road repairs
   •   Requests for consistent pathway connections rather than partial sections
   •   Mixed views on speed reductions, with stronger support where clearly linked to improved
       safety outcomes
   •   A small number of submissions expressing full objection to the project in addition to the
       petitions listed below
Pop Up Display Boards (Attachment 1)
The collated post it notes from the pop-up display boards and the typed summary notes is included
as Attachment 1 to the Report.

Customer Requests (Attachment 2)
During the engagement period, Council received 37 formal customer enquiries relating to the project.
These enquiries primarily concerned parking impacts, traffic displacement, proposed speed limit
changes, and requests to reconsider corridor alignment and are included at Attachment 2 to the

Page 9

GENERAL COMMITTEE MEETING                                                               9 JUNE 2026


Report.

Petition (Attachment 3)
A petition – 'Residents Against Active Street' was formally tabled with Council which raised concerns
about parking loss, traffic congestion, and safety, and requested that the project be halted entirely,
requests for additional consultation and route options review. The petition is included at Attachment
3 to the report.

The petition was a catalyst for additional community consultation activities in recent weeks including
additional pop-up events, one on one meetings, preparation and distribution of additional project
materials and this report.

Community-led Proposed Adjustments (Attachment 4)
Received by the project team recently (19/02/2026), the submission includes a proposal for one-way
traffic (Oriole southbound, Lorikeet northbound), retention of most on-street parking, adjustments to
cyclist access, and potential residential parking permits. The submission is included at Attachment
4.

The proposal for one way traffic would require traffic modelling and design of traffic controls
throughout the whole southern Peregian Beach area to ensure that one waying of the network would
not have adverse effects on vehicle speeding, pedestrian safety and convenience of movement, as
well as broad community consultation to understand if there is further support for the proposals
outside of the group who made the submission. The significance of these changes are outside the
scope of the current project.

Other aspects of the submission can be investigated further and incorporated into the project where
possible, including increasing parking yield and managing bike speeds on footpath areas. These
have been accommodated in the recommended design changes.

Community-led Facebook Poll Submission (Attachment 5)
A community led Facebook poll is included at Attachment 5. The poll reflected a divided community
response, highlighting concerns over tree removal, parking, and increased bike traffic, alongside
support for traffic calming and maintaining neighbourhood character.

SCBUG, ZEN & Other Letters of Support (Attachment 6)
The Sunshine Coast Bicycle User Group (SCBUG) and Zero Emissions Noosa (ZEN) made
submissions supporting the project, citing alignment with strategic transport objectives and the
promotion of active travel safety and have been included at Attachment 6. In addition, 4 other
individual resident submissions supporting the project were received.

One on One Meetings (Attachment 7)
In addition, one on one meetings were undertaken with various residents and stakeholders, including
Peregian Beach Residents Against Active Streets. Meeting notes are included at Attachment 7.

Summary of Community Engagement
Community feedback on the Peregian Beach Active Street Project was mixed. Many residents
supported the project’s goals of improving safety, calming traffic and strengthening walking and
cycling connections. However, others expressed concerns about parking impacts, potential traffic
displacement, increased bike activity and associated safety issues, as well as changes to
neighbourhood character. Some residents also questioned how the new road design concept would
function in practice and what it would mean for day-to-day property access and vehicle
manoeuvrability.

Overall, engagement confirms that while there is on balance strategic and safety-based support for
the project’s intent, particularly in regard to improved vehicle safety and the need for a shared path,
careful design refinement and targeted responses to property access, parking, localised safety

Page 10

GENERAL COMMITTEE MEETING                                                                9 JUNE 2026


concerns as well as ongoing education and enforcement remain critical to achieving community
confidence.

This feedback has informed targeted refinements to the design, where possible, helping to address
key issues while preserving the project’s overarching aim of creating a safer, more accessible active
transport corridor for Peregian Beach.

5. Design changes arising from Community Engagement
The following design changes are proposed arising from community engagement

Proposed Design Change                              Rationale
                                                    Traffic engineering advice recommended that
                                                    consideration be given to the installation of local
                                                    area traffic management measures, such as
                                                    traffic calming devices at appropriate locations
Improved Local Area Traffic Management              on Oriole Avenue. The project team committed
(LATM) measures on surrounding streets to           to monitoring traffic in Oriole Avenue following
improve vehicle speed and safety                    the implementation of the Active St however, the
                                                    significant community concern raised during the
                                                    consultation period suggests a more immediate
                                                    implementation of traffic control devices is
                                                    supported.
                                                  Whilst the project would result in a net loss of
Investigation into increasing formalised parking parking in the study area, the traffic advice
yield across the Peregian Beach South area        received indicated that the available parking
including within Victory Park and along Lorikeet provision is expected to accommodate the
Drive. Ongoing investigations include, but are    expected maximum parking demand
not limited to: one way circulation through       experienced in the study area of 191 vehicles.
Victory Park; angled parking within Victory Park, Notwithstanding the traffic advice, 'parking
parallel parking on Lorikeet Drive adjacent high impacts' was identified as one of the key themes
density residential zone and formalised parking through the consultation period. Further
at the eastern end of Pitta St                    investigations seek to reduce this impact as
                                                  much as possible.
Investigation into a softer colour palette and/or a
reduction in perceived over development to
                                                    Community feedback indicated a strong desire to
lesser impact, village scale raised intersections,
                                                    preserve village character and avoid over
priority crossings, chicanes, speed bumps and
                                                    development.
overrun areas where possible within statutory
traffic requirements.
Widening of the existing boardwalk through
Lorikeet Park and maintenance of the current  The local bush care group originally constructed
alignment as well as inclusion of speed       the existing timber structure including
management devices to control bike speeds on surrounding landscaping. They have expressed
approach to shared path and boardwalk through a preference for its retention.
Lorikeet Park.
Improvements to Victory Park to least impactful     Community feedback has highlighted concerns
carparking layout but including no-parking zone     with the proposed formalisation at Victory Park,
in front of the two beach entrances, provision of   including limited capacity for longer vehicles, the
limited long vehicle parking bays and of end-of-    need to maintain clear access to beach entry
trip facilities such as improved water points and   points, and the importance of providing suitable
bike racks                                          facilities for active transport users.

Page 11

GENERAL COMMITTEE MEETING                                                              9 JUNE 2026


                                                   Community feedback has been received
Inclusion of additional street tree planting       recommending additional street tree planting to
                                                   provide shade along the proposed pathway.
                                                   Resident concerns regarding potential misuse of
Investigation of additional signage for user       the pathway including unsafe e-bike speeds
behaviour at key entry locations and nodes         have informed the inclusion of additional user
                                                   behaviour signage in the design
                                                   The inclusion of a pedestrian crossing at Pitta
Retain vehicle turning at the southern end of
                                                   Street may compromise existing vehicle
Lorikeet Drive, currently provided at the
                                                   movements and the design requires further
intersection of Pitta Street and Lorikeet Drive
                                                   refinement
Investigation into land tenure south of Lorikeet   Resident concerns over CPTED Issues with
Park bridge to facilitate the continued use and    proposed new alignment. Community bushcare
upgrade of the pathway on the existing             group advocating for existing alignment that they
alignment.                                         maintain and planted.

A key theme raised throughout the consultation period was the request for continuation of the Active
Street Stage 1 through to the Peregian Beach Village. A recommendation of the report is to support
the CEO to submit available grant funding applications for Stage 2 of the Active Street/Coastal
Pathway extension to commence design and construction as soon as practicably possible.

6. Ongoing Community Engagement

The ultimate success of the Noosa Cycling and Walking Strategy, and the Noosa Transport Strategy
relies on improved active transport to reduce reliance on private motor vehicles, as well as achieve
a mode of movement aligned to the Noosa lifestyle.

There is an ongoing need for community engagement to ensure long term success of the program.
The report recommends the development of an “Active Street” and “Coastal Pathway” awareness
and education campaign across the shire to raise awareness of the safety and active transport
benefits associated with Active Streets and the ultimate delivery of the Noosa Cycling and Walking
Strategy and Noosa Transport Strategy. Some initial considerations for such a program include:

Phase 1 – Broader shire wide awareness campaign to communicate Coastal Pathway corridor
strategy (HPCR), Active Street features and functionality and general walking and cycling safety
through:
   •   Multi-channel approach: social media, short videos, school talks, case studies, etc.
   •   Collaboration with QPS & TMR Stakeholders
 Key messages:
   ▪   Coastal Pathway Vision
   ▪   Missing section identification and proposed projects
   ▪   What is an Active St and how do I use it
   ▪   “Share the path,” “Shoulder check,” “Leave 1.5m”
Phase 2 – Targeted audience for the Peregian Beach Stage 1 Active St to ensure the community
and visitors understand how to safely use the new Active Street:
   •   Short “how to use” video
   •   School education sessions – street etiquette/understand the signs

Page 12

GENERAL COMMITTEE MEETING                                                               9 JUNE 2026


   •   Local ambassadors and community walkthroughs
   •   Targeted social media and local media content
   •   Liaison with enforcement agencies including blitz campaigns


Link to Corporate Plan
Theme No. 2 - Liveability
Liveability encompasses housing, facilities and services, transport, health and wellbeing to enable
an inclusive, connected and vibrant community.
Objective 2.2
Fund and deliver accessible and improved, parks, open spaces, walking and cycle paths and trails,
including greening our paths and cycleways to meet contemporary needs.
Objective 2.4
Advocate and partner with all levels of government for increased funding for connected transport
nodes, transit hubs, including walking, cycling and public transport and explore opportunities through
smart city, smart biosphere and innovation to transform the way we move around and engage in our
community.

Theme No. 5 - Excellence
This theme focuses on customer experience, financial sustainability, innovation and technology,
levels of service, governance, our employees and volunteers, funding streams and asset
management practices.
Objective 5.6
Increase opportunities for meaningful collaborative community engagement which is highly
representative of our community, especially our youth.




Previous Council Consideration
Ordinary Meeting Minutes 16 October 2025
That the petition with 144 signatories submitted by David Phipps, requesting that Council pause,
review and make further consultation on the Active Street Project at Peregian Beach be received
and referred to the Chief Executive Officer to determine appropriate action.

Noosa Transport Strategy 2017–2027
Council previously adopted the Noosa Transport Strategy, which establishes priorities for safe,
connected walking and cycling networks and identifies the need for high-quality active transport
infrastructure along coastal corridor.

Ordinary Meeting Minutes 15 June 2017
That Council note the report by the Project Officer to the Services & Organisation Committee Meeting
dated 6 June 2017, and: A. Adopt the Transport Strategy 2017-2027, provided at Attachment 1 to
the report and authorise the CEO to make minor changes as necessary; B. Adopt the amended
Transport Policy provided at Attachment 2 to the report; and C. Request the Chief Executive Officer
to report to a future Council meeting with an Implementation Plan for the Transport Strategy and
Transport Policy to ensure that tangible actions can be undertaken in both the short and medium
term following the adoption of the Transport Strategy and Transport Policy.

Noosa Cycling & Walking Strategy 2020–2040 (adopted 2021)
Through the Cycling & Walking Strategy, Council committed to expanding safe walking and cycling
infrastructure, addressing missing links, and prioritising coastal connections. Community
consultation at the time highlighted strong support for safer pedestrian infrastructure in Peregian
Beach.

Page 13

GENERAL COMMITTEE MEETING                                                                    9 JUNE 2026



Ordinary Meeting Minutes 15 July 2021
That Council note the report by the Project Officer to the Services & Organisation Committee Meeting
dated 6 July 2021 and:
A. Note the submissions received during the community consultation on the draft Noosa Cycling &
Walking Strategy and Implementation Plan, provided in Attachment 1 to the report;
B. Adopt the final Noosa Cycling and Walking Strategy and Implementation Plan, provided in
Attachment 2 to the report with the following amendments:
1. On page 38 of the Plan, change the infographic to read: “$1.45m per annum over the next 10-
years estimated to be spent on bike riding and walking infrastructure in Noosa Shire, in addition to
external grant funding”
2. Under Future Projects on page 39, delete the website link to yoursay.noosa.qld.gov.au and
replace with www.noosa.qld.gov.au/cycling-walking-strategy
C. On page 23 of the Plan, change Task 2.3 to read: 2.3 Investigate opportunities to enhance or add
end-of-trip facilities in key centres and tourist hubs. Implement a prioritised program for upgrading of
existing public facilities (eg public toilets with showers) and the construction of new end-of-trip
facilities, including electric charging stations and lockers as well as surfboard racks at designated
beachside locations (with the latter being considered as a short term priority issue). Investigate
opportunities to partner or incentivise private sector to develop end-of-trip facilities for their workforce
at key locations.

Ordinary Meeting Minutes 19 December 2019
That Council note the report by the Infrastructure Planning, Design and Delivery Manager to the
Services & Organisation Committee Meeting dated 10 December 2019 and appoint the following
three Councillors, Cr Wellington, Cr Stockwell and Cr Wilkie as members of Noosa Cycling & Walking
Strategy and Highest Priority Cycling Corridors – Project Control Group (PCG).

Ordinary Meeting Minutes 20 February 2020
PETITION: REQUEST COUNCIL TO IMPROVE THE SAFETY AND AMENITY OF PITTA STREET,
PEREGIAN BEACH
That the petition tabled by Cr Wellington requesting that Council improve the safety and amenity of
Pitta Street, Peregian Beach with regards to parking and pedestrian access be received and referred
to the Chief Executive Officer to determine appropriate action.


Finance
The project is 100% Grant funded through the South East Queensland Livability Fund and the Active
Transport Fund.
Current project budget breakdown:
Funding Mechanism24/25FY             25/26FY             26/27FY            Total
SEQ Liveability         $80,120      $516,548            $283,332           $880,000
ATF                     $0           $501,668            $283,332           $785,000
Noosa Council           $0           $0                  $0                 $0
Total                   $80,120      $1,018,215          $566,665           $1,665,000

As the ATF grant is for construction only funding, matching the SEQ Liveability contribution, there
are incentives to keep non-construction associated costs to a minimum.

At the time of drafting this report, additional costs arising from additional community engagement
and project scope changes for Stage 1 have not been reconciled and will require further
consideration at Council's Capital Works Executive. It is noted that proposed design changes have
been scoped as reasonable considerations. There may be an opportunity for the construction

Page 14

GENERAL COMMITTEE MEETING                                                                 9 JUNE 2026


components of this work to be part funded through the ATF grant. The project team will continue to
pursue this opportunity.

Recommendations E and F, if supported, will require further consideration as part of Councils
budgetary processes, as well as profiling for grant opportunities.


Risk & Opportunities
1. Base Case Risk

   Project timeline not meeting the funding deadline resulting in exposure of Council to the part/full
   project cost and needing to fund this from Council reserves

          a. Triggers:
               i.    Delay in commencement of construction works
               ii. Inability to deliver the approved scope due to delays during construction
               iii. Repairs to existing infrastructure prior to project commencement


          b. Drivers:
               i.    Additional community engagement absorbing programme float and budget
                     contingency
               ii. Construction period being pushed into wet season


           c. Mitigations:
                i.   Seek time extension: SEQ Liveability Fund
                ii. Seek time extension: Active Transport Funding (ATF)
                iii. Procurement: Undertake concurrently with engagement activities to ensure a
                     quick release of tender package to the market.
                iv. Approval: Recommending contract award direct through CEO to avoid time
                    delays with Council meetings.



2. Base Case Opportunities
   a. Existing infrastructure: The project provides the opportunity to address inadequacy and
      requirement for emergent works to repair storm water assets prior to/during project
      implementation. Further project timeline delays and cost impacts.
   b. Leverage funding structure: As the ATF grant is for construction only funding, matching the
      SEQ Liveability contribution. The potential exit to expand the scope of works using council
      reserves, matched by the ATF grant, to address emergent and repair works.




3. Scenario Analysis

The following table further details alternative scenarios and the differentiated risks anticipated.

Page 15

GENERAL COMMITTEE MEETING                                                            9 JUNE 2026


Scenario                        Description                      Likely Outcome
Base Case                       Current Scope, Programme,        Programme float consumed,
                                Budget/funding - no mitigation   project budget contingency
                                                                 consumed, likely to miss funding
                                                                 deadlines resulting in financial
                                                                 exposure to Council.
                                                                 Reputational damage
                                                                 associated with project
                                                                 continuation in spite of
                                                                 immediate resident resistance.
Adjust as per recommendations Implement mitigations, actively Re-instates project float, enable
                              enhance opportunities           more time to close out
                                                              community interactions,
                                                              minimise Council exposure to
                                                              project costs, maintain
                                                              opportunity to leverage funding
                                                              structure to deliver more at
                                                              lower cost to council, and
                                                              reduces reputation damage risk
                                                              by including community
                                                              requests and/or suggestions into
                                                              the project where possible.
Further recommendations           Additional Community            Project will need to be fully
outside of those drafted by staff Consultation and or significant funded by Council.
                                  change to planning and design
                                                                  Alternative design treatments
                                  approach
                                                                  will likely be more expensive
                                                                  than the currently proposed
                                                                  project.
                                                                 Delays to delivery of walking
                                                                 and cycling infrastructure.
Halt project                    Stop working on design and       Council will need to fund works
                                cancel planned construction      to date at an approximate value
                                works.                           of $150k.
                                                                 May damage relationships with
                                                                 funding bodies and potentially
                                                                 limit further funding
                                                                 opportunities.
                                                                 Reputational damage for not
                                                                 following through with Walking
                                                                 and Cycling Strategy objectives
                                                                 and negative impact on future
                                                                 projects proposals across the
                                                                 shire.
                                                                 Loss of funding for "practical"
                                                                 components of the projects such
                                                                 as construction of shared
                                                                 pathway and rectification of
                                                                 stormwater infrastructure.
                                                                 Delays to delivery of walking
                                                                 and cycling infrastructure.

Page 16

GENERAL COMMITTEE MEETING                                                                  9 JUNE 2026



Human Rights
Human Rights Compatibility Statement
In developing this Report, the subject matter has been considered in accordance with the
requirements of the Queensland Human Rights Act 2019. It is considered that the subject matter
does not conflict with any human rights and supports a human rights approach to decision making
by Council. Council representatives will endeavour to act and make decisions under this report in a
manner that is compatible with human rights. This report should be read in conjunction with
Council’s Human Rights Policy.


Consultation
External Consultation - Community & Stakeholder
Targeted community engagement throughout the concept and detailed design stages, focusing on
residents of South Peregian as well as key community and stakeholder groups as detailed in the
body of the report.
Internal Consultation
Departments consulted:
     Office of the CEO, Mayor &         Community Services               Corporate Services
             Councillors
 x    Mayor & Councillors             Director                        Director
 x    Chief Executive Officer         Community Development           Financial Services
 x    Executive Officers              Sport & Active Lifestyles       Fleet
 x    Community Engagement            Arts & Culture                  Revenue Services
      People & Culture                Community Connection            ICT
      Governance                      Customer Experience             Procurement

                                                                      Commercial Property

      Strategy & Environment          Development & Regulation         Infrastructure Services
      Director                        Director                    x   Director
      Strategy & Sustainability       Development Assessment      x   Infrastructure Planning, Design
                                                                      and Delivery
      Economic Development        &   Local Laws                  x   Civil and Asset operations
      Destination Management
      Environmental Services          Environmental Health        x   Waste
      Innovation & Digital Hub        Building & Plumbing             Building & Facilities
                                      Property / Permits              Disaster Management

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.