Negotiated Decision Notice 131998 981211 5

of 20

Page text shows just the words. Original shows the document exactly as it was published.

                      The security will be returned upon satisfactory performance of all relevant conditions of this
                      approval and any other related development permit for operational, less any costs incurred
                      by Council in ensuring compliance with these conditions of for any additional inspections
                      incurred for substandard work or works undertaken not in accordance with the is permit.
               37.    The requirements of ENERGEX, OPTUS and TELSTRA shall be satisfied in relation to any
                      existing services which currently traverse the development site. Written confirmation by the
                      relevant authorities that satisfactory arrangements have been made to formalise any existing
                      informal services shall be submitted prior to commencement of the use.
               38.    All stormwater drainage shall be designed in accordance with the provision of the 1987
                      Australian Rainfall and Runoff (A.R.R.), Australian Standard AS3500.3.2-1988 ‘Stormwater
                      Drainage-Acceptable Solutions’ and Noosa Council Standards. Pipe and channel drainage
                      systems shall be designed to cater for 10 (ten) year Average Recurrence Interval design
                      storm for Kabi Road.
               39.    The water quality of any water originating from and leaving the site shall not vary by more
                      than 5% form the baseline data for water currently leaving the site measured in the north
                      eastern area of the development site. Monitoring of water quality in the dams shall be
                      undertaken monthly during construction and annually during operation.
               40.    A water quality plan be included in the EMP and once approved, shall be complied with at all
                      times.
               41.    Stormwater drainage shall include measures to protect proposed allotments from run-off from
                      surrounding land. The design shall also address controls for gross pollutants, nutrient runoff,
                      oil and grease, and silt and sediment.
                      Underground stormwater systems shall be designed in accordance with Noosa Council’s
                      Engineering Design Standards, and shall also be connected, where possible to Council’s
                      existing drainage systems.
                      An easement of minimum with 4.0 metres shall be granted in favour or Council over any
                      stormwater pipes that traverse private property.
                      Designs that concentrate stormwater onto adjoining land shall require separate form
                      approval from the owner of the land or relevant Government Authority. Such approval shall
                      be submitted with the design in conjunction with an application for a Development Permit for
                      Operational Works.
               Town Planning
               42.    Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development. The approved plans are numbered No. G177.DCP.02
                      Figure 3 prepared by GNP Golf Design Pty Ltd and dated May 1998 and as may be amended
                      by these conditions.
               43.    The approval of the Sport and Recreation (golf course) component of the Integrated
                      Permaculture Designed Organic Orchard and Golf Course Complex, is only valid for as long
                      as the Agriculture use (Permaculture) is undertaken on this site. The Sport and Recreation
                      (Golf Course) use, and ancillary uses, lapses if the Permaculture use ceases on the site.
               44.    Deleted.
               45.    The Regional Manager, Cultural Heritage Program, Southeast Region, Environment
                      Protection Agency should be contacted immediately on (07) 3325 8425 should any cultural
                      artifacts be exposed during construction.
               46.    The proponent should give some consideration to rehabilitating the existing and proposed
                      waterway features, to a more natural state, by the use of native fauna and flora. The
                      Southern Fisheries Centre (Mr Bob Simpson, (07) 3817 9590 may be contacted for advice
                      on stocking native fish.




                                                                                                       Page 6 of 20
Document Set ID: 23699332
Version: 3, Version Date: 22/04/2025
Log in to download the original file

Negotiated Decision Notice 131998 981211 5.pdf · 222 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.