                                                                                                                                                                                                                                                          OP WORKS
                                                                                                                                                                                                                                                       NOT FOR CONSTRUCTION



RESIDENTIAL DUPLEX DEVELOPMENT
6 WYANDRA STREET, NOOSA HEADS, QLD 4567
Lot 40 RP 139776
CIVIL WORKS
GENERAL NOTES:
THE FOLLOWING INSPECTIONS MUST BE COMPLETED BY RECOR ENGINEERS BEFORE                 9.    CONTRACTOR TO UNDERTAKE ALL WORKS IN ACCORDANCE WITH ALL WORKPLACE
ENGINEERING CERTIFICATION WILL BE ISSUED. THE CONTRACTOR IS TO PROVIDE A MINIMUM            HEALTH AND SAFETY REQUIREMENTS.
OF 72 HOURS NOTICE TO RECOR FOR REQUIRED INSPECTIONS. SHOULD THE CONTRACTOR FAIL      10.   WHERE ANY EXCAVATION OR CONSTRUCTION WORKS ARE TO BE IN CLOSE PROXIMITY TO
TO REQUEST AN INSPECTION, THE CONTRACTOR WILL BE RESPONSIBLE FOR ALL COSTS TO               NEIGHBOURING LOT BOUNDARIES OR INFRASTRUCTURE, CONTRACTOR TO ALLOW IN
ALLOW FOR THE WORKS TO BE INSPECTED TO THE SATISFACTION OF RECOR. ANY                       SCOPE OF WORKS TO PROVIDE ALL MEASURES NECESSARY TO ENSURE THE INTEGRITY
INSPECTIONS THAT FAIL ARE TO BE RE-INSPECTED WITH ALL REINSPECTION COSTS TO BE PAID         OF EXISTING BOUNDARIES AND INFRASTRUCTURE. THIS MAY INCLUDE THE USE OF LOW
BY THE CONTRACTOR.                                                                          VIBRATION EQUIPMENT, TRENCH SHORING ETC AS REQUIRED.
a.   PRESTART                                                                         11. PRIOR TO THE CONTRACTOR COMMENCING ANY WORKS DETAILED ON THESE DRAWINGS,
b.   EARTHWORKS - FINAL STRIPPING OF TOPSOIL, INSTALLATION OF SEDIMENT AND EROSION        THE CONTRACTOR IS TO NOTIFY RECOR AND RECEIVE WRITTEN CONFIRMATION THAT
     CONTROL MEASURES UNSUITABLE GROUND                                                   WORKS CAN COMMENCE.
c.   SIDE AND CUT OFF DRAINS                                                          12.   CONTRACTOR TO PROVIDE AS CONSTRUCTED DRAWINGS FOR ALL CONSTRUCTED WORKS
                                                                                            IN ACCORDANCE WITH LOCAL GOVERNMENT REQUIREMENTS. UNLESS OTHERWISE
d.   STORMWATER PIPE LAID ON BEDDING PRIOR TO BACKFILL                                      ADVISED BY RECOR CONTRACTOR TO NOTE COUNCILS ADAC REQUIREMENTS.
e.   STORMWATER TRENCH BACKFILLED PRIOR TO PAVEMENT PLACEMENT                         13.   CONTRACTOR TO UNDERTAKE ALL WORKS IN ACCORDANCE WITH RELEVANT APPROVALS.
f.   STORMWATER STRUCTURE BASE SLABS                                                  14.   CONTRACTOR TO ALLOW TO LIASE/CO-ORDINATE WITH ELECTRICAL, LANDSCAPE AND
g.   SEWER RETICULATION                                                                     OTHER SERVICE CONTRACTORS THROUGHOUT CIVIL CONSTRUCTION.

h.   WATER RETICULATION                                                               15.   CONTRACTOR TO ORGANISE ALL DEMOLITION PERMITS PRIOR DEMOLITION WORKS
                                                                                            COMMENCING ON SITE.
i.   PAVEMENT SUBGRADE
                                                                                      16.   CONTRACTOR TO ALLOW TO DEMOLISH ALL EXISTING STRUCTURES, ROADS AND
j.   PAVEMENT REINFORCING                                                                   SERVICES WITHIN LIMIT OF WORKS AND REMOVE FROM SITE U.N.O.
k.   PAVEMENT PRIOR TO SEALING (PRESEAL)                                              17.   CONTRACTOR TO UNDERTAKE DILAPIDATION REPORT FOR ADJOINING PROPERTIES AND
l.   RETAINING WALL FOOTING REINFORCING                                                     COUNCIL ROADS AND VERGES PRIOR TO COMMENCEMENT OF ANY WORKS ON SITE.

m.   RETAINING WALL BLOCKWORK PRIOR TO CORE FILL                                      18.   CONTRACTOR TO CLEAR AND GRUB ALL VEGETATION ON SITE AS IDENTIFIED IN THE
                                                                                            APPROVED VEGETATION MANAGEMENT PLAN. CONTRACTOR TO ENSURE ALL TREE ROOTS
n.   STEEL REINFORCEMENT OF CONCRETE STRUCTURES                                             AND STUMPS ARE COMPLETELY REMOVED AND BACKFILLED TO LEVEL 1 SUPERVISION.
o.   PRACTICAL COMPLETION                                                                   CONTRACTOR TO ALLOW TO MULCH ALL CLEARED VEGETATION AND STOCKPILE ON SITE
                                                                                            OR REMOVE FROM SITE AS DIRECTED.
p.   ON MAINTENANCE
                                                                                      19. DRAWINGS TO BE READ IN CONJUNCTION WITH THE FOLLOWING
q.   OFF MAINTENANCE                                                                      CONSULTANTS/CONTRACTORS DRAWINGS:
r.   ANY OTHER INSPECTION AS SPECIFIED BY LOCAL COUNCIL (REFER DEVELOPMENT                        SURVEYOR: NOOSA COOLOOLA LAND SURVEYORS PTY LTD
     APPROVAL)
                                                                                                   ARCHITECT: BLACKWOOD ARCHITECTURE & DESIGN
s.   ANY OTHER INSPECTION AS REQUIRED BY UNITY WATER AND WHERE RELEVANT TO THEIR
     CERTIFICATION SCHEME                                                                         HYDRAULICS: TBA
                                                                                                  STRUCTURAL: RECOR
                                                                                                                                                                                                              LOCALITY PLAN
GENERAL NOTES                                                                                     LANDSCAPE: BLACKWOOD ARCHITECTURE & DESIGN
                                                                                                                                                                                                              NOT TO SCALE
1.   ALL DIMENSIONS SHOWN ARE IN METERS UNLESS OTHERWISE SHOWN.                       20. CONTRACTOR TO PREPARE AND HAVE APPROVED BY RELEVANT AUTHORITY: ROAD
                                                                                          OPENING PERMIT AND TRAFFIC MANAGEMENT PLAN FOR ALL WORKS WITHIN COUNCIL
2.   ALL SETOUT ON SITE IS THE SOLE RESPONSIBILITY OF THE CONTRACTOR. CONTRACTOR          ROAD RESERVES. CONTRACTOR TO ALLOW FOR ALL COSTS ASSOCIATED WITH
     TO ALLOW FOR ALL MEANS NECESSARY TO ACCURATELY SETOUT THE WORKS.                     IMPLEMENTATION OF THE TMP.                                                                                                                                                                              13/07/2022

3.   ALL WORKS TO BE CONSTRUCTED IN ACCORDANCE WITH PROJECT SPECIFICATIONS AND        21. ALL WORKS TO BE COMPLETED IN ACCORDANCE WITH ALL LOCAL AUTHORITY APPROVALS                                                                                                                              EA ID: 2557785
     WHERE FURTHER DETAILS ARE REQUIRED THE CONTRACTOR SHALL REFER TO NOOSA               RECEIVED FOR THE PROJECT                                                                                                                                                                                 RPEQ: 26443

     SHIRE COUNCIL DEVELOPMENT GUIDELINES, LOCAL WATER AUTHORITY GUIDELINES,
     ASSOCIATED STANDARD DRAWINGS AND SPECIFICATIONS U.N.O.                           22. CONTRACTOR TO UNDERTAKE ALL WORKS IN ACCORDANCE WITH OPW APPROVALS BY                                                                                           DO NOT SCALE, IF IN DOUBT ASK!
                                                                                          COUNCIL.
4.   SHOULD ANY OF THE CONSTRUCTED WORKS BE CONSTRUCTED OUTSIDE OF THE
     TOLERANCES SPECIFIED WITHIN THE PROJECT SPECIFICATION AND LOCAL AUTHORITY        23. NO WORKS ARE TO BE UNDERTAKEN ON LAND OUTSIDE OF THE SITE BOUNDARY WITHOUT
     REQUIREMENTS, THE CONTRACTOR WILL RECTIFY AT THEIR COST INCLUSIVE OF ANY             FORMAL APPROVAL BY THE OWNER/CUSTODIAN OF THAT LAND INCLUDING BUT NOT
     ADDITIONAL COSTS INCURRED BY RECOR.                                                  LIMITED TO PRIVATE PROPERTY, ROAD RESERVE, PARKS/OPENSPACE, EASEMENTS.

5.   EXISTING SERVICES HAVE BEEN PLOTTED FROM SUPPLIED DATA AND AS SUCH THEIR         24. THE CONTRACTOR SHALL HAVE AN APPROVED SET OF CONSTRUCTION DRAWINGS AND
     ACCURACY CANNOT BE GUARANTEED. NO RESPONSIBILITY IS TAKEN BY RECOR OR THE            APPROVALS ON SITE AT ALL TIMES.
     PRINCIPAL FOR THE ACCURACY AND COMPLETENESS OF THIS INFORMATION. IT IS THE       25. ALL WATER AND SEWER RETICULATION WORKS TO BE CONSTRUCTED IN ACCORDANCE
     RESPONSIBILITY OF THE CONTRACTOR TO ACCURATELY ESTABLISH THE LOCATION AND            WITH THE SEQ WATER SUPPLY AND SEWERAGE DESIGN AND CONSTRUCTION CODE (2013).                                                                     C 11/07/22 ISSUE FOR OPW                                           BP        NW
     LEVEL OF ALL EXISTING SERVICES PRIOR THE COMMENCEMENT OF ANY WORKS. ANY                                                                                                                                                              B       24/06/22 UPDATE ISSUE FOR MCU                              BP        NW
     DISCREPANCIES SHALL BE REPORTED TO THE SUPERINTENDENT. CONTRACTOR TO                                                                                                                                                                 A 30/03/22 ISSUE FOR MCU                                           BP        NW
     LOCATE AND PROTECT SERVICES AS REQUIRED DURING PROPOSED WORKS.                                                                                                                                                                      Rev Date             Description                                    By Chk
6.   THE CONTRACTOR IS TO CHECK THROUGH LOCATING, POTHOLING AND SURVEY ALL
     CRITICAL CONNECTION POINTS FOR ALL CIVIL WORKS SHOWN ON THE DRAWINGS
     INCLUDING ANY POTENTIAL EXISTING SERVICES CLASHES PRIOR TO COMMENCEMENT OF                                                                                               DRAWING SCHEDULE
     CIVIL WORKS. CONTRACTOR TO IMMEDIATELY REPORT ANY DISCREPANCIES TO RECOR
     AND AWAIT FORMAL DIRECTION PRIOR TO COMMENCING CIVIL WORKS.
                                                                                                                DRAWING NUMBER                                                      DRAWING TITLE                             REVISION
7.   ON COMPLETION OF SERVICES INSTALLATION, ALL DISTURBED AREAS SHALL BE                                             C01                                                  COVER SHEET AND LOCALITY PLAN                         C
     RESTORED TO ORIGINAL LEVEL, INCLUDING KERBS, FOOTPATHS, CONCRETE AREAS,
                                                                                                                      C02                                                    EXISTING SITE SERVICES PLAN                         C          [email protected]
     GRAVEL AREAS, GRASSED AREAS AND ROAD PAVEMENTS.
                                                                                                                                                                                                                                            37 MARY ST NOOSAVILLE, QLD
8.   CONTRACTOR SHALL BE RESPONSIBLE FOR REPAIR OF ANY DAMAGE TO                                                      C10                                                 EROSION & SEDIMENT CONTROL PLAN                        C          07 5211 1003
     AUTHORITY/COUNCIL'S INFRASTRUCTURE. SUCH REPAIR OR REINSTATEMENT TO BE
     CARRIED OUT IMMEDIATELY TO THE SATISFACTION OF INFRASTRUCTURE
                                                                                                                      C11                                                EROSION & SEDIMENT CONTROL DETAILS                      C       Client

                                                                                                                                                                                                                                         FORDE PROPERTY
     OWNER/MANAGER / AUTHORITY/COUNCIL.                                                                               C20                                                      BULK EARTHWORKS PLAN                              C       Project Name
                                                                                                                                                                                                                                         RESIDENTIAL DUPLEX DEVELOPMENT
                                                                                                                      C21                                                    BULK EARTHWORK SECTIONS                             C       6 WYANDRA STREET
                                                                                                                      C30                                                 ROADS AND DRAINAGE LAYOUT PLAN                         C       NOOSA HEADS

                                                                                                                      C32                                                    DRIVEWAY SECTIONS (1 OF 2)                          C        Title
                                                                                                                                                                                                                                         COVER SHEET AND LOCALITY PLAN
                                                                                                                      C33                                                    DRIVEWAY SECTIONS (2 OF 2)                          C
                                                                                                                      C34                                                       STORMWATER SECTION                               C
                                                                                                                      C35                                                   STORMWATER CATCHMENT PLAN                            C
                                                                                                                                                                                                                                         Project No.                Discipline           Status
                                                                                                                                                                                                                                                   20220078                      CIVIL                OPW
                                                                                                                                                                                                                                         Designed By                Drawn By             Scale
                                                                                                                                                                                                                                                                                                                        (at
                                                                                                                                                                                                                                                        BRP                      BRP                  1:100            A1)

                                                                                                                                                                                                                                          Drawing No.                                                       Revision

                                                                                                                                                                                                                                                  C01                                                              C
Log in to download the original file

20220078 Wyandra St Civil OPW.pdf · 2.3 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.