PEREGIAN BEACH ACTIVE STREET - STAGE 1 PROGRESS UPDATE AND NEXT STEPS (Deferred from the Ordinary Meeting dated 19 March 2026 - Item 12.2) · Report
GENERAL COMMITTEE MEETING 9 JUNE 2026
Traffic Access, Property Access & Displacement
• Concerns about vehicles diverting to neighbouring streets, including Oriole Avenue
• Desire for mitigation measures to reduce rat-running and maintain local access
• Difficulty accessing properties with boats and trailers (including 7m trailers)
• Concerns about reversing movements near traffic calming devices and U-turn maneuvers
• Requests to widen driveways or adjust kerb clearances where required
Safety, Speed & E-Bikes
• Broad support for slower traffic and a 30 km/h speed environment, particularly where paired
with traffic calming
• Concerns about interactions between fast-moving e-bikes, pedestrians and vehicles
• Vehicles driving in bike lanes and through roundabouts
• Preference for clearly marked pedestrian crossings (e.g. zebra crossings) or higher-contrast
shared zones
• Requests for education and enforcement to support compliance
Vegetation, Drainage & Neighbourhood Character
• Strong preference to retain mature trees, including pandanus
• Desire to minimise visual and environmental impacts
• Concerns about stormwater runoff and drainage near driveways
• Noise concerns associated with overrun areas (described as rumble strips) and raised
treatments and increased cyclist use
Design Alternatives & Route Considerations
• Some residents suggested relocating cycling infrastructure to David Low Way or adjusting
pathway alignment (including the western side).
• Requests for wider pathways (suitable for two cyclists side-by-side)
• Desire to extend pathway connections fully to the village
• CPTED issues associated with the boardwalk and path diversion at Lorikeet Park
Other Key Feedback
• Support for stormwater upgrades and road repairs
• Requests for consistent pathway connections rather than partial sections
• Mixed views on speed reductions, with stronger support where clearly linked to improved
safety outcomes
• A small number of submissions expressing full objection to the project in addition to the
petitions listed below
Pop Up Display Boards (Attachment 1)
The collated post it notes from the pop-up display boards and the typed summary notes is included
as Attachment 1 to the Report.
Customer Requests (Attachment 2)
During the engagement period, Council received 37 formal customer enquiries relating to the project.
These enquiries primarily concerned parking impacts, traffic displacement, proposed speed limit
changes, and requests to reconsider corridor alignment and are included at Attachment 2 to the
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original